Index
Note: Page numbers with “f” denote figures; “t” tables; and “b” boxes.
A
Acceptance certificate,
47
Accuracy of estimates,
61
Actual cost of work performed (ACWP),
291f,
293
Adjudication nominating body (ANB),
396
Advance payments bond,
319
actual drywall framing around,
510f
architects rendering of,
513f
drywall assembly ‘spool sheet’,
512f
drywall framing model around,
511f
Dynamic Detailing implementation,
511–513
rebar using multiple custom components,
513–514
seismic design requirements,
510–511
system rendering through tower,
513f
Analysis & Design (A&D),
508
Analytical estimating,
61
Annual order discount,
335
Approvals of changes,
99f
Approved tender list
See Tender list
Authority of project manager,
8–9
B
Bank bonds (on demand bonds),
317
Bank guarantee draft,
318f
Barriers to communication,
366,
368
Basic principles (networks),
209
Best-of-breed systems,
521
Bid (enquiry) documents,
304
Boiler network (AoA),
140f
Bonds (performance, advance payment, retention),
316–321
Bottom up estimates,
53,
59
Budget at completion (BAC),
291f
Budgeted cost of work performed (BCWP),
291f,
293
Budgeted cost of work scheduled (BCWS),
291f,
293
Building information Modelling (BIM),
503,
505
enabling multidimensional models,
506
Information Modelling,
505
linking systems through open. NET interfaces,
509
principle industry transfer standards,
519
structural steelwork industry,
505
3D modelling technology,
505
UK Government Recommendations,
506–507
Building Research Station,
61
buildingSMART organization,
521
Bulk purchase discount,
335
C
Cast-in-Place Concrete (CIP Concrete),
510
Cause and effect diagram,
232,
228f
Centrifugal pump manufacture,
226–227
Change management advice form,
99f
CIMsteel Integration Standards (CIS),
520–521
CIMsteel Integration Standards (cis/2),
506
Colliery surface reconstruction,
304
Commercial conditions of contract,
327
Commissioning close out report,
311
Communication barriers,
366
Comparative estimating,
60
Computer numerically controlled machines (CNC machines),
505
Concurrent engineering,
393
Configuration change management,
103
Configuration control,
362
Configuration identification,
103
Configuration management,
103
Configuration planning,
103
Configuration status accounting,
103
Construction Design and Management (CDM) regulations,
351
Construction network,
247f
Context
See Project context
Contract documentation,
308
Contracting organization,
13
Control of configured items,
103
Corporate strategy,
12,
401
Cost bound project,
Cost breakdown structure (CBS),
53,
54f,
478f
Cost performance index (CPI),
258,
291
Cost/benefit analysis,
31–32
Critical path methods (CPM),
105
D
Description of works,
106
Design, build and operate contract,
315–316
Design Web Format (DWF),
519
Discounted cashflow (DCF),
28,
452
Discounts (quantity, early payment),
335
Drawing eXchange Format (DXF),
519
E
Earned value analysis,
489
Enterprise-level database,
486
Environmental pressure groups,
34
Estimated cost at completion (EAC),
291f
Estimated project time (EPT),
291f
Extended life cycle,
48–50
F
Failure mode and effect analysis,
91–94
Final forecast hours,
279
Formal handover of contract documents,
406
Forming, storming, norming, performing, mourning,
373–374
Forms of contract ECC/NEC, ICI, FIDIC, I ChemE,
328–330
Free standing contract,
315
Function point analysis,
62
Functional organization,
41,
43
G
General Computer-Aided Design tools (CAD tools),
504
General conditions of contract,
330
Geographical location,
129
Geographical separation,
367
Globally Unique Identifier (GUID),
505
Guide to Project Management, BS 6079,
290f,
345
H
Hazardous substances,
348
Health and Safety at Work Act,
345
Health and safety file,
353
Health and safety legislation,
352
Herzberg motivational theory,
378–379
High level reporting document,
49
Hornet computer program,
279
Housing Grants, Construction and Regeneration Act 1966,
396
I
Impact/probability matrix,
74,
75f
Industry Foundation Class (IFC),
521
Industry Foundation Class files (IFC files),
506
Information distribution,
361
Information management,
359
Information Modelling,
505
Initial Graphics Exchange Specification (IGES),
520
Insurance company bonds,
316
Integrated computer system,
293–294
Integrated Project Delivery (IPD),
510
Integration of material costs,
264
International Standardisation Organisation (ISO),
520
Investment breakdown,
297f
Ishikawa (fish bone) diagram,
94
J
K
Key Performance Indicators (KPI),
