Chapter 26
Provisions, contingent liabilities and contingent assets

List of examples

Chapter 26
Provisions, contingent liabilities and contingent assets

1 INTRODUCTION

1.1 Background

IAS 37 – Provisions, Contingent Liabilities and Contingent Assets – applies to all provisions, contingent liabilities and contingent assets, except those relating to executory contracts that are not onerous and those provisions covered by another Standard. [IAS 37.1].

For some time the IASB has considered amending IAS 37 and an exposure draft was issued in June 2005. Subsequent deliberation, including round-table meetings held with constituents to discuss their views, resulted in the Board revising its proposals and issuing a second exposure draft in January 2010. However, IAS 37 was not revised. Instead, in 2010, the Board suspended the project to allow it to focus on higher priority projects, and pending completion of its project to revise the Conceptual Framework. The IASB again began discussions on a Provisions, Contingent Liabilities and Contingent Assets research project in 2015. Whilst stakeholders have told the Board that IAS 37 generally works well in practice, problems have been identified with some aspects of the Standard. It is often difficult to determine whether an entity has a liability if an entity has an obligation that has arisen from its past actions but is also dependent on a future action of the entity. Some stakeholders have argued that the principles underlying IFRIC 21 – Levies, an interpretation of IAS 37, are inconsistent with other requirements in IAS 37, and have argued that IFRIC 21 results in information that is not useful to investors. In addition, the measurement requirements in IAS 37 for provisions are not clear on which costs should be included as part of ‘the expenditure required to settle’ an obligation, and do not specify whether the rate used to discount provisions should reflect the risk that the entity may fail to fulfil its liability (i.e. the entity's own credit risk). This leads to diversity in practice in the measurement of provisions. At the time of writing, Board discussions are expected to continue during the second half of 2019, with the aim of deciding whether to undertake a project to amend IAS 37 and, if so, which aspects to consider amending.1

1.2 Interpretations related to the application of IAS 37

The Interpretations Committee has issued a number of pronouncements relating to the application of IAS 37 (although one of them was subsequently withdrawn).

1.2.1 IFRIC 1

IFRIC 1 – Changes in Existing Decommissioning, Restoration and Similar Liabilities – provides guidance on how to account for the effect of changes in the measurement of existing provisions for obligations to dismantle, remove or restore items of property, plant and equipment. This is discussed at 6.3 below.

1.2.2 IFRIC 3

Another issue considered by the Interpretations Committee was how to account for a ‘cap and trade’ emission rights scheme. In December 2004, the Interpretations Committee issued IFRIC 3 – Emission Rights – but this was later withdrawn in June 2005. This interpretation, inter alia, required that as emissions are made, a liability was to be recognised for the obligation to deliver allowances equal to the emissions that had been made by the entity. Such a liability was a provision within the scope of IAS 37, and was to be measured at the present market value of the number of allowances required to cover emissions made up to the end of the reporting period. Accounting for liabilities associated with emissions trading schemes is discussed at 6.5 below.

1.2.3 IFRIC 5

IFRIC 5 – Rights to Interests arising from Decommissioning, Restoration and Environmental Rehabilitation Funds – deals with the accounting by an entity when it participates in a ‘decommissioning fund’, the purpose of which is to segregate assets to fund some or all of the costs of its decommissioning or environmental liabilities for which it has to make a provision under IAS 37. This is discussed at 6.3.3 below.

1.2.4 IFRIC 6

IFRIC 6 – Liabilities arising from Participating in a Specific Market – Waste Electrical and Electronic Equipment – provides guidance on the accounting for liabilities for waste management costs. This clarifies when certain producers of electrical goods will need to recognise a liability for the cost of waste management relating to the decommissioning of waste electrical and electronic equipment (historical waste) supplied to private households. This is discussed at 6.7 below.

1.2.5 IFRIC 21

IFRIC 21 addresses the recognition of a liability to pay a levy imposed by government if that liability is within the scope of IAS 37. It also addresses the accounting for a liability to pay a levy whose timing and amount is certain (see 6.8 below).

Although they are not interpretations of the standard as such, the IAS 37 guidance on non-financial liabilities is also referred to in IFRIC 12 – Service Concession Arrangements (see CHAPTER 25); and IFRIC 14 – IAS 19 – The Limit on a Defined Benefit Asset, Minimum Funding Requirements and their Interaction (see Chapter 35).

1.3 Terms used in this chapter

The following terms are used in this chapter with the meanings specified:

Term Definition
Provision A liability of uncertain timing or amount. [IAS 37.10].
Liability A present obligation of the entity arising from past events, the settlement of which is expected to result in an outflow from the entity of resources embodying economic benefits. [IAS 37.10].
Obligating event An event that creates a legal or constructive obligation that results in an entity having no realistic alternative to settling that obligation. [IAS 37.10].
Legal obligation An obligation that derives from a contract (through its explicit or implicit terms); legislation; or other operation of law. [IAS 37.10].
Constructive obligation An obligation that derives from an entity's actions where:
  1. by an established pattern of past practice, published policies or a sufficiently specific current statement, the entity has indicated to other parties that it will accept certain responsibilities; and
  2. as a result, the entity has created a valid expectation on the part of those other parties that it will discharge those responsibilities. [IAS 37.10].
Contingent liability
  1. a possible obligation that arises from past events and whose existence will be confirmed only by the occurrence or non-occurrence of one or more uncertain future events not wholly within the control of the entity; or
  2. a present obligation that arises from past events but is not recognised because:
    1. it is not probable that an outflow of resources embodying economic benefits will be required to settle the obligation; or
    2. the amount of the obligation cannot be measured with sufficient reliability. [IAS 37.10].
Contingent asset A possible asset that arises from past events and whose existence will be confirmed only by the occurrence or non-occurrence of one or more uncertain future events not wholly within the control of the entity. [IAS 37.10].
Onerous contract A contract in which the unavoidable costs of meeting the obligations under the contract exceed the economic benefits expected to be received under it. [IAS 37.10].
Restructuring A programme that is planned and controlled by management, and materially changes either:
  1. the scope of a business undertaken by an entity; or
  2. the manner in which that business is conducted. [IAS 37.10].
Executory contract A contract under which neither party has performed any of its obligations or both parties have partially performed their obligations to an equal extent. [IAS 37.3].
Term Definition
Levy An outflow of resources embodying economic benefits that is imposed by governments on entities in accordance with legislation (i.e. laws and or regulations), other than:
  1. those outflows of resources that are within the scope of other Standards (such as income taxes that are within the scope of IAS 12); and
  2. fines or other penalties that are imposed for breaches of the legislation. [IFRIC 21.4].
Government Refers to government, government agencies and similar bodies whether local, national or international. [IFRIC 21.4].

2 OBJECTIVE AND SCOPE OF IAS 37

2.1 Objective

The objective of IAS 37 ‘is to ensure that appropriate recognition criteria and measurement bases are applied to provisions, contingent liabilities and contingent assets and that sufficient information is disclosed in the notes to enable users to understand their nature, timing and amount’. [IAS 37 Objective].

2.2 Scope of IAS 37

The standard is required to be applied by all entities in accounting for provisions, contingent liabilities and contingent assets, except those arising from executory contracts (unless the contract is onerous) and those covered by another standard. [IAS 37.1].

The following table lists the specific types of transaction or circumstances referred to in the standard that might give rise to a provision, contingent liability or contingent asset. In some cases, the transaction is identified in IAS 37 only to prohibit recognition of any liability, such as for future operating losses and repairs and maintenance of owned assets (see 5 below). This chapter does not address those items identified below as falling outside the scope of the standard.

Types of transaction or circumstances referred to In scope Out of scope Another standard
Restructuring costs
Environmental penalties or clean-up costs
Decommissioning costs
Product warranties / refunds
Legal claims
Reimbursement rights
Future operating costs (training, relocation, etc.)
Future operating losses
Onerous contracts (including onerous contracts under IFRS 15)
Repairs and maintenance costs
Provisions for depreciation, impairment or doubtful debts IAS 16 / IAS 38 / IAS 36 / IFRS 9
Executory contracts (unless onerous)
Income taxes IAS 12
Leases (unless onerous) IFRS 16
Employee benefits IAS 19
Insurance contracts issued by insurers to policyholders IFRS 4 / IFRS 17
Contingent liabilities acquired in a business combination IFRS 3
Contingent consideration of an acquirer in a business combination IFRS 3
Financial instruments and financial guarantees within the scope of IFRS 9 IFRS 9
Trade payables IFRS 9
Accruals

2.2.1 Items outside the scope of IAS 37

2.2.1.A Executory contracts, except where the contract is onerous

The standard uses the term executory contracts to mean ‘contracts under which neither party has performed any of its obligations, or both parties have partially performed their obligations to an equal extent’. [IAS 37.3]. This means that contracts such as supplier purchase contracts and capital commitments, which would otherwise fall within the scope of the standard, are exempt.

This exemption prevents the statement of financial position from being grossed up for all manner of commitments that an entity has entered into, and in respect of which it is debatable whether (or at what point) such contracts give rise to items that meet the definition of a liability or an asset. In particular, the need for this exemption arises because the liability framework on which this standard is based includes the concept of a constructive obligation (see 3.1.1 below) which, when applied to executory contracts would otherwise give rise to an inordinate number of contingent promises requiring recognition or disclosure.

An executory contract will still require recognition as a provision if the contract becomes onerous. [IAS 37.3]. Onerous contracts are dealt with at 6.2 below.

2.2.1.B Items covered by another standard

Where another standard deals with a specific type of provision, contingent liability or contingent asset, it should be applied instead of IAS 37. Examples given in the standard are:

  • income taxes (dealt with in IAS 12 – Income Taxes – see Chapter 33);
  • leases (dealt with in IFRS 16 – Leases – see Chapter 23). However, IAS 37 applies to any lease that becomes onerous before the commencement date of the lease, as defined in IFRS 16. IAS 37 also applies to onerous short-term leases and onerous leases of low value assets that are accounted for under paragraph 6 of IFRS 16; [IAS 37.5(c)]
  • employee benefits (dealt with in IAS 19 – Employee Benefits – see Chapter 35);
  • insurance contracts dealt with in IFRS 4 – Insurance Contracts – see Chapter 55, or insurance and other contracts in scope of IFRS 17 – Insurance Contracts – if that standard has been adopted (see Chapter 56). However, IAS 37 requires an insurer to apply the standard to provisions, contingent liabilities and contingent assets, other than those arising from its contractual obligations and rights under insurance contracts within the scope of IFRS 4, or IFRS 17 if that Standard has been adopted;
  • contingent consideration of an acquirer in a business combination (dealt with in IFRS 3 – Business Combinations – see Chapter 9); and
  • revenue from contracts with customers (dealt with in IFRS 15 – Revenue from Contracts with Customers – see Chapters 2732). However, as IFRS 15 contains no specific requirements to address contracts with customers that are, or have become, onerous, IAS 37 applies to such cases. [IAS 37.5].

Contingent consideration of an acquirer in a business combination is excluded from the scope of IAS 37 as a result of changes to IFRS 3 effective for business combinations with an acquisition date on or after 1 July 2014. See Chapter 9 at 7.1.

As noted above, the scope of IAS 37 excludes income taxes that fall in the scope of IAS 12. The Interpretations Committee confirmed in July 2014 that the recognition of tax-related contingent liabilities and contingent assets should also be assessed using the guidance in IAS 12 rather than IAS 37.2 In addition, IFRIC 23 – Uncertainty over Income Tax Treatments – was issued in June 2017 and clarifies how to apply the recognition and measurement requirements in IAS 12 when there is uncertainty over tax treatments. [IFRIC 23.4]. IAS 37 remains relevant to the disclosure of tax-related contingent liabilities and contingent assets. [IAS 12.88]. However, as discussed at 6.8 below, IAS 37 in general and IFRIC 21 in particular, applies to taxes or levies outside the scope of IAS 12. As regards interest and penalties imposed by taxation authorities the position is unclear. Neither IAS 12 nor IFRIC 23 contain a specific reference to interest and penalties, and, in September 2017, the Interpretations Committee decided not to add a project on interest and penalties to its agenda.3 However, notwithstanding their decision to exclude interest and penalties from the scope of IFRIC 23 and their decision not to add a project on interest and penalties to its agenda, the Interpretations Committee observed that if an entity determines that amounts payable or receivable for interest and penalties are income taxes, then the entity applies IAS 12 to those amounts. If an entity does not apply IAS 12 to interest and penalties, then it applies IAS 37 to those amounts. Uncertain tax treatments are discussed further in Chapter 33 at 9. The circumstances in which interest and penalties might fall within the scope of IAS 12 are considered in Chapter 33 at 4.4. Levies imposed by governments are examined at 6.8 below.

Whilst IAS 37 contains no reference to it, IFRS 3 states that the requirements in IAS 37 do not apply in determining which contingent liabilities to recognise as of the acquisition date (see 4.10 below and Chapter 9 at 5.6.1). [IFRS 3.23].

In addition, the standard does not apply to financial instruments (including guarantees) that are within the scope of IFRS 9 – Financial Instruments. [IAS 37.2]. This means that guarantees of third party borrowings (including those of subsidiaries, associates and joint arrangements) are not covered by IAS 37. However, the guarantee contract may meet the definition of an insurance contract in IFRS 4 and the issuer may have previously asserted that it regards such contracts as insurance contracts. In such cases, the issuer may elect to apply either IFRS 9 (or, for annual reporting periods beginning before 1 January 2021, IAS 39 – Financial Instruments: Recognition and Measurement, for those entities whose predominant activity is issuing contracts in scope of IFRS 4 and who previously have not applied any version of IFRS 9 [IFRS 4.20A, 20B]) or IFRS 4 [IFRS 9.2.1(e)] and the accounting policy applied by the issuer may result in the issuer providing for probable payments under the guarantee. A similar accounting policy choice exists for entities that apply IFRS 17, [IFRS 17.7(e)], although entities applying IFRS 17 do not have the option to apply IAS 39 rather than IFRS 9. (See Chapter 55 for IFRS 4 and Chapter 56 for IFRS 17).

The standard applies to provisions for restructurings, including discontinued operations. However, it emphasises that when a restructuring meets the definition of a discontinued operation under IFRS 5 – Non-current Assets Held for Sale and Discontinued Operations, additional disclosures may be required under that standard (see Chapter 4 at 3). [IAS 37.9].

As noted above, IAS 37 applies to contracts in scope of IFRS 15 that are, or have become, onerous. [IAS 37.5(g)]. IFRS 15 adds that IAS 37 applies to other obligations under a contract with a customer that do not give rise to a performance obligation. For example, a law that requires an entity to pay compensation if its products cause harm or damage does not give rise to a performance obligation and IAS 37 would apply. Similarly, an entity would account for customer indemnities arising from claims of patent, copyright, trademark or other infringement in relation to its products in accordance with IAS 37. [IFRS 15.B33]. Furthermore, whilst an entity would apply IFRS 15 to separately purchased warranties, if a customer does not have the option to purchase a warranty separately, an entity would consider IAS 37 (see 6.10 below), unless the promised warranty, or a part of the promised warranty, provides the customer with a service in addition to the assurance that the product complies with agreed-upon specifications. [IFRS 15.B30].

The standard defines a provision as ‘a liability of uncertain timing or amount’. [IAS 37.10]. Thus it only deals with provisions that are shown as liabilities in a statement of financial position. The term ‘provision’ is also used widely in the context of items such as depreciation, impairment of assets and doubtful debts. Such ‘provisions’ are not addressed in IAS 37, since these are adjustments to the carrying amounts of assets. [IAS 37.7].

2.2.2 Provisions compared to other liabilities

IAS 37 states that the feature distinguishing provisions from other liabilities, such as trade payables and accruals, is the existence of ‘uncertainty about the timing or amount of the future expenditure required in settlement’. [IAS 37.11]. The standard compares provisions to:

  1. trade payables – liabilities to pay for goods or services that have been received or supplied and have been invoiced or formally agreed with the supplier; and
  2. accruals – liabilities to pay for goods or services that have been received or supplied but have not been paid, invoiced or formally agreed with the supplier, including amounts due to employees (for example, amounts relating to accrued vacation pay). Although it is sometimes necessary to estimate the amount or timing of accruals, the uncertainty is generally much less than for provisions.

IAS 37 also notes that accruals are often reported as part of trade and other payables whereas provisions are reported separately. [IAS 37.11].

For trade payables and their associated accruals, there is little uncertainty regarding either the amount of the obligation (which would be determined by the contracted price for the goods and services being provided) or of the timing of settlement (which would normally occur within an agreed period following transfer of the goods and services in question and the issue of an invoice). In practice, however, contracts can be more complex and give rise to a wide range of possible outcomes in terms of the amount or timing of payment. In these circumstances, the difference between provisions and other liabilities is less obvious and judgement may be required to determine where the requirement to make an estimate of an obligation indicates a level of uncertainty about timing or amount that is more indicative of a provision. Such judgements, if significant to the amounts recognised in the financial statements, would merit disclosure (see Chapter 3 at 5.1.1.B). [IAS 1.122].

One reason why this distinction matters is that provisions are subject to narrative disclosure requirements regarding the nature of the obligation and the uncertainties over timing and amount; and to quantitative disclosures of movements arising from their use, remeasurement or release that do not apply to other payables (see 7.1 below). In fact, although questions of recognition and measurement are important, transparency of disclosure is also a very significant matter in relation to accounting for provisions and ensuring that their effect is properly understood by users of the financial statements.

2.2.3 Distinction between provisions and contingent liabilities

There is an area of overlap between provisions and contingent liabilities. Although contingent liabilities are clearly not as likely to give rise to outflows, similar judgements are made in assessing the nature of the uncertainties, the need for disclosures and ultimately the recognition of a liability in the financial statements. The standard notes that in a general sense, all provisions are contingent because they are uncertain in timing or amount. However, in IAS 37 the term ‘contingent’ is used for liabilities and assets that are not recognised because their existence will be confirmed only by the occurrence of one or more uncertain future events not wholly within the entity's control. In addition, the term ‘contingent liability’ is used for liabilities that do not meet the recognition criteria for provisions. [IAS 37.12].

Accordingly, the standard distinguishes between:

  1. provisions – which are recognised as liabilities (assuming that a reliable estimate can be made) because they are present obligations and it is probable that an outflow of resources embodying economic benefits will be required to settle the obligations; and
  2. contingent liabilities – which are not recognised as liabilities because they are either:
    1. possible obligations, as it has yet to be confirmed whether the entity has a present obligation that could lead to an outflow of resources embodying economic benefits; or
    2. present obligations that do not meet the recognition criteria in the standard because either it is not probable that an outflow of resources embodying economic benefits will be required to settle the obligation, or a sufficiently reliable estimate of the amount of the obligation cannot be made. [IAS 37.13].

3 RECOGNITION

3.1 Determining when a provision should be recognised

IAS 37 requires that a provision should be recognised when:

  1. an entity has a present obligation (legal or constructive) as a result of a past event;
  2. it is probable that an outflow of resources embodying economic benefits will be required to settle the obligation; and
  3. a reliable estimate can be made of the amount of the obligation.

No provision should be recognised unless all of these conditions are met. [IAS 37.14].

Each of these three conditions is discussed separately below.

3.1.1 ‘An entity has a present obligation (legal or constructive) as a result of a past event’

The standard defines both legal and constructive obligations. The definition of a legal obligation is fairly straightforward and uncontroversial; it refers to an obligation that derives from a contract (through its explicit or implicit terms), legislation or other operation of law. [IAS 37.10].

The definition of a constructive obligation, on the other hand, may give rise to more problems of interpretation. A constructive obligation is defined as an obligation that derives from an entity's actions where:

  1. by an established pattern of past practice, published policies or a sufficiently specific current statement, the entity has indicated to other parties that it will accept certain responsibilities; and
  2. as a result, the entity has created a valid expectation on the part of those other parties that it will discharge those responsibilities. [IAS 37.10].

The following examples in IAS 37 illustrate how a constructive obligation is created.

These examples demonstrate that the essence of a constructive obligation is the creation of a valid expectation that the entity is irrevocably committed to accepting and discharging its responsibilities.

The standard states that in almost all cases it will be clear whether a past event has given rise to a present obligation. However, it acknowledges that there will be some rare cases, such as a lawsuit against an entity, where this will not be so because the occurrence of certain events or the consequences of those events are disputed. [IAS 37.16]. When it is not clear whether there is a present obligation, a ‘more likely than not’ evaluation (taking into account all available evidence) is deemed to be sufficient to require recognition of a provision at the end of the reporting period. [IAS 37.15].

The evidence to be considered includes, for example, the opinion of experts together with any additional evidence provided by events after the reporting period. If on the basis of such evidence it is concluded that a present obligation is more likely than not to exist at the end of the reporting period, a provision will be required (assuming that the other recognition criteria are met). [IAS 37.16]. This is an apparent relaxation of the standard's first criterion for the recognition of a provision as set out at 3.1 above, which requires there to be a definite obligation, not just a probable one. It also confuses slightly the question of the existence of an obligation with the probability criterion, which strictly speaking relates to whether it is more likely than not that there will be an outflow of resources (see 3.1.2 below). However, this interpretation is confirmed in IAS 10 – Events after the Reporting Period, which includes ‘the settlement after the reporting period of a court case that confirms that the entity had a present obligation at the end of the reporting period’ as an example of an adjusting event. [IAS 10.9].

The second half of this condition uses the phrase ‘as a result of a past event’. This is based on the concept of an obligating event, which the standard defines as ‘an event that creates a legal or constructive obligation and that results in an entity having no realistic alternative to settling that obligation’. [IAS 37.10]. The standard says that this will be the case only:

  1. where the settlement of the obligation can be enforced by law; or
  2. in the case of a constructive obligation, where the event (which may be an action of the entity) creates valid expectations in other parties that the entity will discharge the obligation. [IAS 37.17].

This concept of obligating event is used in the standard when discussing specific examples of recognition, which we consider further at 6 below. However, it is worth mentioning here that this concept, like that of a constructive obligation, is open to interpretation and requires the exercise of judgement, as the obligating event is not always easy to identify.

The standard emphasises that the financial statements deal with the financial position of an entity at the end of its reporting period, not its possible position in the future. Accordingly, no provision should be recognised for costs that need to be incurred to operate in the future. The only liabilities to be recognised are those that exist at the end of the reporting period. [IAS 37.18]. It is not always easy to distinguish between the current state at the reporting date and the entity's future possible position, especially where IAS 37 requires an assessment to be made based on the probability of obligations and expectations as to their outcome. However, when considering these questions it is important to ensure that provisions are not recognised for liabilities that arise from events after the reporting period (see Chapter 38 at 2).

IAS 37 prohibits certain provisions that might otherwise qualify to be recognised by stating that it ‘is only those obligations arising from past events existing independently of an entity's future actions (i.e. the future conduct of its business) that are recognised as provisions'. In contrast to situations where the entity's past conduct has created an obligation to incur expenditure (such as to rectify environmental damage already caused), a commercial or legal requirement to incur expenditure in order to operate in a particular way in the future, will not of itself justify the recognition of a provision. It argues that because the entity can avoid the expenditure by its future actions, for example by changing its method of operation, there is no present obligation for the future expenditure. [IAS 37.19].

The standard expects strict application of the requirement that, to qualify for recognition, an obligation must exist independently of an entity's future actions. Even if a failure to incur certain costs would result in a legal requirement to discontinue an entity's operations, no provision can be recognised. As discussed at 5.2 below, IAS 37 considers the example of an airline required by law to overhaul its aircraft once every three years. It concludes that no provision is recognised because the entity can avoid the requirement to perform the overhaul, for example by replacing the aircraft before the three year period has expired. [IAS 37 IE Example 11B].

Centrica plc describes its interpretation of the group's obligations under UK legislation to install energy efficiency improvement measures in domestic households in a manner consistent with Example 26.3 above.

Significantly, however, such considerations do not apply in the case of obligations to dismantle or remove an asset at the end of its useful life, where an obligation is recognised despite the entity's ability to dispose of the asset before its useful life has expired. Such costs are required to be included by IAS 16 – Property, Plant and Equipment – as part of the measure of an asset's initial cost. [IAS 16.16]. Decommissioning provisions are discussed at 6.3 below. Accordingly, the determination of whether an obligation exists independently of an entity's future actions can be a matter of judgement that depends on the particular facts and circumstances of the case.

There is no requirement for an entity to know to whom an obligation is owed. The obligation may be to the public at large. It follows that the obligation could be to one party, but the amount ultimately payable will be to another party. For example, in the case of a constructive obligation for an environmental clean-up, the obligation is to the public, but the liability will be settled by making payment to the contractors engaged to carry out the clean-up. However, the principle is that there must be another party for the obligation to exist. It follows from this that a management or board decision will not give rise to a constructive obligation unless it is communicated in sufficient detail to those affected by it before the end of the reporting period. [IAS 37.20]. The most significant application of this requirement relates to restructuring provisions, which is discussed further at 6.1 below.

The standard discusses the possibility that an event that does not give rise to an obligation immediately may do so at a later date, because of changes in the law or an act by the entity (such as a sufficiently specific public statement) which gives rise to a constructive obligation. [IAS 37.21]. Changes in the law will be relatively straightforward to identify. The only issue that arises will be to determine exactly when that change in the law should be recognised. IAS 37 states that an obligation arises only when the legislation is virtually certain to be enacted as drafted and suggests that in many cases, this will not be until it is enacted. [IAS 37.22].

The more subjective area is the possibility that an act by the entity will give rise to a constructive obligation. The example given is of an entity publicly accepting responsibility for rectification of previous environmental damage in a way that creates a constructive obligation. [IAS 37.21]. This seems to introduce a certain amount of flexibility to management when reporting results. By bringing forward or delaying a public announcement of a commitment that management had always intended to honour, it can affect the reporting period in which a provision is recognised. Nevertheless, the existence of a public announcement provides a more transparent basis for recognising a provision than, for example, a decision made behind the closed doors of a boardroom.

3.1.2 ‘It is probable that an outflow of resources embodying economic benefits will be required to settle the obligation’

This requirement has been included as a result of the standard's attempt to incorporate contingent liabilities within the definition of provisions. This is discussed at 3.2 below.

The meaning of probable in these circumstances is that the outflow of resources is more likely than not to occur; that is, it has a probability of occurring that is greater than 50%. [IAS 37.23]. The standard also makes it clear that where there are a number of similar obligations, the probability that an outflow will occur is based on the class of obligations as a whole. This is because in the case of certain obligations such as warranties, the possibility of an outflow for an individual item may be small (likely to be much less than 50%) whereas the possibility of at least some outflow of resources for the population as a whole will be much greater (almost certainly greater than 50%). [IAS 37.24]. With regard to the measurement of a provision arising from a number of similar obligations, the standard refers to the calculation of an ‘expected value’, whereby the obligation is estimated by weighting all the possible outcomes by their associated probabilities. [IAS 37.39]. Where the obligation being measured relates to a single item, the standard suggests that the best estimate of the liability may be the individual most likely outcome. [IAS 37.40]. For the purposes of recognition, a determination that it is more likely than not that any outflow of resources will be required is sufficient. The measurement of provisions is discussed at 4 below.

3.1.3 ‘A reliable estimate can be made of the amount of the obligation’

The standard takes the view that a sufficiently reliable estimate can almost always be made for a provision where an entity can determine a range of possible outcomes. Hence, the standard contends that it will only be in extremely rare cases that a range of possible outcomes cannot be determined and therefore no sufficiently reliable estimate of the obligation can be made. [IAS 37.25]. In these extremely rare circumstances, no liability is recognised. Instead, the liability should be disclosed as a contingent liability (see disclosure requirements at 7.2 below). [IAS 37.26]. Whether such a situation is as rare as the standard asserts is open to question, especially for entities trying to determine estimates relating to potential obligations that arise from litigation and other legal claims (see 6.11 below).

3.2 Contingencies

IAS 37 says that contingent liabilities and contingent assets should not be recognised, but only disclosed. [IAS 37.27‑28, 31, 34].

Contingent liabilities that are recognised separately as part of allocating the cost of a business combination are covered by the requirements of IFRS 3. [IFRS 3.23]. Such liabilities continue to be measured after the business combination at the higher of:

  1. the amount that would be recognised in accordance with IAS 37, and
  2. the amount initially recognised less, if appropriate, the cumulative amount of income recognised in accordance with the principles of IFRS 15. [IFRS 3.56].

The requirements in respect of contingent liabilities identified in a business combination are discussed in Chapter 9 at 5.6.1.

3.2.1 Contingent liabilities

A contingent liability is defined in the standard as:

  1. a possible obligation that arises from past events and whose existence will be confirmed only by the occurrence or non-occurrence of one or more uncertain future events not wholly within the control of the entity; or
  2. a present obligation that arises from past events but is not recognised because:
    1. it is not probable that an outflow of resources embodying economic benefits will be required to settle the obligation; or
    2. the amount of the obligation cannot be measured with sufficient reliability. [IAS 37.10].

At first glance, this definition is not easy to understand because a natural meaning of ‘contingent’ would include any event whose outcome depends on future circumstances. The meaning is perhaps clearer when considering the definition of a liability and the criteria for recognising a provision in the standard. A possible obligation whose existence is yet to be confirmed does not meet the definition of a liability; and a present obligation in respect of which an outflow of resources is not probable, or which cannot be measured reliably does not qualify for recognition. [IAS 37.14]. On that basis a contingent liability under IAS 37 means one of the following:

  1. an obligation that is estimated to be less than 50+% likely to exist (i.e. it does not meet the definition of a liability). Where it is more likely than not that a present obligation exists at the end of the reporting period, a provision is recognised. [IAS 37.16(a)]. Where it is more likely than not that no present obligation exists, a contingent liability is disclosed (unless the possibility is remote); [IAS 37.16(b)]
  2. a present obligation that has a less than 50+% chance of requiring an outflow of economic benefits (i.e. it meets the definition of a liability but does not meet the recognition criteria). Where it is not probable that there will be an outflow of resources, an entity discloses a contingent liability (unless the possibility is remote); [IAS 37.23] or
  3. a present obligation for which a sufficiently reliable estimate cannot be made (i.e. it meets the definition of a liability but does not meet the recognition criteria). In these rare circumstances, a liability cannot be recognised and it is disclosed as a contingent liability. [IAS 37.26].

The term ‘possible’ is not defined, but literally it could mean any probability greater than 0% and less than 100%. However, the standard effectively divides this range into four components, namely ‘remote’, ‘possible but not probable’, ‘probable’ and ‘virtually certain’. The standard requires a provision to be recognised if ‘it is more likely than not that a present obligation exists at the end of the reporting period’. [IAS 37.16(a)]. Therefore, IAS 37 distinguishes between a ‘probable’ obligation (which is more likely than not to exist and, therefore requires recognition as a provision) and a ‘possible’ obligation (for which either the existence of a present obligation is yet to be confirmed or where the probability of an outflow of resources is 50% or less). [IAS 37.13]. Appendix A to IAS 37, in summarising the main requirements of the standard, uses the phrase ‘a possible obligation … that may, but probably will not, require an outflow of resources’. Accordingly, the definition restricts contingent liabilities to those where either the existence of the liability or the transfer of economic benefits arising is less than 50+% probable (or where the obligation cannot be measured at all, but as noted at 3.1.3 above, this would be relatively rare).

The standard requires that contingent liabilities are assessed continually to determine whether circumstances have changed, in particular whether an outflow of resources embodying economic benefits has become probable. Where this becomes the case, then provision should be made in the period in which the change in probability occurs (except in the rare circumstances where no reliable estimate can be made). [IAS 37.30]. Other changes in circumstances might require disclosure of a previously remote obligation on the grounds that an outflow of resources has become possible (but not probable).

3.2.2 Contingent assets

A contingent asset is defined in a more intuitive way. It is ‘a possible asset that arises from past events and whose existence will be confirmed only by the occurrence or non-occurrence of one or more uncertain future events not wholly within the control of the entity’. [IAS 37.10]. In this case, the word ‘possible’ is not confined to a level of probability of 50% or less, which may further increase the confusion over the different meaning of the term in the definition of contingent liabilities.

Contingent assets usually arise from unplanned or other unexpected events that give rise to the possibility of an inflow of economic benefits to the entity. An example is a claim that an entity is pursuing through legal process, where the outcome is uncertain. [IAS 37.32].

The standard states that a contingent asset should not be recognised, as this could give rise to recognition of income that may never be realised. However, when the realisation of income is virtually certain, then the related asset is no longer regarded as contingent and recognition is appropriate. [IAS 37.33].

Virtual certainty is not defined in the standard, but it is certainly a much higher hurdle than ‘probable’ and indeed more challenging than the term ‘highly probable’, defined in IFRS 5 as ‘significantly more likely than probable’. [IFRS 5 Appendix A]. We think it reasonable that virtual certainty is interpreted as being as close to 100% as to make any remaining uncertainty insignificant. What this means in practice requires each case to be decided on its merits and any judgement should be made in the knowledge that, in any event, it is rarely possible to accurately assess the probability of the outcome of a particular event.

The standard requires disclosure of the contingent asset when the inflow of economic benefits is probable. [IAS 37.34]. For the purposes of the standard ‘probable’ means that the event is more likely than not to occur; that is, it has a probability greater than 50%. [IAS 37.23]. The disclosure requirements are detailed at 7.3 below.

As with contingent liabilities, any contingent assets should be assessed continually to ensure that developments are appropriately reflected in the financial statements. If it has become virtually certain that an inflow of economic benefits will arise, the asset and the related income should be recognised in the period in which the change occurs. If a previously unlikely inflow becomes probable, then the contingent asset should be disclosed. [IAS 37.35].

The requirement to recognise the effect of changing circumstances in the period in which the change occurs extends to the analysis of information available after the end of the reporting period and before the date of approval of the financial statements. In our view, such information would not give rise to an adjusting event after the reporting period. In contrast to contingent liabilities (in respect of which IAS 10 includes as a specific example of an adjusting event ‘the settlement after the reporting period of a court case that confirms that the entity had a present obligation at the end of the reporting period’ [IAS 10.9]), no adjustment should be made to reflect the subsequent settlement of a legal claim in favour of the entity. In this instance, the period in which the change occurs is subsequent to the reporting period. There is also no suggestion that the example in IAS 10 is referring to anything but liabilities. An asset could only be recognised if, at the end of the reporting period, the entity could show that it was virtually certain that its claim would succeed.

3.2.2.A Obligations contingent on the successful recovery of a contingent asset

Entities may sometimes be required to pay contingent fees to a third party dependent upon the successful recovery of a contingent asset. For example, the payment of fees to a legal advisor in a contract agreed on a ‘no win, no fee’ basis will depend upon the successful outcome of a legal claim. In such cases, we believe that the obligation for the success fee arises from an executory contract that should be evaluated separately from the legal claim. The liability for the success fee would therefore only be recognised by the entity upon winning the claim.

IAS 37 uses the term executory contracts to mean ‘contracts under which neither party has performed any of its obligations, or both parties have partially performed their obligations to an equal extent’. [IAS 37.3]. When a contract for services is wholly contingent on recovering a contingent asset, no service requiring payment is deemed to be provided until or unless the matter is resolved successfully. Unless the contract also required payment to be made in the event of failure, the amount of work put in by the lawyer to prepare a case and argue for recovery of the contingent asset is irrelevant to the existence of a liability to pay fees.

If the entity has deemed it appropriate to recognise an asset in respect of the claim, it would be appropriate to take account of any such fees in the measurement of that asset (in determining the net amount recoverable); but no accrual should be made for the legal fees themselves unless a successful outcome is confirmed.

This analysis is specific to a no win-no fee arrangement related to a contingent asset and may not be appropriate in other circumstances.

3.2.3 How probability determines whether to recognise or disclose

The following matrix summarises the treatment of contingencies under IAS 37:

Likelihood of outcome Accounting treatment: contingent liability Accounting treatment: contingent asset
Virtually certain Recognise Recognise
Probable Recognise Disclose
Possible but not probable Disclose No disclosure permitted
Remote No disclosure required No disclosure permitted

The standard does not put a numerical measure of probability on either ‘virtually certain’ or ‘remote’. In our view, the use of such measures would downgrade a process requiring the exercise of judgement into a mechanical exercise. It is difficult to imagine circumstances when an entity could reliably determine an obligation to be, for example, 92%, 95% or 99% likely, let alone be able to compare those probabilities objectively. Accordingly, we think it reasonable to regard ‘virtually certain’ as describing a likelihood that is as close to 100% as to make any remaining uncertainty insignificant; to see ‘remote’ as meaning a likelihood of an outflow of resources that is not significant; and for significance to be a matter for judgement and determined according to the merits of each case.

3.3 Recognising an asset when recognising a provision

In most cases, the recognition of a provision results in an immediate expense in profit or loss. Nevertheless, in some cases it may be appropriate to recognise an asset. These issues are not discussed in IAS 37, which neither prohibits nor requires capitalisation of the costs recognised when a provision is made. It states that other standards specify whether expenditures are treated as assets or expenses. [IAS 37.8].

Whilst the main body of IAS 37 is silent on the matter, the standard contains the following example which concludes that an asset should be recognised when a decommissioning provision is established.

This conclusion is supported by IAS 16, which requires the cost of an item of property, plant and equipment to include the initial estimate of the costs of dismantling and removing an asset and restoring the site on which it is located, the obligation for which an entity incurs either when the item is acquired or as a consequence of having used the item during a particular period for purposes other than to produce inventories during that period. [IAS 16.16(c), 18]. The treatment of decommissioning costs is discussed further at 6.3 below.

4 MEASUREMENT

4.1 Best estimate of provision

IAS 37 requires the amount to be recognised as a provision to be the best estimate of the expenditure required to settle the present obligation at the end of the reporting period. [IAS 37.36]. This measure is determined before tax, as the tax consequences of the provision, and changes to it, are dealt with under IAS 12. [IAS 37.41].

The standard equates this ‘best estimate’ with ‘the amount that an entity would rationally pay to settle the obligation at the end of the reporting period or to transfer it to a third party at that time’. [IAS 37.37]. It is interesting that a hypothetical transaction of this kind should be proposed as the conceptual basis of the measurement required, rather than putting the main emphasis upon the actual expenditure that is expected to be incurred in the future.

The standard does acknowledge that it would often be impossible or prohibitively expensive to settle or transfer the obligation at the end of the reporting period. However, it goes on to state that ‘the estimate of the amount that an entity would rationally pay to settle or transfer the obligation gives the best estimate of the expenditure required to settle the present obligation at the end of the reporting period’. [IAS 37.37].

During the Provisions research project, stakeholders have noted that the measurement objective in IAS 37 is not precise and, in practice, is interpreted in different ways.4 The assumptions that an entity makes regarding derecognition of the liability may influence how the entity determines the best estimate of the expenditure required to settle the obligation. In practice, there are several ways in which an IAS 37 obligation may be derecognised. For example:

  1. The obligation is settled by the entity performing the obligation itself (for example, the entity uses its own personnel to clean up a site to satisfy an environmental clean-up obligation);
  2. The entity employs a third party to perform the work required to settle the obligation (for example, the entity hires a third party company to clean up the site);
  3. The entity transfers the obligation to a third party (for example, another entity takes on the obligation to clean up the site, the entity pays the transferee, and is relieved of the obligation); or
  4. The obligation is cash settled by negotiation with the party to whom the obligation is owed (for example, the entity negotiates a cash settlement with the local municipality in order to be relieved of the obligation).