38–39
L
BIM strategy for efficiency,
517
bowl terraced seating model,
518f
general arrangement drawing,
517f
steel-framed structure,
516
Steelwork arrangement detail,
518f
Life Cycles
Life cycle diagram,
51,
342
Linking systems through open. NET interfaces,
509
Lubrication schedules,
406
M
Make good roads and fences,
406
Man hour/time curve,
276f
Management information systems (MIS),
509
Manufacturing bar chart activities,
203f
Manufacturing bar chart format,
195–197
Matrix organization,
41–42
Max. and min number of bidders,
302
Mechanical, electrical, and piping (MEP),
503–504
actual drywall framing around,
510f
drywall framing model around,
511f
Methods and procedures,
68–69
Methods of measurement,
287t
Monte Carlo simulation,
76
Multi-project system,
490
N
National Museum of Qatar,
514,
514f
challenges for design,
515
structural modelling,
515
Negative stakeholders,
34
Negotiation agreement,
389
Negotiation bargaining,
389
Negotiation introductions,
388
Negotiation outcomes,
390f
Negotiation planning,
388
Non construction networks,
221
O
Office of Statewide Healthcare Planning and Development (OSHPD),
510–511
Operating instructions,
406
earned value analysis,
489
multi-project system,
490
through project life cycle,
491
work breakdown structure,
487
Organization breakdown structure,
54,
452,
478f
Organization structures,
41
Overall project completion,
157–158
P
Parent company guarantees,
305
Pareto analysis (80/20 rule),
94–96
% complete,
202,
256,
258,
260,
263,
265,
284f,
286,
288,
455
Performance bound project,
Performance criteria,
84,
90
Personal Computer (PC),
175
Pharmaceutical factory,
130
Planning,
Portfolio management,
13–14
Portland cement factory,
131
Positive stakeholders,
34
Pre-qualification questionnaire,
299
Private Finance Initiative (PFI),
315
Project management
OGC,
Project management software evolution
early project management software packages,
485
enterprise-level database,
486
production of reports,
486
scalable integrated system,
487
simple IT limitations,
485
Project manager
BS 6079,
Project manager’s authority,
Project manager’s responsibility,
Project
charter,
environment
See Project context
investment breakdown,
297f
management,
management and planning,
207
management plan (PMP),
65
manager’s charter
See Project charter
objectives,
office
See Project support office
Prompt payment discount,
335
Protective equipment,
345
Protective materials,
309
Public Private Partnership (PPP),
315
Public sector levies,
315
Pumping installation,
433
Q
Quality/performance criteria,
11
Quality
standard ISO 9000 series,
88t
tools
See Quality control
Quantitative analysis,
71,
75
R
Radio-frequency identification (RFID),
506
Recommendation for future,
410
Request for quotation (RfQ),
304
Requirement management,
22–23
Resource
leveling
See Resource smoothing
management
See Resource loading
Risk
breakdown structure (RBS),
56
log
See Risk register
Role of project manager,
8–9
S
Safety bound project,
4–6
Scalable integrated system,
487
Schedule performance index (SPI),
291,
293,
489
Secondary stakeholders,
33
Sequential numbering,
112
Shipping restrictions/problems,
17,
308
Situational leadership,
383
Small pipeline project,
196f
Smoothing
See Resource smoothing
Soft skills,
Sponsor requirements,
22–23
Stages of completion,
138
Stakeholder management,
33
Stakeholders (direct),
33
Stakeholders (indirect),
33–35
Standard conditions of contract,
329f
Standard for the Exchange of Product Model Data (STEP),
520
Steel Detailing Neutral File format (SDNF format),
520
Structural steelwork industry,
505
Subjective estimating,
59–60
Success/Failure criteria,
316
Surplus material disposal,
474
T
Table of PMP topics in BS 6079,
Technical specification,
331
conveying differences,
514
showing model to site comparisons,
511f
Drywall assembly ‘spool sheet’,
512f
Dynamic Detailing implementation,
511–513
Three point estimating,
159,
490
3D modelling technology,
505
Time, cost, performance/quality criteria,
3f
Time bound project,
Time scaled network,
127f
Total quality management (TQM),
87
Transfer of ownership certificate,
320f
Transmission failures,
367
Types of contract, firm, fixed, target, cost plus, reimbursable,
313
Types of risk
See Risk types
Typical subcontracts,
327
U
UK Government Recommendations,
506,
507
project BIM maturity levels,
507
Universally Unique Identifier (UUID),
505
V
Value analysis,
Value management,
69,
343
W
Worked examples
Z