In our view, any of the assumptions above are acceptable bases provided that they appropriately reflect the facts and circumstances of the situation. If an entity exercises significant judgement in determining the most appropriate approach, consideration should be given to the disclosure requirements in paragraph 122 of IAS 1 – Presentation of Financial Statements. See Chapter 3 at 5.1.1.B. At the time of writing, the IASB staff intend to further investigate the feasibility of clarifying the measurement objective of IAS 37.5

The estimates of outcome and financial effect are determined by the judgement of the entity's management, supplemented by experience of similar transactions and, in some cases, reports from independent experts. The evidence considered will include any additional evidence provided by events after the reporting period. [IAS 37.38].

The standard suggests that there are various ways of dealing with the uncertainties surrounding the amount to be recognised as a provision. It mentions three, an expected value (or probability-weighted) method; the mid-point of the range of possible outcomes; and an estimate of the individual most likely outcome. An expected value approach would be appropriate when a large population of items is being measured, such as warranty costs. This is a statistical computation which weights the cost of all the various possible outcomes according to their probabilities, as illustrated in the following example taken from IAS 37. [IAS 37.39].

In a situation where there is a continuous range of possible outcomes and each point in that range is as likely as any other, IAS 37 requires that the mid-point of the range is used. [IAS 37.39]. This is not a particularly helpful way of setting out the requirement, as it does not make it clear what the principle is meant to be. The mid-point in this case represents the median as well as the expected value. The latter may have been what was intended, but the median could be equally well justified on the basis that it is 50% probable that at least this amount will be payable, while anything in excess of that constitutes a possible but not a probable liability, that should be disclosed rather than accrued. Interestingly, US GAAP has a different approach to this issue in relation to contingencies. FASB ASC Topic 450 – Contingencies – states that where a contingent loss could fall within a range of amounts then, if there is a best estimate within the range, it should be accrued, with the remainder noted as a contingent liability. However, if there is no best estimate then the lowest figure within the range should be accrued, with the remainder up to the maximum potential loss noted as a contingent liability.6

Where the obligation being measured relates to a single item, the standard suggests that the best estimate of the liability may be the individual most likely outcome. However, even in such a case, it notes that consideration should be given to other possible outcomes and where these are predominantly higher or mainly lower than the most likely outcome, the resultant ‘best estimate’ will be a higher or lower amount than the individual most likely outcome. To illustrate this, the standard gives an example of an entity that has to rectify a fault in a major plant that it has constructed for a customer. The most likely outcome is that the repair will succeed at the first attempt. However, a provision should be made for a larger amount if there is a significant chance that further attempts will be necessary. [IAS 37.40].

4.2 Dealing with risk and uncertainty in measuring a provision

It is clear from the definition of a provision as a liability of uncertain timing or amount that entities will have to deal with risk and uncertainty in estimating an appropriate measure of the obligation at the end of the reporting period. It is therefore interesting to consider how the measurement rules detailed in IAS 37 help entities achieve a faithful representation of the obligation in these circumstances. A faithful representation requires estimates that are neutral, that is, without bias. [CF(2010) QC12, QC14]. The Conceptual Framework (2010) warns against the use of conservatism or prudence in estimates because this is ‘likely to lead to a bias’. It adds that the exercise of prudence can be counterproductive, in that the overstatement of liabilities in one period frequently leads to overstated financial performance in later periods, ‘a result that cannot be described as prudent or neutral’. [CF(2010) BC3.28]. In March 2018, the IASB issued a revised Conceptual Framework for Financial Reporting. The revised framework became effective immediately for the IASB and IFRS Interpretations Committee and is effective from 1 January 2020 for entities that use the Conceptual Framework to develop accounting policies when no IFRS standard applies to a particular transaction. The revised Conceptual Framework also notes that a faithful representation requires estimates that are neutral, i.e. without bias. [CF 2.13, 2.15].

The standard does not refer to neutrality as such; however, it does discuss the concept of risk and the need for exercising caution and care in making judgements under conditions of uncertainty. It states that ‘the risks and uncertainties that inevitably surround many events and circumstances shall be taken into account in reaching the best estimate of a provision’. [IAS 37.42]. It refers to risk as being variability of outcome and suggests that a risk adjustment may increase the amount at which a liability is measured. [IAS 37.43]. Whilst the standard provides an example of a case in which the best estimate of an obligation might have to be larger than the individual most likely outcome, [IAS 37.40], it gives no indication of how this increment should be determined. It warns that caution is needed in making judgements under conditions of uncertainty, so that expenses or liabilities are not understated. However, it says that uncertainty does not justify the creation of excessive provisions or a deliberate overstatement of liabilities. Accordingly, care is needed to avoid duplicating adjustments for risk and uncertainty, for example by estimating the costs of a particularly adverse outcome and then overestimating its probability. [IAS 37.43]. Any uncertainties surrounding the amount of the expenditure are to be disclosed (see 7.1 below). [IAS 37.44].

The overall result of all this is somewhat confusing. Whilst a best estimate based solely on the expected value approach or the mid-point of a range addresses the uncertainties relating to there being a variety of possible outcomes, it does not fully reflect risk, because the actual outcome could still be higher or lower than the estimate. Therefore, the discussion on risk suggests that an additional adjustment should be made. However, apart from indicating that the result may be to increase the recognised liability and pointing out the need to avoid duplicating the effect of risk in estimates of cash flows and probability, [IAS 37.43], it is not clear quite how this might be achieved. This leaves a certain amount of scope for variation in the estimation of provisions and is further complicated when the concept of risk is combined with considerations relating to the time value of money (see 4.3.2 below).

4.3 Discounting the estimated cash flows to a present value

The standard requires that where the effect of the time value of money is material, the amount of a provision should be the present value of the expenditures expected to be required to settle the obligation. [IAS 37.45]. The discount rate (or rates) to be used in arriving at the present value should be ‘a pre-tax rate (or rates) that reflect(s) current market assessments of the time value of money and the risks specific to the liability. The discount rate(s) shall not reflect risks for which the future cash flow estimates have been adjusted.’ [IAS 37.47]. However, it is worth noting that no discounting is required for provisions where the cash flows will not be sufficiently far into the future for discounting to have a material impact. [IAS 37.46].

The main types of provision where the impact of discounting will be significant are those relating to decommissioning and other environmental restoration liabilities. IFRIC 1 addresses some of the issues relating to the use of discounting (in the context of provisions for obligations to dismantle, remove or restore items of property, plant and equipment, referred to as ‘decommissioning, restoration and similar liabilities’) which are discussed at 6.3.1 below.

4.3.1 Real versus nominal rate

IAS 37 does not indicate whether the discount rate should be a real discount rate or a nominal discount rate (although a real discount rate is referred to in Example 2 in Appendix D which illustrates the narrative disclosure for decommissioning costs). The discount rate to be used depends on whether:

  1. the future cash flows are expressed in current prices, in which case a real discount rate (which excludes the effects of general inflation) should be used; or
  2. the future cash flows are expressed in expected future prices, in which case a nominal discount rate (which includes a return to cover expected inflation) should be used.

Either alternative is acceptable, and these methods may produce the same figure for the initial present value of the provision. However, the effect of the unwinding of the discount may be different in each case (see 4.3.5 below).

4.3.2 Adjusting for risk and using a government bond rate

IAS 37 also requires that risk is taken into account in the calculation of a provision, but gives little guidance as to how this should be done. Where discounting is concerned, it merely says that the discount rate should not reflect risks for which the future cash flow estimates have been adjusted. [IAS 37.47]. One may use a discount rate that reflects the risk associated with the liability (a risk-adjusted rate). The following example, taken from the UK Accounting Standards Board's (ASB) Working Paper – Discounting in Financial Reporting,7 shows how an entity might calculate such a risk adjusted rate.

As can be seen from this example, the risk-adjusted discount rate is a lower rate than the unadjusted (risk-free) discount rate. This may seem counter-intuitive initially, because the experience of most borrowers is that banks and other lenders will charge a higher rate of interest on loans that are assessed to be higher risk to the lender. However, in the case of a provision a risk premium is being suffered to eliminate the possibility of the actual cost being higher (thereby capping a liability), whereas in the case of a loan receivable a premium is required to compensate the lender for taking on the risk of not recovering its full value (setting a floor for the value of the lender's financial asset). In both cases the actual cash flows incurred by the paying entity are higher to reflect a premium for risk. In other words, the discount rate for an asset is increased to reflect the risk of recovering less and the discount rate for a liability is reduced to reflect the risk of paying more.

A problem with changing the discount rate to account for risk is that this adjusted rate is a theoretical rate, as it is unlikely that there would be a market assessment of the risks specific to the liability alone. [IAS 37.47]. However the lower discount rate in the above example is consistent with the premise that a risk-adjusted liability should be higher than a liability without accounting for the risk that the actual settlement amount is different to the estimate. [IAS 37.43]. It is also difficult to see how a risk-adjusted rate could be obtained in practice. In the above example, it was obtained only by reverse-engineering; it was already known that the net present value of a risk-adjusted liability was £138, so the risk-adjusted rate was just the discount rate applied to unadjusted cash flow of £150 to give that result.

IAS 37 offers an alternative approach – instead of using a risk-adjusted discount rate, the estimated future cash flows themselves can be adjusted for risk. [IAS 37.47]. This does of course present the problem of how to adjust the cash flows for risk (see 4.2 above). However, this may be easier than attempting to risk-adjust the discount rate.

For the purposes of discounting post-employment benefit obligations, IAS 19 requires the discount rate to be determined by reference to market yields at the end of the reporting period on high quality corporate bonds (although in countries where there is no deep market in such bonds, the market yields on government bonds should be used). [IAS 19.83]. Although IAS 19 indicates that this discount rate reflects the time value of money (but not the actuarial or investment risk), [IAS 19.84], we do not believe it is appropriate to use the yield on a high quality corporate bond for determining a risk-free rate to be used in discounting provisions under IAS 37. Accordingly, in our view, where an entity is using a risk-free discount rate for the purposes of calculating a provision under IAS 37, that rate should be based on a government bond rate with a similar currency and remaining term as the provision. It follows that because a risk-adjusted rate is always lower than the risk-free rate, an entity cannot justify the discounting of a provision at a rate that is higher than a government bond rate with a similar currency and term to the provision.

Whichever method of reflecting risk is adopted, IAS 37 emphasises that care must be taken that the effect of risk is not double-counted by inclusion in both the cash flows and the discount rate. [IAS 37.47].

In recent years, government bond rates have been more volatile as markets have changed rates to reflect (among other factors) heightened perceptions of sovereign debt risk. In some cases, government bond yields may be negative. The question has therefore arisen whether government bond rates, at least in certain jurisdictions, should continue to be regarded as the default measure of a risk-free discount rate. Whilst the current volatility in rates has highlighted the fact that no debt (even government debt) is totally risk free, the challenge is to find a more reliable measure as an alternative. Any adjustment to the government bond rate to ‘remove’ the estimate of sovereign debt risk is conceptually flawed, as it not possible to isolate one component of risk from all the other variables that influence the setting of an interest rate. Another approach might be to apply some form of average bond rate over a period of 3, 6 or 12 months to mitigate the volatility inherent in applying the spot rate at the period end. However, this is clearly inappropriate given the requirements in IAS 37 to determine the best estimate of an obligation by reference to the expenditure required to settle it ‘at the end of the reporting period’, [IAS 37.36], and to determine the discount rate on the basis of ‘current market assessments’ of the time value of money. [IAS 37.47].

With ‘risk’ being a measure of potential variability in returns, it remains the case that in most countries a government bond will be subject to the lowest level of variability in that jurisdiction. As such, in most countries it remains the most suitable of all the observable measures of the time value of money in a particular country. Where government bond rates are negative or, more likely, result in a negative discount rate once adjusted for risk, we believe that it is not appropriate to apply a floor of zero to the discount rate as this would result in an understatement of the liability. As discussed above, and at 4.3.1 above, IAS 37 offers various approaches to determining an appropriate discount rate. It may sometimes be the case that one or more of the allowed approaches result in a negative discount rate whereas the application of an alternative permitted approach would not. In order to avoid some of the presentational difficulties associated with a negative discount rate, entities faced with a negative real discount rate before risk adjustment may wish to consider the alternative approach of discounting expected future cash flows expressed in future prices, at a nominal discount rate (see 4.3.1 above), if the nominal rate is not negative. Similarly, entities that are faced with a negative risk-adjusted discount rate only because of risk adjustment (i.e. where risk free rates themselves are not negative) may wish to adopt the alternative approach of adjusting the estimated future cash flows to reflect the risks associated with the liability, rather than risk-adjusting the discount rate.

A difficulty that can arise in certain countries is finding a government bond with a similar term to the provision, for example when measuring a decommissioning provision expected to be settled in 30 years in a country where there are no government bonds with a term exceeding 10 years. In such cases, the government bond rate might be adjusted and the techniques adopted by actuaries for measuring retirement obligations with long maturities, that involve extrapolating current market rates along a yield curve, [IAS 19.86], might be considered. The difficulties of finding an appropriate discount rate in the context of retirement benefit obligations are discussed in Chapter 35 at 7.6.

4.3.3 Own credit risk

IAS 37 does not address whether an entity's own credit risk should be considered a risk specific to a liability when determining a risk-adjusted discount rate. In March 2011, the Interpretations Committee decided not to take to its agenda a request for interpretation of the phrase ‘the risks specific to the liability’ and whether this means that an entity's own credit risk should be excluded from any adjustments made to the discount rate used to measure liabilities. In doing so, the Interpretations Committee acknowledged that IAS 37 is not explicit on the question of own credit risk; but understood that the predominant practice was to exclude it for the reason that credit risk is generally viewed as a risk of the entity rather than a risk specific to the liability.9

Whether own credit risk is considered a risk specific to a liability may depend, at least in part, on the way in which an entity measures a provision (i.e. how an entity determines the best estimate of the expenditure required to settle the obligation). As discussed at 4.1 above, the measurement objective in IAS 37 is not precise, and the term ‘best estimate’ may be interpreted in different ways. For example, an entity may determine the best estimate by assuming that the obligation will be cash settled by negotiation with the party to whom the obligation is owed. In this case, own credit risk might be considered relevant if the party to whom the obligation is owed would be willing to negotiate a lower settlement amount if the entity risks defaulting in the future. If an entity has exercised significant judgement in determining the best estimate of the expenditure required to settle an obligation, and whether own credit risk is taken into account, consideration should be given to the disclosure requirements in paragraph 122 of IAS 1. See Chapter 3 at 5.1.1.B.

4.3.4 Pre-tax discount rate

Since IAS 37 requires provisions to be measured before tax, it follows that cash flows should be discounted at a pre-tax discount rate. [IAS 37.47]. No further explanation of this is given in the standard.

This is probably because, in reality, the use of a pre-tax discount rate will be most common. Supposing, for example, that the risk-free rate of return is being used, then the discount rate used will be a government bond rate. This rate will be obtained gross. Thus, the idea of trying to determine a pre-tax rate (for example by obtaining a required post-tax rate of return and adjusting it for the tax consequences of different cash flows) will seldom be relevant.

The calculation is illustrated in the following example.

4.3.5 Unwinding of the discount

IAS 37 indicates that where discounting is used, the carrying amount of a provision increases in each period to reflect the passage of time, and that this increase is recognised as a borrowing cost. [IAS 37.60]. This is the only guidance that the standard gives on the unwinding of the discount. IFRIC 1 in relation to provisions for decommissioning, restoration and similar liabilities requires that the periodic unwinding of the discount is recognised in profit or loss as a finance cost as it occurs. The Interpretations Committee concluded that the unwinding of the discount is not a borrowing cost for the purposes of IAS 23 – Borrowing Costs – and thus cannot be capitalised under that standard. [IFRIC 1.8]. It noted that IAS 23 addresses funds borrowed specifically for the purpose of obtaining a particular asset and agreed that a decommissioning liability does not fall within this description since it does not reflect funds borrowed. Accordingly, the Interpretations Committee concluded that the unwinding of the discount is not a borrowing cost as defined in IAS 23. [IFRIC 1.BC26].

However, there is no discussion of the impact that the original selection of discount rate can have on its unwinding, that is, the selection of real versus nominal rates, and risk-free versus risk-adjusted rates and the fact that these different discount rates will unwind differently. This is best illustrated by way of an example.

Although the total expense in each year is the same under either method, what will be different is the allocation of the change in provision between operating costs (assuming the original provision was treated as an operating expense) and finance charges. It can be seen from the second table in the above example that using the real discount rate will give rise to a much lower finance charge each year. However, this does not lead to a lower provision in the statement of financial position at the end of each year. Provisions have to be revised annually to reflect the current best estimate of the obligation. [IAS 37.59]. Thus, the provision in the above example at the end of each year needs to be adjusted to reflect current prices at that time (and any other adjustments that arise from changes in the estimate of the provision), as well as being adjusted for the unwinding of the discount. For example, the revised provision at the end of Year 1 is €100,173, being €105,000 discounted for two years at 2.381%. After allowing for the unwinding of the discount, this required an additional provision of €4,770. Alternatively, entities may take the view that the amount included as a borrowing cost should be based on the nominal discount rate. The basis for this argument is that IAS 37 requires the increase in a provision due to the passage of time to be recognised as a borrowing cost [IAS 37.60] and inflation, which is reflected in the nominal rate but not the real rate, is part of the time value of money.

A more significant difference will arise where the recognition of the original provision is included as part of the cost of property, plant or equipment, rather than as an expense, such as when a decommissioning provision is recognised. In that case, using a real discount rate will result initially in a lower charge to the income statement, since under IFRIC 1 any revision to the estimate of the provision is not taken to the income statement but is treated as an adjustment to the carrying value of the related asset, which is then depreciated prospectively over the remaining life of the asset (see 6.3.1 below).

A similar issue arises with the option of using the risk-free or the risk-adjusted discount rate. However, this is a more complex problem, because it is not clear what to do with the risk-adjustment built into the provision. This is illustrated in the following example.

In this example, the unwinding of different discount rates gives rise to different provisions. The difference of £10 (£22 – £12) relates to the risk adjustment that has been made to the provision. However, as the actual date of settlement comes closer, the estimates of the range of possible outcomes (and accordingly the expected value of the outflow) and the premium the entity would accept for certainty would need to be re-estimated. As such, the effect of any initial difference related to the decision to apply a risk-free or risk-adjusted rate will be lost in the other estimation adjustments that would be made over time.

In circumstances where a provision has been discounted using a negative discount rate (see 4.3.2 above), entities will need to give some consideration to how the unwinding of the discount should be presented in the statement of comprehensive income. The presentation of income and expense resulting from negative interest has been discussed by the Interpretations Committee in the context of financial instruments. Whilst that topic was not taken on to the Interpretations Committee's agenda, the Committee noted in their agenda decision that the expense arising on a financial asset because of a negative interest rate should not be presented as interest revenue, but in an appropriate expense classification.10 Whilst negative interest rates on financial liabilities were not explicitly addressed in the agenda decision, the Interpretations Committee noted during discussions that an inflow of economic benefits arising from a liability cannot be characterised as revenue.11 In our view, similar considerations are appropriate to the presentation of the unwinding of the discount on a provision that has been discounted using a negative nominal discount rate.

4.3.6 The effect of changes in interest rates on the discount rate applied

The standard requires the discount rate to reflect current market assessments of the time value of money. [IAS 37.47]. This means that where interest rates change, the provision should be recalculated on the basis of revised interest rates (see Example 26.11 below).

Any revision in the interest rate will give rise to an adjustment to the carrying value of the provision in addition to the unwinding of the previously estimated discount. The standard requires these movements to be disclosed in the notes to the financial statements (see 7.1 below). [IAS 37.84(e)]. However, the standard does not explicitly say how the effect of changes in interest rates should be classified in the income statement. We believe that this element should be treated separately from the effect of the passage of time, with only the charge for unwinding of the discount being classified as a finance cost. Any adjustment to the provision as a result of revising the discount rate is a change in accounting estimate, as defined in IAS 8 – Accounting Policies, Changes in Accounting Estimates and Errors (see Chapter 3 at 4.5). Accordingly, it should be reflected in the line item of the income statement to which the expense establishing the provision was originally taken and not as a component of the finance cost. Indeed, this is the approach required by IFRIC 1 in relation to provisions for decommissioning, restoration and similar liabilities in relation to assets measured using the cost model (see 6.3.1 below). However, in that case the original provision gives rise to an asset rather than an expense, so any subsequent adjustment is not included in profit or loss, [IAS 8.36], but added to or deducted from the cost of the asset to which it relates. [IFRIC 1.5]. The adjusted depreciable amount of the asset is then depreciated prospectively over its remaining useful life. [IFRIC 1.7]. Nevertheless, the effect is distinguished from the unwinding of the discount.

In addition, the standard gives no specific guidance on how or when this adjustment should be made. For example, it is unclear whether the new discount rate should be applied during the year or just at the year-end, and whether the rate should be applied to the new estimate of the provision or the old estimate. IFRIC 1 implies that the finance cost is adjusted prospectively from the date on which the liability is remeasured. Example 1 to IFRIC 1 states that if the change in the liability had resulted from a change in discount rate, instead of a change in the estimated cash flows, the change would still have been reflected in the carrying value of the related asset, but next year's finance cost would have reflected the new discount rate. [IFRIC 1.IE5]. This conclusion is consistent with the requirement in IAS 37 for the value of a provision to reflect the best estimate of the expenditure required to settle the obligation as at the end of the reporting period, [IAS 37.36], as illustrated in the following example.

In Year 2, the finance charge is based on the previous estimate of the discount rate and the revision to the estimate of the provision would be charged to the same line item in the income statement that was used to establish the provision of €93,184 at the start of Year 1.

Where market rates of interest are more volatile, entities may decide to reassess the applicable discount rate for a provision during an annual reporting period. Equally, it would be appropriate to revise this assessment as at the end of any interim reporting period during the financial year to the extent that the impact is material.

4.4 Anticipating future events that may affect the estimate of cash flows

The standard states that ‘future events that may affect the amount required to settle an obligation shall be reflected in the amount of a provision where there is sufficient objective evidence that they will occur’. [IAS 37.48]. The types of future events that the standard has in mind are advances in technology and changes in legislation.

The requirement for objective evidence means that it is not appropriate to reduce the best estimate of future cash flows simply by assuming that a completely new technology will be developed before the liability is required to be settled. There will need to be sufficient objective evidence that such future developments are likely. For example, an entity may believe that the cost of cleaning up a site at the end of its life will be reduced by future changes in technology. The amount recognised has to reflect a reasonable expectation of technically qualified, objective observers, taking account of all available evidence as to the technology that will be available at the time of the clean-up. Thus it is appropriate to include, for example, expected cost reductions associated with increased experience in applying existing technology or the expected cost of applying existing technology to a larger or more complex clean-up operation than has previously been carried out. [IAS 37.49].

Similarly, if new legislation is to be anticipated, there will need to be evidence both of what the legislation will demand and whether it is virtually certain to be enacted and implemented. In many cases sufficient objective evidence will not exist until the new legislation is enacted. [IAS 37.50].

These requirements are most likely to impact provisions for liabilities that will be settled some distance in the future, such as decommissioning costs (see 6.3 below).

4.5 Provisions that will be settled in a currency other than the entity's functional currency

Entities may sometimes expect to settle an obligation in a currency other than their functional currency. In such cases, the provision would be measured in the currency in which settlement is expected and then discounted using a discount rate appropriate for that currency. This approach is consistent with that required by IAS 36 – Impairment of Assets – for foreign currency cash flows in value in use calculations. [IAS 36.54]. The present value would be translated into functional currency at the spot exchange rate at the date at which the provision is recognised. [IAS 21.21]. If the provision is considered to be a monetary liability, i.e. it is expected to be paid in a fixed or determinable number of units of currency, [IAS 21.8], it would thereafter be retranslated at the spot exchange rate at each reporting date. [IAS 21.23]. In most cases, exchange differences arising on provisions will be taken to profit or loss in the period in which they arise, in accordance with the general rule for monetary items in IAS 21 – The Effects of Changes in Foreign Exchange Rates. [IAS 21.28].

Exchange differences arising on decommissioning provisions recognised under IAS 37 and capitalised as part of the cost of an asset under IAS 16 are considered in Chapter 43 at 10.2.

4.6 Reimbursements, insurance and other recoveries from third parties

In some circumstances an entity is able to look to a third party to reimburse part of the costs required to settle a provision or to pay the amounts directly to a third party. Examples are insurance contracts, indemnity clauses and suppliers' warranties. [IAS 37.55]. A reimbursement asset is recognised only when it is virtually certain to be received if the entity settles the obligation. The asset cannot be greater than the amount of the provision. No ‘netting off’ is allowed in the statement of financial position, with any asset classified separately from any provision. [IAS 37.53]. However, the expense relating to a provision can be shown in the income statement net of reimbursement. [IAS 37.54]. This means that if an entity has insurance cover in relation to a specific potential obligation, this is treated as a reimbursement right under IAS 37. It is not appropriate to record no provision (where the recognition criteria in the standard are met) on the basis that the entity's net exposure is expected to be zero.

The main area of concern with these requirements is whether the ‘virtually certain’ criterion that needs to be applied to the corresponding asset might mean that some reimbursements will not be capable of recognition at all. For items such as insurance contracts, this may not be an issue, as entities will probably be able to confirm the existence of cover for the obligation in question and accordingly be able to demonstrate that a recovery on an insurance contract is virtually certain if the entity is required to settle the obligation. Of course, it may be more difficult in complex situations for an entity to confirm it has cover against any loss. For other types of reimbursement, it may be more difficult to establish that recovery is virtually certain.

Except when an obligation is determined to be joint and several (see 4.7 below), any form of net presentation in the statement of financial position is prohibited. This is because the entity would remain liable for the whole cost if the third party failed to pay for any reason, for example as a result of the third party's insolvency. In such situations, the provision should be made gross and any reimbursement should be treated as a separate asset (but only when it is virtually certain that the reimbursement will be received if the entity settles the obligation). [IAS 37.56].

If the entity has no liability in the event that the third party cannot pay, then these costs are excluded from the estimate of the provision altogether because, by its very nature, there is no liability. [IAS 37.57].

In contrast, where an entity is assessing an onerous contract, it is common for entities to apply what looks like a net approach. However, because an onerous contract provision relates to the excess of the unavoidable costs over the expected economic benefits, [IAS 37.68], there is no corresponding asset to be recognised. This is discussed further at 6.2 below.

4.7 Joint and several liability

It is interesting to contrast the approach of IAS 37 to reimbursements with the case where an entity is jointly and severally liable for an obligation. Joint and several liability arises when a number of entities are liable for a single obligation (for example, to damages), both individually and collectively. The holder of the obligation in these circumstances can collect the entire amount from any single member of the group or from any and all of the members in various amounts until the liability is settled in full. Even when the members have an agreement between themselves as to how the total obligation should be divided, each member remains liable to make good any deficiency on the part of the others. This situation is different from proportionate liability, where individual members of a group might be required to bear a percentage of the total liability, but without any obligation to make good any shortfall by another member. Joint and several liability can be established in a contract, by a court judgement or under legislation.

An entity that is jointly and severally liable recognises only its own share of the obligation, based on the amount it is probable that the entity will pay. The remainder that is expected to be met by other parties is treated only as a contingent liability. [IAS 37.29, 58].

The fact that the other third parties in this situation have a direct (albeit shared) obligation for the past event itself, rather than only a contractual relationship with the entity, is enough of a difference in circumstances to allow a form of net determination of the amount to recognise. Arguably, the economic position is no different, because the entity is exposed to further loss in the event that the third parties are unable or unwilling to pay. However, IAS 37 does not treat joint and several liability in the same way as reimbursement, which would have required a liability to be set up for the whole amount with a corresponding asset recognised for the amount expected to be met by other parties.

4.8 Provisions are not reduced for gains on disposal of related assets

IAS 37 states that gains from the expected disposal of assets should not be taken into account in measuring a provision, even if the expected disposal is closely linked to the event giving rise to the provision. Such gains should be recognised at the time specified by the Standard dealing with the assets concerned. [IAS 37.51‑52]. This is likely to be of particular relevance in relation to restructuring provisions (see 6.1.4 below). However, it may also apply in other situations. Extract 26.2 at 6.3 below illustrates an example of a company excluding gains from the expected disposal of assets in determining its provision for decommissioning costs.

4.9 Changes and uses of provisions

After recognition, a provision will be re-estimated, used and released over the period up to the eventual determination of a settlement amount for the obligation. IAS 37 requires that provisions should be reviewed at the end of each reporting period and adjusted to reflect the current best estimate. If it is no longer probable that an outflow of resources embodying economic benefits will be required to settle the obligation, the provision should be reversed. [IAS 37.59]. Where discounting is applied, the carrying amount of a provision increases in each period to reflect the passage of time. This increase is recognised as a borrowing cost. [IAS 37.60]. As discussed at 4.3.5 above, the periodic unwinding of the discount is recognised as a finance cost in the income statement, and it is not a borrowing cost capable of being capitalised under IAS 23. [IFRIC 1.8].

The standard does not allow provisions to be redesignated or otherwise used for expenditures for which the provision was not originally recognised. [IAS 37.61]. In such circumstances, a new provision is created and the amount no longer needed is reversed, as to do otherwise would conceal the impact of two different events. [IAS 37.62]. This means that the questionable practice of charging costs against a provision that was set up for a different purpose is specifically prohibited.

4.10 Changes in contingent liabilities recognised in a business combination

In a business combination, the usual requirements of IAS 37 do not apply and the acquirer recognises a liability at the acquisition date for those contingent liabilities of the acquiree that represent a present obligation arising as a result of a past event and in respect of which the fair value can be measured reliably. [IFRS 3.23]. After initial recognition, and until the liability is settled, cancelled or expires, the acquirer measures the contingent liability recognised in a business combination at the higher of:

  1. the amount that would be recognised in accordance with IAS 37; and
  2. the amount initially recognised less, if appropriate, the cumulative amount of income recognised in accordance with the principles of IFRS 15. [IFRS 3.56].

This requirement does not apply to contracts accounted for in accordance with IFRS 9. See Chapter 9 at 5.6.1.B.

This requirement prevents the immediate release to post acquisition profit of any contingency recognised in a business combination.

5 CASES IN WHICH NO PROVISION SHOULD BE RECOGNISED

IAS 37 sets out three particular cases in which the recognition of a provision is prohibited. They are: future operating losses, repairs and maintenance of owned assets and staff training costs. The Interpretations Committee has also considered repeated requests relating to obligations arising on entities operating in a rate-regulated environment. The Interpretations Committee concluded that there is no justification for the recognition of a special regulatory liability, although the issue of IFRS 14 – Regulatory Deferral Accounts – in January 2014 provides some relief for first-time adopters of IFRS who have recognised regulatory deferral account balances under their previous GAAP (see 5.4 below). The common theme in these cases is that the potential obligation does not exist independently of an entity's future actions. In other words, the entity is able to change the future conduct of its business in a way that avoids the future expenditure. Only those obligations that exist independently of an entity's future actions are recognised as provisions. [IAS 37.19]. This principle is also relevant to determining the timing of recognition of a provision, whereby no liability is recognised until the obligation cannot otherwise be avoided by the entity. Examples include those arising from participation in a particular market under IFRIC 6 (see 6.7 below) and an obligation for levies imposed by government under IFRIC 21 (see 6.8 below).

5.1 Future operating losses

IAS 37 explicitly states that ‘provisions shall not be recognised for future operating losses’. [IAS 37.63]. This is because such losses do not meet the definition of a liability and the general recognition criteria of the standard. [IAS 37.64]. In particular there is no present obligation as a result of a past event. Such costs should be left to be recognised as they occur in the future in the same way as future profits.

However, it would be wrong to assume that this requirement has effectively prevented the effect of future operating losses from being anticipated, because they are sometimes recognised as a result of requirements in another standard, either in the measurement of an asset of the entity or to prevent inappropriate recognition of revenue. For example:

  • under IAS 2 – Inventories – inventories are written down to the extent that they will not be recovered from future revenues, rather than leaving the non-recovery to show up as future operating losses (see Chapter 22 at 3.3); and
  • under IAS 36 impairment is assessed on the basis of the present value of future operating cash flows, meaning that the effect of not only future operating losses but also sub-standard operating profits will be recognised (see Chapter 20). IAS 37 specifically makes reference to the fact that an expectation of future operating losses may be an indication that certain assets are impaired. [IAS 37.65].

This is therefore a rather more complex issue than IAS 37 acknowledges. Indeed, IAS 37 itself has to navigate closely the dividing line between the general prohibition of the recognition of future losses and the recognition of contractual or constructive obligations that are expected to give rise to losses in future periods.

5.2 Repairs and maintenance of owned assets

Repairs and maintenance provisions in respect of owned assets are generally prohibited under IAS 37. Under the standard, the following principles apply:

  1. provisions are recognised only for obligations existing independently of the entity's future actions (i.e. the future conduct of its business) and in cases where an entity can avoid future expenditure by its future actions, for example by changing its method of operation, it has no present obligation; [IAS 37.19]
  2. financial statements deal with an entity's position at the end of the reporting period and not its possible position in the future. Therefore, no provision is recognised for costs that need to be incurred to operate in the future; [IAS 37.18] and
  3. for an event to be an obligating event, the entity can have no realistic alternative to settling the obligation created by the event. [IAS 37.17].

These principles are applied strictly in the case of an obligation to incur repairs and maintenance costs in the future, even when this expenditure is substantial, distinct from what may be regarded as routine maintenance and essential to the continuing operations of the entity, such as a major refit or refurbishment of the asset. This is illustrated by two examples in an appendix to the standard.

Entities might try to argue that a repairs and maintenance provision should be recognised on the basis that there is a clear intention to incur the expenditure at the appointed time and that this means it is more likely than not, as at the end of the reporting period, that an outflow of resources will occur. However, the application of the three principles noted above, particularly that an entity should not provide for future operating costs, make an entity's intentions irrelevant. In the example above, recognition was not allowed because the entity could do all manner of things to avoid the obligation, including selling the asset, however unlikely that might be in the context of the entity's business or in terms of the relative cost of replacement as compared to repair. The existence of a legal requirement, probably resulting in the aircraft being grounded, was still not enough. This detachment from intention or even commercial reality, regarded by some as extreme, is most recently exhibited in the Interpretations Committee's approach to the recognition of levies imposed by government under IFRIC 21 (see 6.8 below).

The effect of the prohibition on setting up provisions for repairs obviously has an impact on presentation in the statement of financial position. It may not always, however, have as much impact on the statement of comprehensive income. This is because it is stated in the examples that depreciation would be adjusted to take account of the repairs. For example, in the case of the furnace lining, the lining should be depreciated over five years in advance of its expected repair. Similarly, in the case of the aircraft overhaul, the example in the standard states that an amount equivalent to the expected maintenance costs is depreciated over three years. The result of this is that the depreciation charge recognised in profit or loss over the life of the component of the asset requiring regular repair may be equivalent to that which would previously have arisen from the combination of depreciation and a provision for repair. This is the way IAS 16 requires entities to account for significant parts of an item of property, plant and equipment which have different useful lives (see Chapter 18 at 5.1). [IAS 16.44].

5.3 Staff training costs

In the normal course of business it is unlikely that provisions for staff training costs would be permissible, because it would normally contravene the general prohibition in the standard on the recognition of provisions for future operating costs. [IAS 37.18]. In the context of a restructuring, IAS 37 identifies staff retraining as an ineligible cost because it relates to the future conduct of the business. [IAS 37.81]. Example 26.2 at 3.1.1 above reproduces an example in the standard where the government introduces changes to the income tax system, such that an entity in the financial services sector needs to retrain a large proportion of its administrative and sales workforce in order to ensure continued compliance with financial services regulation. The standard argues that there is no present obligation until the actual training has taken place and so no provision should be recognised. We also note that in many cases the need to incur training costs is not only future operating expenditure but also fails the ‘existing independently of an entity's future actions' criterion, [IAS 37.19], in that the cost could be avoided by the entity, for example, if it withdrew from that market or hired new staff who were already appropriately qualified.

This example again illustrates how important it is to properly understand the nature of any potential ‘constructive obligation’ or ‘obligating event’ and to determine separately its financial effect in relation to past transactions and events on the one hand and in relation to the future operation of the business on the other. Otherwise, it can be easy to mistakenly argue that a provision is required, such as for training costs to ensure that staff comply with new legal requirements, on the basis that the entity has a constructive obligation to ensure staff are appropriately skilled to adequately meet the needs of its customers. However, the obligation, constructive or not, declared or not, relates to the entity's future conduct, is a future cost of operation and is therefore ineligible for recognition under the standard until the training takes place.

5.4 Rate-regulated activities

In many countries, the provision of utilities (e.g. water, natural gas or electricity) to consumers is regulated by the national government. Regulations differ between countries but often regulators operate a cost-plus system under which a utility provider is allowed to make a fixed return on investment. Under certain national GAAPs, an entity may account for the effects of regulation by recognising a ‘regulatory asset’ that reflects the increase in future prices approved by the regulator or a ‘regulatory liability’ that reflects a requirement from the regulator to reduce tariffs or improve services so as to return the benefit of earlier excess profits to customers. This issue has for a long time been a matter of significant interest as entities in those countries adopt IFRS, because the recognition of these regulatory assets and liabilities is prohibited under IFRS. Just as the ability to charge higher prices for goods services to be rendered in the future does not meet the definition of an intangible asset in IAS 38 – Intangible Assets (see Chapter 17 at 11.1), the requirement to charge a lower price for the delivery of goods and services in the future does not meet the definition of a past obligating event, or a liability, in IAS 37.

A liability is defined in IAS 37 as ‘a present obligation of the entity arising from past events, the settlement of which is expected to result in an outflow from the entity of resources embodying economic benefits’. [IAS 37.10]. The return to customers of amounts mandated by a regulator depends on future events including:

  • future rendering of services;
  • future volumes of output (generally consisting of utilities such as water or electricity) consumed by users; and
  • the continuation of regulation.

Similar considerations apply to actions that a regulator may require entities to complete in the future, such as an obligation to invest in equipment to improve efficiency. Other than decommissioning obligations (see 6.3 below), such items do not meet the definition of a liability because there needs to be a present obligation at the end of the reporting period before a liability can be recognised. Such a regulatory obligation that fails to qualify for recognition under IAS 37 is illustrated in Extract 26.1 at 3.1.1 above.

Whilst the requirements of IAS 37 and the Conceptual Framework issued in 2010 are clear in this respect, their perceived inflexibility in this regard has been identified as a significant barrier that prevents the entities affected by it from adopting IFRS as a whole.12 In 2012, the IASB decided on a two-tier approach to address this.13 As a result, in January 2014, the IASB issued IFRS 14, an interim Standard on the accounting for regulatory deferral accounts that would apply for first-time adopters of IFRS until the completion of a more comprehensive project. [IFRS 14.BC10]. IFRS 14 became effective for annual periods beginning on or after 1 January 2016, with early application permitted. [IFRS 14.C1].

The Standard can be applied in only very limited circumstances. A first-time adopter is permitted (but not required) to apply IFRS 14 in its first IFRS financial statements if, and only if, it conducts rate-regulated activities (as defined in the Standard) and recognised amounts that qualify as regulatory deferral account balances in its financial statements prepared under its previous GAAP. [IFRS 14.5]. An entity shall not change its accounting policies in order to start to recognise regulatory deferral account balances. [IFRS 14.13].

Entities can apply IFRS 14 after first-time adoption if, and only if, they had elected to apply the Standard in their first IFRS financial statements and had recognised regulatory deferral account balances in those financial statements. [IFRS 14.6]. Therefore, the scope for applying this standard does not extend to existing IFRS reporters; nor to first-time adopters whose previous GAAP did not allow for the recognition of regulatory assets and liabilities; nor even to first-time adopters whose previous GAAP allowed such recognition but the entity chose not to do so.

The requirements of first-time adoption of IFRS are discussed further in Chapter 5.

As regards its comprehensive standard-setting project, the Board aims to develop an accounting model that will require rate-regulated companies to provide information about their incremental rights to add amounts, and incremental obligations to deduct amounts, in determining the future rates to be charged to customers as a result of goods or services already supplied. That information will supplement the information provided by applying IFRS 15 and is intended to provide users of financial statements with clearer and more complete information about the financial performance, financial position and future cash flow prospects of entities affected by rate-regulation. The core principle of the model is that an entity recognises:

  1. a regulatory asset for the entity's present right to add an amount to the future rates charged to customers because the total allowed compensation for the goods or services already supplied exceeds the amount already charged to customers;
  2. a regulatory liability for the entity's present obligation to deduct an amount from the future rates charged to customers because the total allowed compensation for the goods or services already supplied is lower than the amount already charged to customers; and
  3. regulatory income or regulatory expense, being the movement between the opening and closing amounts of regulatory assets and regulatory liabilities.14

Discussions of the proposed model have continued during 2019, and a further discussion paper or exposure draft is expected in the first half of 2020.15

6 SPECIFIC EXAMPLES OF PROVISIONS AND CONTINGENCIES

IAS 37 expands on its general recognition and measurement requirements by including more specific requirements for particular situations, i.e. future restructuring costs and onerous contracts. This section discusses those situations, looks at other examples, including those addressed in an appendix to the Standard and other areas where the Interpretations Committee has considered how the principles of IAS 37 should be applied.

6.1 Restructuring provisions

IAS 37 allows entities to recognise restructuring provisions, but it has specific rules on the nature of obligations and the types of cost that are eligible for inclusion in such provisions, as discussed below. These rules ensure that entities recognise only obligations that exist independently of their future actions, [IAS 37.19], and that provisions are not made for future operating costs and losses. [IAS 37.63].

6.1.1 Definition

IAS 37 defines a restructuring as ‘a programme that is planned and controlled by management, and materially changes either:

  1. the scope of a business undertaken by an entity; or
  2. the manner in which that business is conducted’. [IAS 37.10].

This is said to include:

  1. the sale or termination of a line of business;
  2. the closure of business locations in a country or region or the relocation of business activities from one country or region to another;
  3. changes in management structure, for example, eliminating a layer of management; and
  4. fundamental reorganisations that have a material effect on the nature and focus of the entity's operations. [IAS 37.70].

This definition is very wide and whilst it may be relatively straightforward to establish whether an operation has been sold, closed or relocated, the determination of whether an organisational change is fundamental, material or just part of a process of continuous improvement is a subjective judgement. Whilst organisational change is a perennial feature in most business sectors, entities could be tempted to classify all kinds of operating costs as restructuring costs and thereby invite the user of the financial statements to perceive them in a different light from the ‘normal’ costs of operating in a dynamic business environment. Even though the requirements in IAS 37 prevent such costs being recognised too early, the standard still leaves the question of classification open to judgement. As such there can be a tension between the permitted recognition of expected restructuring costs, subject to meeting the criteria set out at 6.1.2 below, and the general prohibition in IAS 37 against provision for future operating losses, which is discussed at 5.1 above.

IAS 37 emphasises that when a restructuring meets the definition of a discontinued operation under IFRS 5, additional disclosures may be required under that standard (see Chapter 4 at 3). [IAS 37.9].

6.1.2 Recognition of a restructuring provision

IAS 37 requires that restructuring costs are recognised only when the general recognition criteria in the standard are met, i.e. there is a present obligation (legal or constructive) as a result of a past event, in respect of which a reliable estimate can be made of the probable cost. [IAS 37.71]. The standard's specific requirements for the recognition of a provision for restructuring costs seek to define the circumstances that give rise to a constructive obligation and thereby restrict the recognition of a provision to cases when an entity:

  1. has a detailed formal plan for the restructuring identifying at least:
    1. the business or part of a business concerned;
    2. the principal locations affected;
    3. the location, function, and approximate number of employees who will be compensated for terminating their services;
    4. the expenditures that will be undertaken; and
    5. when the plan will be implemented; and
  2. has raised a valid expectation in those affected that it will carry out the restructuring by starting to implement that plan or announcing its main features to those affected by it. [IAS 37.72].

The standard gives examples of the entity's actions that may provide evidence that the entity has started to implement a plan, quoting the dismantling of plant or selling of assets, or the public announcement of the main features of the plan. However, it also emphasises that the public announcement of a detailed plan to restructure will not automatically create an obligation; the important principle is that the announcement is made in such a way and in sufficient detail to give rise to valid expectations in other parties such as customers, suppliers and employees that the restructuring will be carried out. [IAS 37.73].

The standard also suggests that for an announced plan to give rise to a constructive obligation, its implementation needs to be planned to begin as soon as possible and to be completed in a timeframe that makes significant changes to the plan unlikely. Any extended period before commencement of implementation, or if the restructuring will take an unreasonably long time, will mean that recognition of a provision is premature, because the entity is still likely to have a chance of changing the plan. [IAS 37.74].

In summary, these conditions require the plan to be detailed and specific, to have gone beyond the directors' powers of recall and to be put into operation without delay or significant alteration.

The criteria set out above for the recognition of provisions mean that a board decision, if it is the only relevant event arising before the end of the reporting period, is not sufficient. This message is reinforced specifically in the standard, the argument being made that a constructive obligation is not created by a management decision. There will only be a constructive obligation where the entity has, before the end of the reporting period:

  1. started to implement the restructuring plan; or
  2. announced the main features of the restructuring plan to those affected by it in a sufficiently specific manner to raise a valid expectation in them that the entity will carry out the restructuring. [IAS 37.75].

If the restructuring is not started or announced in detail until after the end of the reporting period, no provision is recognised. Instead, the entity discloses a non-adjusting event after the reporting period. [IAS 37.75, IAS 10.22(e)].

The following examples in IAS 37 illustrate how a constructive obligation for a restructuring may or may not be created.

The standard acknowledges that there will be circumstances where a board decision could trigger recognition, but not on its own. Only if earlier events, such as negotiations with employee representatives for termination payments or with purchasers for the sale of an operation, have been concluded subject only to board approval would the decision of the board create an obligation. In such circumstances, it is reasoned that when board approval has been obtained and communicated to the other parties, the entity is committed to restructure, assuming all other conditions are met. [IAS 37.76].

There is also discussion in the standard of the situation that may arise in some countries where, for example, employee representatives may sit on the board, so that a board decision effectively communicates the decision to them, which may result in a constructive obligation to restructure. [IAS 37.77].

In practice it can be very difficult to determine whether it is appropriate to recognise a provision for the future costs of a restructuring programme. The determination of whether an organisational change is fundamental, material or just part of a process of continuous improvement is a subjective judgement. Once it has been established that the activities in question constitute a restructuring rather than an ongoing operating cost, it can be difficult to determine whether management's actions before the reporting date have been sufficient to have ‘raised a valid expectation in those affected’. [IAS 37.72]. Even if a trigger point is easily identifiable, such as the date of an appropriately detailed public announcement, it might not necessarily commit management to the whole restructuring, but only to specific items of expenditure such as redundancy costs. When the announcement is less clear, referring for example to consultations, negotiations or voluntary arrangements, particularly with employees, judgement is required. Furthermore, taken on its own, the ‘valid expectation’ test is at least as open to manipulation as one based on the timing of a board decision. Entities anxious to accelerate or postpone recognition of a liability could do so by advancing or deferring an event that signals such a commitment, such as a public announcement, without any change to the substance of their position.

In these situations it is important to consider all the related facts and circumstances and not to ‘home in’ on a single recognition criterion. The objective of the analysis is to determine whether there is a past obligating event at the reporting date. The guidance in the standard about restructuring, referring as it does to constructive obligations and valid expectations is ultimately aimed at properly applying the principle in IAS 37 that only those obligations arising from past events and existing independently of an entity's future actions are recognised as provisions. [IAS 37.19]. In essence, a restructuring provision qualifies for recognition if, as at the reporting date, it relates to a detailed plan of action from which management cannot realistically withdraw.

6.1.3 Recognition of obligations arising from the sale of an operation

IAS 37 has some further specific rules governing when to recognise an obligation arising on the sale of an operation, stating that no obligation arises for the sale of an operation until the entity is committed to the sale, i.e. there is a binding sale agreement. [IAS 37.78]. Thus a provision cannot be made for a loss on sale unless there is a binding sale agreement by the end of the reporting period. The standard says that this applies even when an entity has taken a decision to sell an operation and announced that decision publicly, it cannot be committed to the sale until a purchaser has been identified and there is a binding sale agreement. Until there is such an agreement, the entity will be able to change its mind and indeed will have to take another course of action if a purchaser cannot be found on acceptable terms. [IAS 37.79].

Even in cases where it is part of a larger restructuring that qualifies for recognition under IAS 37, an obligation arising from the sale is not recognised until there is a binding sale agreement. Instead, the assets of the operation must be reviewed for impairment under IAS 36. This may therefore mean that an expense is recorded in the income statement; it is just that the expense gives rise to a reduction of the carrying amount of assets rather than the recognition of a liability. The standard also recognises that where a sale is only part of a restructuring, the entity could be committed to the other parts of restructuring before a binding sale agreement is in place. [IAS 37.79]. Hence, the costs of the restructuring will be recognised over different reporting periods.

6.1.4 Costs that can (and cannot) be included in a restructuring provision

Having met the specific tests in the standard for the recognition of a restructuring provision at the end of the reporting period, IAS 37 imposes further criteria to restrict the types of cost that can be provided for. Presumably these additional restrictions are intended to ensure that the entity does not contravene the general prohibition in IAS 37 against provision for future operating losses. [IAS 37.63].

A restructuring provision should include only the direct expenditures arising from the restructuring, which are those that are both:

  1. necessarily entailed by the restructuring; and
  2. not associated with the ongoing activities of the entity. [IAS 37.80].

The standard gives specific examples of costs that may not be included within the provision, because they relate to the future conduct of the business. Such costs include:

  1. retraining or relocating continuing staff;
  2. marketing; or
  3. investment in new systems and distribution networks. [IAS 37.81].

Because these costs relate to the future conduct of the business, they are recognised on the same basis as if they arose independently of a restructuring. [IAS 37.81]. In most cases, this means that the costs are recognised as the related services are provided.

This example shows that individual classes of expenditure should be disaggregated into components that distinguish those elements associated with ongoing activities. Even if expenditure would not have been incurred without the restructuring activity, its association with ongoing activities means that it is ineligible for inclusion in a provision. IAS 37 requires the cost to be both necessarily entailed by the restructuring and not associated with the ongoing activities of the entity. [IAS 37.80].

For that reason, whilst the cost of making employees redundant is an eligible restructuring cost, any incremental amounts paid to retain staff to ensure a smooth transition of operations from one location to another are not eligible because they are incurred to facilitate ongoing activities. IAS 19 requires these to be treated as short-term employee benefits to the extent that they are expected to be settled within 12 months after the end of the reporting period.16 Similarly, whilst the costs of dismantling plant and equipment intended to be scrapped is an eligible restructuring cost, the costs of dismantling plant and equipment intended to be relocated and installed at the new site is ineligible, because it is associated with ongoing activities.

A further rule in IAS 37 is that the provision should not include identifiable future operating losses up to the date of the restructuring, unless they relate to an onerous contract. [IAS 37.82]. This means that even if the operation being reorganised is loss-making, its ongoing costs are not provided for. This is consistent with the general prohibition against the recognition of provisions for future operating losses. [IAS 37.63].

The general requirement in the standard that gains from the expected disposal of assets cannot be taken into account in the measurement of provisions, [IAS 37.51], is also relevant to the measurement of restructuring provisions, even if the sale of the asset is envisaged as part of the restructuring. [IAS 37.83]. Whilst the expected disposal proceeds from asset sales might have been a significant element of the economic case for a restructuring, the income from disposal is not anticipated just because it is part of a restructuring plan.

6.2 Onerous contracts

Although future operating losses in general cannot be provided for, IAS 37 requires that ‘if an entity has a contract that is onerous, the present obligation under the contract shall be recognised and measured as a provision’. [IAS 37.66].

The standard notes that many contracts (for example, some routine purchase orders) can be cancelled without paying compensation to the other party, and therefore there is no obligation. However, other contracts establish both rights and obligations for each of the contracting parties. Where events make such a contract onerous, the contract falls within the scope of the standard and a liability exists which is recognised. Executory contracts that are not onerous fall outside the scope of the standard. [IAS 37.67].

IAS 37 defines an onerous contract as ‘a contract in which the unavoidable costs of meeting the obligations under the contract exceed the economic benefits expected to be received under it’. [IAS 37.10]. This requires that the contract is onerous to the point of being directly loss-making, not simply uneconomic by reference to current prices.

IAS 37 considers that ‘the unavoidable costs under a contract reflect the least net cost of exiting from the contract, which is the lower of the cost of fulfilling it and any compensation or penalties arising from failure to fulfil it’. [IAS 37.68]. This evaluation does not require an intention by the entity to fulfil or to exit the contract. It does not even require there to be specific terms in the contract that apply in the event of its termination or breach. Its purpose is to recognise only the unavoidable costs to the entity, which in the absence of specific clauses in the contract relating to termination or breach could include an estimation of the cost of ceasing to honour the contract and having the other party go to court for compensation for the resultant breach.

There is some diversity in practice in how entities determine the unavoidable costs of fulfilling their obligations under a contract. In December 2018, the IASB issued the Exposure Draft Onerous Contracts – Cost of Fulfilling a Contract (Proposed amendments to IAS 37) that proposed to clarify that the costs of fulfilling a contract comprise the costs that relate directly to the contract, rather than only the incremental costs of the contract. Examples of costs that relate directly to a contract to provide goods or services would include:

  1. direct labour (for example, salaries and wages of employees who manufacture and deliver the goods or provide the services directly to the counterparty);
  2. direct materials (for example, supplies used in fulfilling the contract);
  3. allocations of costs that relate directly to contract activities (for example, costs of contract management and supervision, insurance, and depreciation of tools, equipment and right-of-use assets used in fulfilling the contract);
  4. costs explicitly chargeable to the counterparty under the contract; and
  5. other costs incurred only because an entity entered into the contract (for example, payments to subcontractors).

The exposure draft also notes that general and administrative costs do not relate directly to a contract unless they are explicitly chargeable to the counterparty under the contract.17

The Board discussed a summary of feedback on the Exposure draft in May 2019 18 and at the time of writing, are deciding the project direction.19

As noted above, IAS 37 defines an onerous contract as ‘a contract in which the unavoidable costs of meeting the obligations under the contract exceed the economic benefits expected to be received under it’. [IAS 37.10]. There is also some diversity in practice in how entities determine the economic benefits expected to be received under a contract. However, the Board decided not to address this matter as part of the Exposure Draft because expanding the project beyond the clarification of costs to fulfil a contract could cause delay.20

There is a subtle yet important distinction between making a provision in respect of the unavoidable costs under a contract (reflecting the least net cost of what the entity has to do) compared to making an estimate of the cost of what the entity intends to do. The first is an obligation, which merits the recognition as a provision, whereas the second is a choice of the entity, which fails the recognition criteria because it does not exist independently of the entity's future actions, [IAS 37.19], and is therefore akin to a future operating loss.

In considering the extent to which the contract is onerous, Entity P in the example above should not concentrate solely on the net cost of the excess units of $1,575,000 (105,000 × $15) that it is contracted to purchase but which are expected to be left unsold. Instead, the entity should consider all of the related benefits of the contract, which includes the profits earned as a result of having a secure source of supply of components. Therefore the supply contract is onerous (directly loss making) only to the extent of the costs not covered by related revenues, justifying a provision of $675,000 ($1,575,000 – $900,000).

IAS 37 requires that any impairment loss that has occurred on assets dedicated to an onerous contact is recognised before establishing a provision for the onerous contract. [IAS 37.69].

6.2.1 Onerous leases

As discussed at 2.2.1.B above, IAS 37 specifically applies to leases only in limited circumstances. IAS 37 specifically applies only to:

  • leases that become onerous before the commencement date of the lease; and
  • short-term leases (as defined in IFRS 16) and leases for which the underlying asset is of low value that are accounted for in accordance with paragraph 6 of IFRS 16 and that have become onerous. [IAS 37.5(c)].

The IASB noted in paragraph BC 72 of IFRS 16 that it ‘…decided not to specify any particular requirements in IFRS 16 for onerous contracts. The IASB made this decision because …(a) for leases that have already commenced, no requirements are necessary. After the commencement date, an entity will appropriately reflect an onerous lease contract by applying the requirements of IFRS 16. For example, a lessee will determine and recognise any impairment of right-of-use assets applying IAS 36 Impairment of Assets.’ However, this raises the question how an entity should account for onerous variable lease payments that do not depend on an index or a rate and are not included in the measurement of right-of-use assets or lease liabilities under IFRS 16 (e.g. variable payments related to property taxes or non-lease components that have not been separated from the lease components, in accordance with paragraph 15 of IFRS 16). It is not immediately obvious whether such onerous variable lease payments fall within the scope of IFRS 16 or IAS 37.

As discussed in Chapter 20, at 7.1.8.A, we believe that contractual variable lease payments that are not included in the lease liability (such as those that are not based on an index or rate) should be reflected in cash flow forecasts used for value-in-use calculations for impairment testing purposes. Once the right-of-use is fully impaired, entities may need to use their judgement to determine whether any further onerous lease provisions should be recognised under the requirements of IAS 37. If an entity exercises significant judgement in determining the most appropriate approach, consideration should be given to the disclosure requirements in paragraph 122 of IAS 1. See Chapter 3 at 5.1.1.B.

6.2.2 Contracts with customers that are, or have become, onerous

As IFRS 15 contains no specific requirements to address contracts with customers that are, or have become, onerous, IAS 37 applies to such contracts. [IAS 37.5(g)]. In assessing whether a contract is onerous, an entity should compare the unavoidable costs of meeting the obligations under the contract to the economic benefits expected to be received under it. The unavoidable costs under the contract are the lower of the cost of fulfilling the contract and any compensation or penalties arising from failure to fulfil the contract. [IAS 37.68]. As discussed at 6.2 above, in December 2018, the IASB issued an exposure draft that proposed to clarify that the costs of fulfilling a contract comprise the costs that relate directly to the contract, rather than only the incremental costs of the contract.21

One question that may arise, is how an entity should account for an onerous contract with a customer when the contract includes several ‘over time’ performance obligations that are satisfied consecutively. Since the requirements for onerous contracts are outside the scope of IFRS 15, an entity's accounting for onerous contracts does not affect the accounting for its revenue from contracts with customers in accordance with IFRS 15. Therefore, an entity must use an ‘overlay’ approach, which consists of two steps:

  1. apply the requirements of IFRS 15 to measure progress in satisfying each performance obligation, and account for the related costs when incurred in accordance with the applicable standards; and
  2. at the end of each reporting period, apply IAS 37 to determine if the remaining contract as a whole is onerous. If the entity concludes that the remaining contract as a whole is onerous, it recognises a provision only to the extent that the amount of the remaining unavoidable costs under the contract exceed the remaining economic benefits to be received under it.

This approach is illustrated below.

The effect of an onerous contract provision, or a change in the provision, is recognised as an expense in profit or loss and not as an adjustment to revenue.

As provisions for onerous contracts with customers are in the scope of IAS 37, they should be classified as provisions in the balance sheet and disclosed in accordance with IAS 37 (see 7.1 below). Onerous contract provisions are outside the scope of IFRS 15 and should not be included within contract liabilities.

Since the definition of an onerous contract in IAS 37 refers only to a contract, the unit of account to determine whether an onerous contract exists is the contract itself, rather than the performance obligations identified in accordance with IFRS 15. [IAS 37.10]. As a result, the entity must consider the entire remaining contract, including remaining revenue to be recognised for unsatisfied, or partially unsatisfied, performance obligations and the remaining costs to fulfil those performance obligations.

As discussed at 6.2 above, there is diversity in practice in how entities determine the economic benefits expected to be received under a contract for the purposes of assessing whether a contract is onerous. Where a contract with a customer contains an element of variable consideration, it is likely that judgement will be required in assessing the economic benefits expected to be received under a contract. This may particularly be the case where an entity is required to constrain the estimate of variable consideration to be included in the transaction price for revenue recognition purposes under IFRS 15. Variable consideration under IFRS 15 is discussed further in Chapter 29 at 2.2.

6.3 Decommissioning provisions

Decommissioning costs arise when an entity is required to dismantle or remove an asset at the end of its useful life and to restore the site on which it has been located, for example, when an oil rig or nuclear power station reaches the end of its economic life.

Rather than allowing an entity to build up a provision for the required costs over the life of the facility, IAS 37 requires that the liability is recognised as soon as the obligation arises. This is because the construction of the asset (and the environmental damage caused by it) creates the past obligating event requiring restoration in the future. [IAS 37 IE Example 3].

The accounting for decommissioning costs is dealt with in IAS 37 by way of an example relating to an oil rig in an offshore oilfield (see Example 26.5 at 3.3 above). A provision is recognised at the time of constructing the oil rig in relation to the eventual costs that relate to its removal and the restoration of damage caused by building it. Additional provisions are recognised over the life of the oil field to reflect the need to reverse damage caused during the extraction of oil. [IAS 37 IE Example 3]. The total decommissioning cost is estimated, discounted to its present value and it is this amount which forms the initial provision. This ‘initial estimate of the costs of dismantling and removing the item and restoring the site’ is added to the corresponding asset's cost. [IAS 16.16]. Thereafter, the asset is depreciated over its useful life, while the discounted provision is progressively unwound, with the unwinding charge shown as a finance cost, as discussed at 4.3.5 above.

The effect of discounting on the statement of comprehensive income is to split the cost of the eventual decommissioning into two components: an expense based on the present value of the expected future cash outflows; and a finance element representing the unwinding of the discount. The overall effect is to produce a rising pattern of cost over the life of the facility, often with much of the total cost of the decommissioning classified as a finance cost.

AngloGold Ashanti's accounting policies and provisions note in respect of decommissioning obligations and restoration obligations are shown in the following extract.

6.3.1 Changes in estimated decommissioning costs (IFRIC 1)

IAS 37 requires provisions to be revised annually to reflect the current best estimate of the provision. [IAS 37.59]. However, the standard gives no guidance on accounting for changes in the decommissioning provision. Similarly, IAS 16 is unclear about the extent to which an item's carrying amount should be affected by changes in the estimated amount of dismantling and site restoration costs that occur after the estimate made upon initial measurement. This was addressed by the IASB with the publication of IFRIC 1 in May 2004. [IFRIC 1.1].

IFRIC 1 applies to any decommissioning, restoration or similar liability that has been both included as part of the cost of an asset measured in accordance with IAS 16 or as part of the cost of a right-of-use asset in accordance with IFRS 16 and recognised as a liability in accordance with IAS 37. [IFRIC 1.2]. It addresses how the effect of the following events that change the measurement of an existing decommissioning, restoration or similar liability should be accounted for:

  1. a change in the estimated outflow of resources embodying economic benefits (e.g. cash flows) required to settle the obligation;
  2. a change in the current market-based discount rate (this includes changes in the time value of money and the risks specific to the liability); and
  3. an increase that reflects the passage of time (also referred to as the unwinding of the discount). [IFRIC 1.3].

IFRIC 1 requires that (c) above, the periodic unwinding of the discount, is recognised in profit or loss as a finance cost as it occurs. [IFRIC 1.8]. The Interpretations Committee concluded that the unwinding of the discount is not a borrowing cost as defined in IAS 23, and thus cannot be capitalised under that standard. [IFRIC 1.BC26‑27].

For a change caused by (a) or (b) above, however, the adjustment is taken to the income statement only in specific circumstances. Any revision to the provision (other than to reflect the passage of time) is first recognised in the carrying value of the related asset or in other comprehensive income, depending on whether the asset is measured at cost or using the revaluation model. [IFRIC 1.4‑7].

If the related asset is measured using the cost model, the change in the liability should be added to or deducted from the cost of the asset to which it relates. Where the change gives rise to an addition to cost, the entity should consider the need to test the new carrying value for impairment. This is particularly relevant for assets approaching the end of their useful life, as their remaining economic benefits are often small compared to the potential changes in the related decommissioning liability. Reductions over and above the remaining carrying value of the asset are recognised immediately in profit or loss. [IFRIC 1.5]. The adjusted depreciable amount of the asset is then depreciated prospectively over its remaining useful life. [IFRIC 1.7]. IFRIC 1 includes the following illustrative example.

In illustrating the requirements of the Interpretation, the example in IFRIC 1 reduces the carrying value of the whole asset (comprising its construction cost and decommissioning cost) by the reduction in the present value of the decommissioning provision. The solution set out in the example does not treat the decommissioning element as a separate component of the asset. Had this been the case, the component would have had accumulated depreciation as at 31 December 2020 of $2,500,000 ($10,000,000 × 10/40), giving a carrying amount of $7,500,000 at that date and a gain of $500,000 when reduced by the decrease in the provision of $8,000,000. Accordingly, we believe that the example in IFRIC 1 indicates that it would not be appropriate to recognise any gain until the carrying value of the whole asset is extinguished.

If the related asset is measured using the revaluation model, changes in the liability alter the revaluation surplus or deficit previously recognised for that asset. Decreases in the provision are recognised in other comprehensive income and increase the value of the revaluation surplus in respect of the asset, except that:

  1. a decrease in the provision should be recognised in profit or loss to the extent that it reverses a previous revaluation deficit on that asset that was recognised in profit or loss; and
  2. if a decrease in the provision exceeds the carrying amount of the asset that would have been recognised under the cost model, the excess should be recognised in profit or loss. [IFRIC 1.6].

Increases in the provision are recognised in profit or loss, except that they should be recognised in other comprehensive income, and reduce the revaluation surplus, to the extent of any credit balance existing in the revaluation surplus in respect of that asset. Changes in the provision might also indicate the need for the asset (and therefore all assets in the same class) to be revalued. [IFRIC 1.6].

The illustrative examples in IFRIC 1 address this alternative.

The depreciation expense for 2014 is therefore $3,420,000 ($126,600,000 ÷ 37) and the discount expense for 2013 is $580,000 (5% of $11,600,000). On 31 December 2014, the decommissioning liability (before any adjustment) is $12,180,000 and the discount rate has not changed. However, on that date, the entity estimates that, as a result of technological advances, the present value of the decommissioning liability has decreased by $5,000,000. Accordingly, the entity adjusts the decommissioning liability to $7,180,000. To determine the extent to which any of the change to the provision is recognised in profit or loss, the entity has to keep a record of revaluations previously recognised in profit or loss; the carrying amount of the asset that would have been recognised under the cost model; and the previous revaluation surplus relating to that asset. [IFRIC 1.6]. In this example, the whole of the adjustment is taken to revaluation surplus, because it does not exceed the carrying amount that would have been recognised for the asset under the cost model of $103,000 (see below). [IFRIC 1.IE6‑10].

In addition, the entity decides that a full valuation of the asset is needed at 31 December 2014, in order to ensure that the carrying amount does not differ materially from fair value. Suppose that the asset is now valued at $107,000,000, which is net of an allowance of $7,180,000 for the reduced decommissioning obligation. The valuation of the asset for financial reporting purposes, before deducting this allowance, is therefore $114,180,000. The effect on the revaluation reserve of the revision to the estimate of the decommissioning provision and the new valuation can be illustrated in the table below. [IFRIC 1.IE11‑12].

Cost model Revaluation Revaluation reserve
$'000 $'000 $'000
Carrying amount as at 31 December 2013 111,000 126,600 15,600
Depreciation charge for 2014 (3,000) (3,420)
Carrying amount as at 31 December 2014 108,000 123,180
Revision to estimate of provision (5,000)
Revaluation adjustment in 2014 (9,000) (9,000)
103,000 114,180
Provision as at 31 December 2013 11,600 11,600
Unwinding of discount @ 5% 580 580
Revision to estimate (5,000) (5,000) 5,000
Provision as at 31 December 2014 7,180 7,180
Carrying amount less provision 95,820 107,000 11,600

As indicated at 4.3.6 above, IAS 37 is unclear whether a new discount rate should be applied during the year or just at the year-end, and whether the rate should be applied to the new estimate of the provision or the old estimate. Although IFRIC 1 requires that changes in the provision resulting from a change in the discount rate is added to, or deducted from, the cost of the related asset in the current period, it does not deal specifically with these points. However, Example 1 in the illustrative examples to IFRIC 1 indicates that a change in discount rate would be accounted for in the same way as other changes affecting the estimate of a provision for decommissioning, restoration and similar liabilities. That is, it is reflected as a change in the liability at the time the revised estimate is made and the new estimate is discounted at the revised discount rate from that point on. [IFRIC 1.IE5].

When accounting for revalued assets to which decommissioning liabilities attach, the illustrative example in IFRIC 1 states that it is important to understand the basis of the valuation obtained. For example:

  1. if an asset is valued on a discounted cash flow basis, some valuers may value the asset without deducting any allowance for decommissioning costs (a ‘gross’ valuation), whereas others may value the asset after deducting an allowance for decommissioning costs (a ‘net’ valuation), because an entity acquiring the asset will generally also assume the decommissioning obligation. For financial reporting purposes, the decommissioning obligation is recognised as a separate liability, and is not deducted from the asset. Accordingly, if the asset is valued on a net basis, it is necessary to adjust the valuation obtained by adding back the allowance for the liability, so that the liability is not counted twice. This is the case in Example 26.18 above;
  2. if an asset is valued on a depreciated replacement cost basis, the valuation obtained may not include an amount for the decommissioning component of the asset. If it does not, an appropriate amount will need to be added to the valuation to reflect the depreciated replacement cost of that component. [IFRIC 1.IE7].

6.3.2 Changes in legislation after construction of the asset

The scope of IFRIC 1 is set out in terms of any existing decommissioning, restoration or similar liability that is both recognised as part of the cost of the asset under IAS 16 or as part of the cost of a right-of-use asset in accordance with IFRS 16; and recognised as a liability in accordance with IAS 37. [IFRIC 1.2]. The Interpretation does not address the treatment of obligations arising after the asset has been constructed, for example as a result of changes in legislation. [IFRIC 1.BC23]. Nevertheless, in our opinion the cost of the related asset should be measured in accordance with the principles set out in IFRIC 1 regardless of whether the obligation exists at the time of constructing the asset or arises later in its life.

As discussed at 3.3 in Chapter 18, IAS 16 makes no distinction in principle between the initial costs of acquiring an asset and any subsequent expenditure upon it. In both cases any and all expenditure has to meet the recognition rules, and be expensed in profit or loss if it does not. IAS 16 states that the cost of an item of property, plant and equipment includes ‘the initial estimate of the costs of dismantling and removing the item and restoring the site on which it is located, the obligation for which an entity incurs either when the item is acquired or as a consequence of having used the item during a particular period for purposes other than to produce inventories during that period.’ [IAS 16.16(c)]. For example, the introduction of new legislation to require the clean-up of sites that cease to be used as gasoline filling stations would give rise to the recognition of a decommissioning provision and, to the extent that the clean-up obligation arose as a result of the construction of the filling stations, an increase in the carrying value of the properties. Similarly, IFRS 16 states that the cost of a right-of-use asset includes ‘an estimate of costs to be incurred by the lessee in dismantling and removing the underlying asset, restoring the site on which it is located or restoring the underlying asset to the condition required by the terms and conditions of the lease, unless those costs are incurred to produce inventories. The lessee incurs the obligation for those costs either at the commencement date or as a consequence of having used the underlying asset during a particular period.’ [IFRS 16.24(d)].

Both IAS 16 and IFRS 16 require an entity to apply IAS 2 to the costs of obligations for dismantling, removing and restoring the site on which an item is located that are incurred during a particular period as a consequence of having used the item to produce inventories during that period. [IAS 16.18, IFRS 16.25]. For example, the cost of restoring the site of a quarry would be reflected as part of the cost of the aggregate extracted from it, and not added to the carrying value of the site. Accordingly, if an entity previously had no obligation to restore the site and new legislation was introduced after 25% of the site had been excavated and 80% of that output had been sold, then 80% of the new estimate of the restoration cost would be expensed; 20% added to the cost of inventory; and none added to the carrying value of the site.

When changes in legislation give rise to a new decommissioning, restoration or similar liability that is added to the carrying amount of the related asset, it would be appropriate to perform an impairment review in accordance with IAS 36 (see Chapter 20).

6.3.3 Funds established to meet an obligation (IFRIC 5)

Some entities may participate in a decommissioning, restoration or environmental rehabilitation fund, the purpose of which is to segregate assets to fund some or all of the costs of decommissioning for which the entity has to make a provision under IAS 37. IFRIC 5 was issued in December 2004 to address this issue, referring to decommissioning to mean not only the dismantling of plant and equipment but also the costs of undertaking environmental rehabilitation, such as rectifying pollution of water or restoring mined land. [IFRIC 5.1].

Contributions to these funds may be voluntary or required by regulation or law, and the funds may have one of the following common structures:

  • funds that are established by a single contributor to fund its own decommissioning obligations, whether for a particular site, or for a number of geographically dispersed sites;
  • funds that are established with multiple contributors to fund their individual or joint decommissioning obligations, where contributors are entitled to reimbursement for decommissioning expenses to the extent of their fund contributions plus any actual earnings on those contributions less their share of the costs of administering the fund. Contributors may have an obligation to make potential additional contributions, for example, in the event of the bankruptcy of another contributor;
  • funds that are established with multiple contributors to fund their individual or joint decommissioning obligations when the required level of contributions is based on the current activity of a contributor, but the benefit obtained by that contributor is based on its past activity. In such cases there is a potential mismatch in the amount of contributions made by a contributor (based on current activity) and the value realisable from the fund (based on past activity). [IFRIC 5.2].

Such funds generally have the following features:

  • the fund is separately administered by independent trustees;
  • entities (contributors) make contributions to the fund, which are invested in a range of assets that may include both debt and equity investments, and are available to help pay the contributors' decommissioning costs. The trustees determine how contributions are invested, within the constraints set by the fund's governing documents and any applicable legislation or other regulations;
  • the contributors retain the obligation to pay decommissioning costs. However, contributors are able to obtain reimbursement of decommissioning costs from the fund up to the lower of the decommissioning costs incurred and the entity's share of assets of the fund; and
  • the contributors may have restricted or no access to any surplus of assets of the fund over those used to meet eligible decommissioning costs. [IFRIC 5.3].

IFRIC 5 applies to accounting in the financial statements of a contributor for interests arising from decommissioning funds that have both the following features:

  • the assets are administered separately (either by being held in a separate legal entity or as segregated assets within another entity); and
  • a contributor's right to access the assets is restricted. [IFRIC 5.4].

A residual interest in a fund that extends beyond a right to reimbursement, such as a contractual right to distributions once all the decommissioning has been completed or on winding up the fund, may be an equity instrument within the scope of IFRS 9, and is not within the scope of IFRIC 5. [IFRIC 5.5].

The issues addressed by IFRIC 5 are:

  1. How should a contributor account for its interest in a fund?
  2. When a contributor has an obligation to make additional contributions, for example, in the event of the bankruptcy of another contributor, how should that obligation be accounted for? [IFRIC 5.6]
6.3.3.A Accounting for an interest in a fund

IFRIC 5 requires the contributor to recognise its obligations to pay decommissioning costs as a liability and recognise its interest in the fund separately, unless the contributor is not liable to pay decommissioning costs even if the fund fails to pay. [IFRIC 5.7].

The contributor determines whether it has control, joint control or significant influence over the fund by reference to IFRS 10 – Consolidated Financial Statements, IFRS 11 – Joint Arrangements – and IAS 28 – Investments in Associates and Joint Ventures. If the contributor determines that it has such control, joint control or significant influence, it should account for its interest in the fund in accordance with those standards (see Chapters 6, 12 and 11 respectively). [IFRIC 5.8].

Otherwise, the contributor should recognise the right to receive reimbursement from the fund as a reimbursement in accordance with IAS 37 (see 4.6 above). This reimbursement should be measured at the lower of:

  • the amount of the decommissioning obligation recognised; and
  • the contributor's share of the fair value of the net assets of the fund attributable to contributors. [IFRIC 5.9].

This ‘asset cap’ means that the asset recognised in respect of the reimbursement rights can never exceed the recognised liability. Accordingly, rights to receive reimbursement to meet decommissioning liabilities that have yet to be recognised as a provision are not recognised. [IFRIC 5.BC14]. Although many respondents expressed concern about this asset cap and argued that rights to benefit in excess of this amount give rise to an additional asset, separate from the reimbursement asset, the Interpretations Committee, despite having sympathy with the concerns, concluded that to recognise such an asset would be inconsistent with the requirement in IAS 37 that ‘the amount recognised for the reimbursement should not exceed the amount of the provision’. [IFRIC 5.BC19‑20].

Changes in the carrying value of the right to receive reimbursement other than contributions to and payments from the fund should be recognised in profit or loss in the period in which these changes occur. [IFRIC 5.9].

The effect of this requirement is that the amount recognised in the statement of comprehensive income relating to the reimbursement bears no relation to the expense recognised in respect of the provision, particularly for decommissioning liabilities where most changes in the measurement of the provision are not taken to the profit or loss immediately, but are recognised prospectively over the remaining useful life of the related asset (see 6.3.1 above).

One company that has been affected by the ‘asset cap’ is Fortum as shown below. In this extract, the company observes that because IFRS does not allow the asset to exceed the amount of the provision, [IFRIC 5.BC19‑20], it recognises a reimbursement asset in its statement of financial position that is lower than its actual share of the fund.

6.3.3.B Accounting for obligations to make additional contributions

IFRIC 5 requires that when a contributor has an obligation to make potential additional contributions, for example, in the event of the bankruptcy of another contributor or if the value of the investments held by the fund decreases to an extent that they are insufficient to fulfil the fund's reimbursement obligations, this obligation is a contingent liability that is within the scope of IAS 37. The contributor shall recognise a liability only if it is probable that additional contributions will be made. [IFRIC 5.10].

6.3.3.C Gross presentation of interest in the fund and the decommissioning liability

IFRIC 5 requires the contributor to a fund to recognise its obligations to pay decommissioning costs as a liability and recognise its interest in the fund separately, unless the contributor is not liable to pay decommissioning costs even if the fund fails to pay. [IFRIC 5.7]. Accordingly, in most cases it would not be appropriate to offset the decommissioning liability and the interest in the fund.

The Interpretations Committee reached this conclusion because IAS 37 requires an entity that remains liable for expenditure to recognise a provision even where reimbursement is available and to recognise a separate reimbursement asset only when the entity is virtually certain that it will be received when the obligation is settled. [IFRIC 5.BC7]. The Interpretations Committee also noted that the conditions in IAS 32 – Financial Instruments: Presentation – for offsetting a financial asset and a financial liability would rarely be met because of the absence of a legal right of set off and the likelihood that settlement will not be net or simultaneous. [IAS 32.42]. Arguments that the existence of a fund allows derecognition of the liability by analogy to IAS 39;22 or a net presentation similar to a pension fund, were also rejected. [IFRIC 5.BC8].

6.3.3.D Disclosure of interests arising from decommissioning, restoration and environmental rehabilitation funds

IFRIC 5 requires the following disclosures:

  • a contributor should disclose the nature of its interest in a fund and any restrictions on access to the assets in the fund; [IFRIC 5.11]
  • when a contributor has an obligation to make potential additional contributions that is not recognised as a liability (see 6.3.3.B above), it should provide the contingent liability disclosures required by IAS 37 (see 7.2 below); [IFRIC 5.12] and
  • when a contributor accounts for its right to receive reimbursement from the fund as a reimbursement right under IAS 37 in accordance with paragraph 9 of IFRIC 5 (see 6.3.3.A above), it should disclose the amount of the expected reimbursement and the amount of any asset that has been recognised for that expected reimbursement. [IFRIC 5.13].

6.3.4 Interaction of leases with asset retirement obligations

An entity may sometimes (expect to) use a leased asset to carry out decommissioning or remediation work for which it has recognised a decommissioning, remediation or asset retirement provision. For example, at the end of life of an oil field, an entity may use a leased ship or rig to undertake the plugging and abandonment of oil wells. The entity may have included the estimated cost of plugging and abandonment of the wells in the decommissioning provision set up at the commencement of oil production. If an entity uses leased assets to carry out decommissioning or remediation work for which it recognised a decommissioning, remediation, or asset retirement provision, the question arises as to whether, at lease commencement, the entity's recognition of a lease liability for the leased assets in accordance with IFRS 16 results in derecognition of the asset retirement obligation recognised in the balance sheet. Given that, prior to the commencement of any asset retirement obligation related activities, the entity still has an obligation to rehabilitate under IAS 37, it cannot derecognise the asset retirement obligation. Instead, it now has a separate lease liability for the financing of the lease of the asset. Accordingly, acquiring the right-of-use asset does not result in the derecognition of the asset retirement obligation liability, rather it would be the activity undertaken or output of the asset which would ultimately settle the asset retirement obligation. This is discussed further in Chapter 43 at 17.7.

6.4 Environmental provisions – general guidance in IAS 37

The standard illustrates its recognition requirements in two examples relating to environmental provisions. The first deals with the situation where it is virtually certain that legislation will be enacted which will require the clean-up of land already contaminated. In these circumstances, the virtual certainty of new legislation being enacted means that the entity has a present legal obligation as a result of the past event (contamination of the land), requiring a provision to be recognised. [IAS 37 IE Example 2A]. However, in its discussion about what constitutes an obligating event, the standard notes that ‘differences in circumstances surrounding enactment make it impossible to specify a single event that would make the enactment of a law virtually certain. In many cases, it will be impossible to be virtually certain of the enactment of a law until it is enacted.’ [IAS 37.22]. The second example deals with a similar situation, except that the entity is not expected to be legally required to clean it up. Nevertheless, the entity has a widely publicised environmental policy undertaking to clean up all contamination that it causes, and has a record of honouring this policy. In these circumstances a provision is still required because the entity has created a valid expectation that it will clean up the land, meaning that the entity has a present constructive obligation as a result of past contamination. [IAS 37 IE Example 2B]. It is therefore clear that where an entity causes environmental damage and has a present legal or constructive obligation to make it good; it is probable that an outflow of resources will be required to settle the obligation; and a reliable estimate can be made of the amount, a provision will be required. [IAS 37.14].

One company making provision for environmental costs is AkzoNobel, which describes some of the uncertainties relating to its measurement in the extract below.

If the expenditure relating to an environmental obligation is not expected to be incurred for some time, a significant effect of the standard is its requirement that provisions should be discounted, which can have a material impact.

6.5 Liabilities associated with emissions trading schemes

A number of countries around the world either have, or are developing, schemes to encourage reduced emissions of pollutants, in particular of greenhouse gases. These schemes comprise tradable emissions allowances or permits, an example of which is a ‘cap and trade’ model whereby participants are allocated emission rights or allowances equal to a cap (i.e. a maximum level of allowable emissions) and are permitted to trade those allowances. A cap and trade emission rights scheme typically has the following features:23

  • an entity participating in the scheme (participant) is set a target to reduce its emissions to a specified level (the cap). The participant is issued allowances equal in number to its cap by a government or government agency. Allowances may be issued free of charge, or participants may pay the government for them;
  • the scheme operates for defined compliance periods;
  • participants are free to buy and sell allowances;
  • if at the end of the compliance period a participant's actual emissions exceeded its emission rights, the participant will incur a penalty;
  • in some schemes emission rights may be carried forward to future periods; and
  • the scheme may provide for brokers – who are not themselves participants – to buy and sell emission rights.

In response to diversity in the accounting for cap and trade emission rights schemes, the Interpretations Committee added this matter to its agenda. Accordingly, in December 2004 the IASB issued IFRIC 3 to address the accounting for emission allowances that arise from cap and trade emission rights schemes.

IFRIC 3 took the view that a cap and trade scheme did not give rise to a net asset or liability, but that it gave rise to various items that were to be accounted for separately:24

  1. an asset for allowances held – Allowances, whether allocated by government or purchased, were to be regarded as intangible assets and accounted for under IAS 38. Allowances issued for less than fair value were to be measured initially at their fair value;25
  2. a government grant – When allowances are issued for less than fair value, the difference between the amount paid and fair value was a government grant that should be accounted for under IAS 20 – Accounting for Government Grants and Disclosure of Government Assistance. Initially the grant was to be recognised as deferred income in the statement of financial position and subsequently recognised as income on a systematic basis over the compliance period for which the allowances were issued, regardless of whether the allowances were held or sold;26
  3. a liability for the obligation to deliver allowances equal to emissions that have been made – As emissions are made, a liability was to be recognised as a provision that falls within the scope of IAS 37. The liability was to be measured at the best estimate of the expenditure required to settle the present obligation at the end of the reporting period. This would usually be the present market price of the number of allowances required to cover emissions made up to the end of the reporting period.27

However, the interpretation met with significant resistance because application of IFRIC 3 would result in a number of accounting mismatches:28

  • a measurement mismatch between the assets and liabilities recognised in accordance with IFRIC 3;
  • a mismatch in the location in which the gains and losses on those assets are reported; and
  • a possible timing mismatch because allowances would be recognised when they are obtained – typically at the start of the year – whereas the emission liability would be recognised during the year as it is incurred.

Consequently, the IASB decided in June 2005 to withdraw IFRIC 3 despite the fact that it considered it to be ‘an appropriate interpretation of existing IFRSs’.29 The IASB activated its project on emission trading schemes in December 2007 but work was suspended in November 2010. In May 2012, IASB members gave their unanimous support to giving priority to restarting research on emission trading schemes.30 In February 2015, the project was renamed from ‘Emission trading schemes’ to ‘Pollutant pricing mechanisms’. This change was to reflect a decision by the Board in January 2015 to broaden the scope of the project to consider a variety of schemes that use emission allowances and other financial tools to manage the emission of pollutants. The Board also decided in January 2015 that they would take a ‘fresh start’ approach to the project rather than starting from the tentative decisions made in the previous project.31 After considering feedback from the 2015 Agenda Consultation, the Board decided to transfer the project to its research pipeline. The Board planned no immediate further work on the project, but expected to carry out work on the project before the next agenda consultation, which is expected in 2021.32

In the meantime, entities can either:

  1. apply IFRIC 3, which despite having been withdrawn, is considered to be an appropriate interpretation of existing IFRS; or
  2. develop its own accounting policy for cap and trade schemes based on the hierarchy of authoritative guidance in IAS 8.

A more detailed discussion of the issues and methods applied in practice is covered in Chapter 17 at 11.2.

6.6 Green certificates compared to emissions trading schemes

Some countries have launched schemes to promote the production of power from renewable sources based on green certificates – also known as renewable energy certificates (RECs), green tags, or tradable renewable certificates.

In a green certificates system, a producer of electricity from renewable sources is granted certificates by the government based on the power output (kWh) of green electricity produced. These certificates may be used in the current and future compliance periods as defined by the particular scheme. The certificates can be sold separately. Generally the cost to produce green electricity is higher than the cost of producing an equivalent amount of electricity generated from non-renewable sources, although this is not always the case. Distributors of electricity sell green electricity at the same price as other electricity.

In a typical green certificates scheme, distributors of electricity to consumers (businesses, households etc.) are required to remit a number of green certificates based on the kWh of electricity sold on an annual basis. Distributors must therefore purchase green certificates in the market (such certificates having been sold by producers). If a distribution company does not have the number of required certificates, it is required to pay a penalty to the environmental agency. Once the penalty is paid, the entity is discharged of its obligations to remit certificates.

It is this requirement to remit certificates that creates a market in and gives value to green certificates (the value depends on many variables but primarily on the required number of certificates that have to be delivered relative to the amount of power that is produced from renewable sources, and the level of penalty payable if the required number of certificates are not remitted).

There are similarities between green certificates and emission rights. However, green certificates are granted to generators of cleaner energy as an incentive for ‘good’ production achieved, irrespective of whether or not there is a subsequent sale of that cleaner energy to an end consumer. For a distributor of energy, a green certificate gives a similar ‘right to pollute’ as an emission right except that a distributor of energy under a green certificate regime must acquire the certificates from the market (i.e. they are not granted to the distributor by the government). As with emission rights, the topic of green certificates cuts across a number of different areas of accounting, not just provisions. A more detailed discussion of the issues and methods applied in practice is covered in Chapter 17 at 11.3.

6.7 EU Directive on ‘Waste Electrical and Electronic Equipment’ (IFRIC 6)

This Directive regulates the collection, treatment, recovery and environmentally sound disposal of waste electrical or electronic equipment (WE&EE).33 It applies to entities involved in the manufacture and resale of electrical or electronic equipment, including entities (both European and Non-European) that import such equipment into the EU. As member states in the EU began to implement this directive into their national laws, it gave rise to questions about when the liability for the decommissioning of WE&EE should be recognised. The Directive distinguishes between ‘new’ and ‘historical’ waste and between waste from private households and waste from sources other than private households. New waste relates to products sold after 13 August 2005. All household equipment sold before that date is deemed to give rise to historical waste for the purposes of the Directive. [IFRIC 6.3].

The Directive states that the cost of waste management for historical household equipment should be borne by producers of that type of equipment that are in the market during a period to be specified in the applicable legislation of each Member State (the measurement period). The Directive states that each Member State shall establish a mechanism to have producers contribute to costs proportionately ‘e.g. in proportion to their respective share of the market by type of equipment.’ [IFRIC 6.4].

The Interpretations Committee was asked to determine in the context of the decommissioning of WE&EE what constitutes the obligating event in accordance with paragraph 14(a) of IAS 37 (discussed at 3.1.1 above) for the recognition of a provision for waste management costs:

  • the manufacture or sale of the historical household equipment?
  • participation in the market during the measurement period?
  • the incurrence of costs in the performance of waste management activities? [IFRIC 6.8]

IFRIC 6 was issued in September 2005 and provides guidance on the recognition, in the financial statements of producers, of liabilities for waste management under the EU Directive on WE&EE in respect of sales of historical household equipment. [IFRIC 6.6]. The interpretation addresses neither new waste nor historical waste from sources other than private households. The Interpretations Committee considers that the liability for such waste management is adequately covered in IAS 37. However, if, in national legislation, new waste from private households is treated in a similar manner to historical waste from private households, the principles of IFRIC 6 are to apply by reference to the hierarchy set out in IAS 8 (see Chapter 3 at 4.3). The IAS 8 hierarchy is also stated to be relevant for other regulations that impose obligations in a way that is similar to the cost attribution model specified in the EU Directive. [IFRIC 6.7].

IFRIC 6 regards participation in the market during the measurement period as the obligating event in accordance with paragraph 14(a) of IAS 37. Consequently, a liability for waste management costs for historical household equipment does not arise as the products are manufactured or sold. Because the obligation for historical household equipment is linked to participation in the market during the measurement period, rather than to production or sale of the items to be disposed of, there is no obligation unless and until a market share exists during the measurement period. It is also noted that the timing of the obligating event may also be independent of the particular period in which the activities to perform the waste management are undertaken and the related costs incurred. [IFRIC 6.9].

The following example, which is based on one within the accompanying Basis for Conclusions on IFRIC 6, illustrates its requirements.

Some constituents asked the Interpretations Committee to consider the effect of the following possible national legislation: the waste management costs for which a producer is responsible because of its participation in the market during a specified period (for example 2020) are not based on the market share of the producer during that period but on the producer's participation in the market during a previous period (for example 2019). The Interpretations Committee noted that this affects only the measurement of the liability and that the obligating event is still participation in the market during 2019. [IFRIC 6.BC7].

IFRIC 6 notes that terms used in the interpretation such as ‘market share’ and ‘measurement period’ may be defined very differently in the applicable legislation of individual Member States. For example, the length of the measurement period might be a year or only one month. Similarly, the measurement of market share and the formulae for computing the obligation may differ in the various national legislations. However, all of these examples affect only the measurement of the liability, which is not within the scope of the interpretation. [IFRIC 6.5].

6.8 Levies imposed by governments

When governments or other public authorities impose levies on entities in relation to their activities, as opposed to income taxes and fines or other penalties, it is not always clear when the liability to pay a levy arises and a provision should be recognised. In May 2013, the Interpretations Committee issued IFRIC 21 to address this question. [IFRIC 21.2, 7]. The Interpretation does not address the accounting for the costs arising out of an obligation to pay a levy, for example to determine whether an asset or expense should be recorded. Other standards should be applied in this regard. [IFRIC 21.3].

The Interpretation became mandatory for accounting periods beginning on or after 1 January 2014, although it permitted earlier application. [IFRIC 21.A1]. It requires that, for levies within its scope, an entity should recognise a liability only when the activity that triggers payment, as identified by the relevant legislation, occurs. [IFRIC 21.8].

6.8.1 Scope of IFRIC 21

A levy is defined as an outflow of resources embodying economic benefits that is imposed by governments on entities in accordance with legislation, other than:

  1. those outflows of resources that are within the scope of other Standards (such as income taxes that are within the scope of IAS 12); and
  2. fines or other penalties that are imposed for breaches of the legislation. [IFRIC 21.4].

In addition to income taxes (see Chapter 33) and fines, the Interpretation does not apply to contractual arrangements with government in which the entity acquires an asset (see Chapters 17 and 18) or receives services; and it is not required to be applied to liabilities that arise from emission trading schemes (see 6.5 above). [IFRIC 21.5, 6]. Although IFRIC 21 does not apply to income taxes in scope of IAS 12, the Interpretations Committee concluded in 2006 that any taxes not within the scope of other standards (such as IAS 12) are within the scope of IAS 37. Therefore such taxes may be within the scope of IFRIC 21. [IFRIC 21.BC4].

IFRIC 21 was developed to address concerns over the timing of recognition for government-imposed levies in which the obligation to pay depended upon participation in a particular market on a specified date. However, the definition of levy in IFRIC 21 has resulted in the scope of the interpretation being broader than entities might have expected. The term ‘levy’ may not be widely used across jurisdictions, and may be referred to as a charge, duty or a tax, for example. However, it is not the terminology, but the nature of the payment, that should be considered when determining if it is in the scope of IFRIC 21.

Entities should consider all payments imposed by governments pursuant to legislation to determine whether they are in scope of IFRIC 21. The interpretation provides a broad definition of government, including municipal, provincial, state, federal or international governments or government agencies or organisations controlled or administered by government. [IFRIC 21.4].

IFRIC 21 clarifies that both levies that give rise to a liability under IAS 37, and levies whose timing or amounts are certain are within scope of the interpretation. [IFRIC 21.2]. Therefore, the scope of IFRIC 21 is broader than IAS 37. For example, a non-refundable fixed fee imposed by government payable at a specific date may be a levy within the scope of IFRIC 21.

In some cases, payments may pass through one or more non-governmental bodies or entities before being received by the government. In our view, IFRIC 21 does not distinguish between recipients of the payment; the key factor is whether the payment is required by law. Therefore, as long as the payments are required by law, they are generally considered to be imposed by the government. [IFRIC 21.4].

Some of the legislation relating to payments imposed by governments can be complex, so entities should carefully analyse the facts and circumstances to determine whether a payment falls within the scope of IFRIC 21. However, where entities are making payments for any of the following items, it may be necessary to assess for any potential IFRIC 21 impacts:

  • taxes other than income taxes, e.g. property tax, land tax and capital-based tax;
  • certain fees, concessions, contributions or royalty fees imposed on industries which are regulated by government, e.g. telecommunications, mining, airline, banking, insurance, dairy produce and energy and natural resources; and
  • transaction taxes based on activity in a specified market, e.g. banking and insurance.

6.8.2 Recognition and measurement of levy liabilities

For levies within the scope of the Interpretation, the activity that creates the obligation under the relevant legislation to pay the levy is the obligating event for recognition purposes. [IFRIC 21.8]. In many cases this activity is related to the entity's participation in a relevant market at a specific date or dates. The Interpretation states that neither a constructive nor a present obligation arises as a result of being economically compelled to continue operating; or from any implication of continuing operations in the future arising from the use of the going concern assumption in the preparation of financial statements. [IFRIC 21.9, 10].

When a levy is payable progressively, for example as the entity generates revenues, the entity recognises a liability over a period of time on that basis. This is because the obligating event is the activity that generates revenues. [IFRIC 21.11]. If an obligation to pay a levy is triggered in full as soon as a minimum threshold is reached, such as when the entity commences generating sales or achieves a certain level of revenue, the liability is recognised in full on the first day that the entity reaches that threshold. [IFRIC 21.12]. If an entity pays over amounts to government before it is determined that an obligation to pay that levy exists, it recognises an asset. [IFRIC 21.14].

The table below summarises the illustrative examples that accompany IFRIC 21, which provide guidelines on how to account for the timing of the recognition for the various types of levies: [IFRIC 21.IE1]

Illustrative examples Obligating event Recognition of liability
Levy triggered progressively as revenue is generated in a specified period. Generation of revenue in the specified period. Recognise progressively.
A liability must be recognised progressively because, at any point in time during the specified period, the entity has a present obligation to pay a levy on revenues generated to date.
Levy triggered in full as soon as revenue is generated in one period, based on revenues from a previous period. First generation of revenue in subsequent period. Full recognition at that point in time.
Where an entity generates revenue in one period, which serves as the basis for measuring the amount of the levy, the entity does not become liable for the levy, and therefore cannot recognise a liability, until it first starts generating revenue in the subsequent period.
Levy triggered in full if the entity operates as a bank at the end of the annual reporting period. Operating as a bank at the end of the reporting period. Full recognition at the end of the annual reporting period.
Before the end of the annual reporting period, the entity has no present obligation to pay a levy, even if it is economically compelled to continue operating as a bank in the future. The liability is recognised only at the end of the annual reporting period.
Levy triggered if revenues are above a minimum specified threshold (e.g. when a certain level of revenue has been achieved) Reaching the specified minimum threshold. Recognise an amount consistent with the obligation at that point of time.
A liability is recognised only at the point that the specified minimum threshold is reached. For example, a levy is triggered when an entity generates revenues above specified thresholds: 0% for the first $50 million and 2% above $50 million.
In this example, no liability is accrued until the entity's revenues reach the revenue threshold of $50 million.

As set out in the table above, when a levy is triggered progressively, for example, as the entity generates revenues, the entity recognises a liability over the period of time on that basis. Some examples of progressive-type levies are set out below.

When the legislation provides that a levy is triggered by an entity operating in a market only at the end of its annual reporting period, no liability is recognised until the last day of the annual reporting period. No amount is recognised before that date in anticipation of the entity still operating in the market. Accordingly, a provision would not be permitted to be recognised in interim financial statements if the obligating event occurs only at the end of the annual reporting period. [IFRIC 21.IE1 Example 3]. The accounting treatment in interim reports is discussed in Chapter 41 at 9.7.5.

6.8.3 Recognition of an asset or expense when a levy is recorded

IFRIC 21 only provides guidance on when to recognise a liability, which is the credit side of the journal entry. The interpretation specifically states that it does not address whether the debit side of the journal entry is an asset or an expense, [IFRIC 21.3], except in the case of prepaid levies. [IFRIC 21.14].

Prepayments may be fairly common in arrangements in which the legislation requires entities to pay levies in advance and where the obligating events for these levies are progressive. For example, property taxes that are paid in advance at a specified date (e.g. 1 January) for an obligating event that relates to future periods (e.g. 1 January to 31 December). In such instances, the entity would recognise the prepaid levy as an asset. [IFRIC 21.14]. In this scenario, the prepaid levy would then be amortised over the period.

Aside from prepaid levies, there are also instances when the assessment of expensing the liability or recognising a corresponding asset requires the application of other standards, such as IAS 2, IAS 16 or IAS 38. Given that levies are imposed by government and arise from non-exchange transactions, there would not typically be a clear linkage to future economic benefits. Consequentially, if the incurrence of the liability does not give rise to an identifiable future economic benefit to the entity, the recognition of an asset would be inappropriate as the definition of an asset would not be met. In such cases, the debit side would therefore be to an expense account.

In the case where asset recognition is appropriate under other IFRS standards, levies are generally not expected to give rise to a stand-alone asset in its own right, given that payments for the acquisition of goods or services are scoped out of IFRIC 21. [IFRIC 21.5]. However, a levy may form part of the acquisition costs of some other asset, provided it meets the asset recognition criteria in other IFRS standards. For example, an entity may be required to pay an import duty to the government under legislation for any large cargo trucks purchased from overseas. The entity uses the large cargo trucks as part of their operations to transport their goods to customers locally and therefore capitalises the trucks as part of property, plant and equipment under IAS 16. The import duty that is payable under the legislation may give rise to an IFRIC 21 levy, which would also be capitalised as part of the cost of the asset. [IAS 16.16(a)].

6.8.4 Payments relating to taxes other than income tax

As discussed at 6.8.1 above, IFRIC 21 does not apply to income taxes in scope of IAS 12. However, the Interpretations Committee concluded in 2006 that any taxes not within the scope of other standards (such as IAS 12) are within the scope of IAS 37. Therefore such taxes may be within the scope of IFRIC 21. [IFRIC 21.BC4].

In 2018, the Interpretations Committee discussed a fact pattern where an entity is in dispute with a tax authority in respect of a tax other than income tax. The entity determines that it is probable that it does not have an obligation for the disputed amount and consequently, it does not recognise a liability applying IAS 37. The entity nonetheless pays the disputed amount to the tax authority, either voluntarily or because it is required to do so. The entity has no right to a refund of the amount before resolution of the dispute. Upon resolution, either the tax authority returns the payment to the entity (if the outcome of the dispute is favourable to the entity) or the payment is used to settle the tax liability (if the outcome of the dispute is unfavourable to the entity).

In March 2018, the Interpretations Committee observed that the payment made by the entity gives rise to an asset as defined in the Conceptual Framework that was in issue at the time. The Conceptual Framework (2010) defines an asset as a resource controlled by the entity as a result of past events and from which future economic benefits are expected to flow to the entity. [CF(2010) 4.4(a)]. On making the payment, the entity has a right to receive future economic benefits either in the form of cash or by using the payment to settle the tax liability. The payment is not a contingent asset as defined in IAS 37 because it is an asset, and not a possible asset, of the entity. The entity therefore recognises an asset when it makes the payment to the tax authority.34

Also in March 2018, the IASB issued a revised Conceptual Framework for Financial Reporting. The revised framework became effective immediately for the IASB and IFRS Interpretations Committee and is effective from 1 January 2020 for entities that use the Conceptual Framework to develop accounting policies when no IFRS standard applies to a particular transaction. Paragraph 4.3 of the revised Conceptual Framework defines an asset as a present economic resource controlled by the entity as a result of past events. In May 2018, the Interpretations Committee considered whether the new Conceptual Framework would change its observation that the payment made by the entity gives rise to an asset, and not a possible asset (contingent asset), of the entity. The Committee tentatively concluded that the new Conceptual Framework would not change its previous observation. The Committee also noted that this matter had raised questions about the role of the new Conceptual Framework and decided to consult the Board on these questions.35

6.9 Dilapidation and other provisions relating to leased assets

As discussed at 5.2 above, it is not appropriate to recognise provisions that relate to repairs and maintenance of owned assets. However, the position can be different in the case of obligations relating to assets held under leases. Nevertheless, the same principles under IAS 37 apply:

  1. provisions are recognised only for obligations existing independently of the entity's future actions (i.e. the future conduct of its business) and in cases where an entity can avoid future expenditure by its future actions, for example by changing its method of operation, it has no present obligation; [IAS 37.19]
  2. financial statements deal with an entity's position at the end of the reporting period and not its possible position in the future. Therefore, no provision is recognised for costs that need to be incurred to operate in the future; [IAS 37.18] and
  3. for an event to be an obligating event, the entity must have no realistic alternative to settling the obligation created by the event. [IAS 37.17].

Leases often contain clauses which specify that the lessee should incur periodic charges for maintenance, make good dilapidations or other damage occurring during the rental period or return the asset to the configuration that existed as at inception of the lease. These contractual provisions may restrict the entity's ability to change its future conduct to avoid the expenditure. For example, the entity might not be able to transfer the asset in its existing condition. Alternatively, the entity could return the asset to avoid the risk of incurring costs relating to any future damage, but would have to make a payment in relation of dilapidations incurred to date. Therefore the contractual obligations in a lease could create an environment in which a present obligation could exist as at the reporting date from which the entity cannot realistically withdraw.

Under principle (b) above, any provision should reflect only the conditions as at the reporting date. This means that a provision for specific damage done to the leased asset would merit recognition, as the event giving rise to the obligation under the lease has certainly occurred. For example, if an entity has erected partitioning or internal walls in a leasehold property and under the lease these must be removed at the end of the term, then provision should be made for this cost (on a discounted basis, if material) at the time of putting up the partitioning or the walls. In this case, an equivalent asset would be recognised and depreciated over the term of the lease. This is similar to a decommissioning provision discussed at 6.3 above. Another example would be where an airline company leases aircraft, and upon delivery of the aircraft has made changes to the interior fittings and layout, but under the leasing arrangements must return the asset to the configuration that existed as at inception of the lease.

What is less clear is whether a more general provision can be built up over time for maintenance charges and dilapidation costs in relation to a leased asset. It might be argued that in this case, the event giving rise to the obligation under the lease is simply the passage of time, and so a provision can be built up over time. However, in our view the phrase ‘the event giving rise to the obligation under the lease’ indicates that a more specific event must occur; there has to be specific evidence of dilapidation etc. before any provision can be made. That is, it cannot be assumed that the condition of a leased asset has deteriorated simply because time has passed. However, in practice, it will often be the case that dilapidations do occur over time, in which case a dilapidations provision should be recognised as those dilapidations occur over the lease term. Example 26.12 at 5.2 above dealt with an owned aircraft that by law needs overhauling every three years, but no provision could be recognised for such costs. Instead, IAS 37 suggests that an amount equivalent to the expected maintenance costs is treated as a separate part of the asset and depreciated over three years. Airworthiness requirements for the airline industry are the same irrespective of whether the aircraft is owned or leased. So, if an airline company leases the aircraft, should a provision be made for the overhaul costs? The answer will depend on the terms of the lease.

For a lessee, the accounting for contractual overhaul obligations will require careful consideration. IFRS 16 requires the depreciation requirements of IAS 16 to be applied in the subsequent measurement of a right-of-use asset. [IFRS 16.31]. Under the depreciation requirements of IAS 16, each part of an asset with a cost that is significant in relation to the total cost of the item must be depreciated separately. [IAS 16.44]. The application of this ‘component approach’ to the right-of-use asset could imply an approach similar to that suggested in Example 26.12 at 5.2 above for owned assets. An entity should apply judgement in determining an appropriate accounting policy for how the application of component accounting for the right-of-use asset would interact with the recognition of provisions for regulatory overhauls under IAS 37.

The fact that a provision for repairs can be made at all for leased assets might appear inconsistent with the case where the asset is owned by the entity. In that case, as discussed at 5.2 above, no provision for repairs could be made. There is, however, a difference between the two situations. Where the entity owns the asset, it has the choice of selling it rather than repairing it, and so the obligation is not independent of the entity's future actions. However, in the case of an entity leasing the asset, it can have a contractual obligation to repair any damage from which it cannot walk away.

6.10 Warranty provisions

Warranty provisions are specifically addressed in one of the examples appended to IAS 37. However, as noted at 2.2.1.B above, an entity would apply IFRS 15 to separately purchased warranties and to those warranties determined to provide the customer with a service in addition to the assurance that the product complies with agreed-upon specifications. Only if a customer does not have the option to purchase a warranty separately and the warranty is determined only to provide assurance that the product complies with agreed-upon specifications would an entity consider IAS 37. [IFRS 15.B30]. The requirements for warranties falling within the scope of IFRS 15 are considered further in Chapter 31.

The following example illustrates how warranty costs are addressed if IAS 37 applies.

The assessment of the probability of an outflow of resources is made across the population as a whole, and not using each potential claim as the unit of account. [IAS 37.24]. On past experience, it is probable that there will be some claims under the warranties, so a provision is recognised.

The assessment over the class of obligations as a whole makes it more likely that a provision will be recognised, because the probability criterion is considered in terms of whether at least one item in the population will give rise to a payment. Recognition then becomes a matter of reliable measurement and entities calculate an expected value of the estimated warranty costs. IAS 37 discusses this method of ‘expected value’ and illustrates how it is calculated in an example of a warranty provision. [IAS 37.39]. See Example 26.6 at 4.1 above.

An example of a company that makes a warranty provision is Philips Group as shown below:

6.11 Litigation and other legal claims

IAS 37 includes an example of a court case in its appendix to illustrate how its principles distinguish between a contingent liability and a provision in such situations. See Example 26.4 at 3.2.1 above. However, the assessment of the particular case in the example is clear-cut. In most situations, assessing the need to provide for legal claims is one of the most difficult tasks in the field of provisioning. This is due mainly to the inherent uncertainty in the judicial process itself, which may be very long and drawn out. Furthermore, this is an area where either provision or disclosure might risk prejudicing the outcome of the case, because they give an insight into the entity's own view on the strength of its defence that can assist the claimant.

In principle, whether a provision should be made will depend on whether the three conditions for recognising a provision are met, i.e.

  1. there is a present obligation as a result of a past event;
  2. it is probable that an outflow of resources embodying economic benefits will be required to settle the obligation; and
  3. a reliable estimate can be made of the amount of the obligation. [IAS 37.14].

In situations such as these, a past event is deemed to give rise to a present obligation if, taking account of all available evidence (including, for example, the opinion of experts), it is more likely than not that a present obligation exists at the end of the reporting period. [IAS 37.15]. The evidence to be considered includes any additional evidence occurring after the end of the reporting period. Accordingly, if on the basis of the evidence it is concluded that a present obligation is more likely than not to exist, a provision will be required, assuming the other conditions are met. [IAS 37.16].

Condition (b) will be met if the transfer of economic benefits is more likely than not to occur, that is, it has a probability greater than 50%. In making this assessment, it is likely that account should be taken of any expert advice.

As far as condition (c) is concerned, the standard takes the view that a reasonable estimate can generally be made and it is only in extremely rare cases that this will not be the case. [IAS 37.25].

Clearly, whether an entity should make provision for the costs of settling a case or to meet any award given by a court will depend on a reasoned assessment of the particular circumstances, based on appropriate legal advice.

6.12 Refunds policy

Example 26.1 at 3.1.1 above reflects an example given in the appendix of IAS 37 of a retail store that has a policy of refunding goods returned by dissatisfied customers. There is no legal obligation to do so, but the company's policy of making refunds is generally known. The example argues that the conduct of the store has created a valid expectation on the part of its customers that it will refund purchases. The obligating event is the original sale of the item, and the probability of some economic outflow is greater than 50%, as there will nearly always be some customers demanding refunds. Hence, a provision should be made, [IAS 37 IE Example 4], presumably calculated on the ‘expected value’ basis.

This example is straightforward when the store has a very specific and highly publicised policy on refunds. However, some stores' policies on refunds might not be so clear cut. A store may offer refunds under certain conditions, but not widely publicise its policy. In these circumstances, there might be doubt as to whether the store has created a valid expectation on the part of its customers that it will honour all requests for a refund.

As with warranty costs (discussed at 6.10 above), the accounting treatment of refunds impinges into the area of revenue recognition. Under IFRS 15, an entity recognises the amount of expected returns as a refund liability, representing its obligation to return the customer's consideration. [IFRS 15.55]. As noted at 2.2.1.B above, other than contracts with customers that are, or have become onerous, contracts in scope of IFRS 15 are outside the scope of IAS 37. [IAS 37.5].

6.13 Self insurance

Another situation where entities sometimes make provisions is self insurance which arises when an entity decides not to take out external insurance in respect of a certain category of risk because it would be uneconomic to do so. The same position may arise when a group insures its risks with a captive insurance subsidiary, the effects of which have to be eliminated on consolidation. In fact, the term ‘self insurance’ is potentially misleading, since it really means that the entity is not insured at all and will settle claims from third parties from its own resources in the event that it is found to be liable. Accordingly, the recognition criteria in IAS 37 should be applied, with a provision being justified only if there is a present obligation as a result of a past event; if it is probable that an outflow of resources will occur; and a reliable estimate can be determined. [IAS 37.14].

Therefore, losses are recognised based on their actual incidence and any provisions that appear in the statement of financial position should reflect only the amounts expected to be paid in respect of those incidents that have occurred by the end of the reporting period.

In certain circumstances, a provision will often be needed not simply for known incidents, but also for those which insurance companies call IBNR – Incurred But Not Reported – representing an estimate of claims that have occurred at the end of the reporting period but which have not yet been notified to the reporting entity. We believe that it is appropriate that provision for such expected claims is made to the extent that such items can be measured reliably.

6.14 Obligations to make donations to non-profit organisations

When an entity promises to make donations to a non-profit organisation it can be difficult to determine whether a past obligating event exists that requires a provision to be recognised or whether it is appropriate instead to account for the gift as payments are made.

The following principles are relevant in determining when a promise to make a donation should be recognised as an obligation:

  • to the extent that there is an enforceable contract, the donor should recognise an expense and a liability upon entry into that contract;
  • where the agreement is not enforceable, the donor recognises an expense and a liability when a constructive obligation arises. The timing of recognition depends on whether the donation is conditional, whether it is probable that those conditions are substantially met and whether a past event has occurred; and
  • if the donor expects to receive benefits commensurate with the value of the donation, the arrangement should be treated as an exchange transaction. Such transactions are in some cases executory contracts and may also give rise to the recognition of an asset rather than an expense.

In cases where the ‘donation’ is made under an enforceable contract, a present obligation is created when the entity enters into that contract. When payment is required in cash, the signing of an enforceable contract gives rise to a financial liability, [IAS 32.11], which is measured initially at fair value. [IFRS 9.5.1.1].

Where there is no legal obligation to make the payments, a liability is recognised when a constructive obligation arises. It is a matter of judgement whether and when a constructive obligation exists. In many unenforceable contracts, a signed contract would not, in itself, be sufficient to create a constructive obligation. Hence, in the absence of other facts and circumstances that would create a constructive obligation, the donor would recognise the expenditure when the cash or other assets are transferred.

By contrast, an exchange transaction is a reciprocal transfer in which each party receives and sacrifices approximately equal value. Assets and liabilities are not recognised until each party performs their obligations under the arrangement.

Applying these principles to the options listed in Example 26.23 above:

  • In Option 1, the contract is unenforceable, there is no announcement or conditions preceding payment and there is no exchange of benefits. Accordingly, an expense would be recognised only when the entity transfers cash to the university.
  • For Option 2, it may be appropriate for the entity to conclude that the entity's announcement of the donation to be paid by instalments indicates that there is a constructive obligation because the entity has a created a valid expectation that it will make all of the payments promised. Alternatively, it could determine that once the first instalment is paid, the entity has created a valid expectation that it will make the remaining payments. This is a matter of judgement. In this case the entity would recognise an expense and a liability, measured at the net present value of the 5 instalments of €200,000, at the point when it is determined that a constructive obligation exists.
  • Option 3 involves an enforceable contract with no exchange of benefits. Therefore a liability and an expense is recognised on signing the enforceable contract, measured at the fair value of the 5 instalments of €200,000.
  • Under Option 4, the contract is unenforceable and the donation is subject to a condition. In these circumstances, whether there is a constructive obligation to make the donation is a matter of judgement. Management might conclude that no constructive obligation exists until it is probable that the condition is met (which might not be until the additional funds have been collected). Only then would a liability and expense be recognised, measured at the net present value of the €1m promised.
  • Option 5 involves an enforceable contract which may give rise to a liability when the contract is signed. However, there is an exchange of benefits relating to the research and development activities performed on behalf of the entity. Whether these benefits have a value of at least the present value of the 5 instalments of €200,000 is a matter of judgement. If it is determined that this is an exchange transaction that is not onerous, the entity could regard the signing of the contract as executory and could apply the criteria in IAS 38 to determine whether an asset or expense would be recognised for the related research and development costs as incurred (see Chapter 17 at 6.2).

Where the arrangement gives rise to an exchange transaction rather than a donation, the expenditure incurred by the donor is recorded in accordance with the relevant IFRS.

6.15 Settlement payments

A similar issue to that discussed at 6.14 above arises when an entity promises to make a settlement payment in cases where an entity believes that there is no present legal obligation. For example, an entity dismisses an employee for behaving in a manner which breaches their employment contract. The entity determines that it has no present legal obligation under the terms of the employment contract or employment law, but promises to make a settlement payment to the former employee in order to avoid future possible lawsuits and unfavourable publicity. It can be difficult to determine whether a past obligating event exists that requires a provision to be recognised before payment to the employee is made.

Where there is no legal obligation to make the payments, a liability is recognised when a constructive obligation arises. It is a matter of judgement whether and when a constructive obligation exists. A binding agreement to make a payment to the former employee could give rise to a legal obligation. In the absence of facts and circumstances that would create a constructive or legal obligation prior to settlement, the entity would recognise the settlement as an expense when the cash is transferred.

7 DISCLOSURE REQUIREMENTS

A significant distinction between the accounting treatment of provisions and other liabilities, such as trade payables and accruals, is the level of disclosure required.

7.1 Provisions

For each class of provision an entity should provide a reconciliation of the carrying amount of the provision at the beginning and end of the period showing:

  1. additional provisions made in the period, including increases to existing provisions;
  2. amounts used, i.e. incurred and charged against the provision, during the period;
  3. unused amounts reversed during the period; and
  4. the increase during the period in the discounted amount arising from the passage of time and the effect of any change in the discount rate.
  5. Comparative information is not required. [IAS 37.84].

It is not clear whether disclosure (d) allows a single amount to be provided for the sum of the unwinding of the discount and any change in the provision resulting from a reassessment of the discount rate to be used or it requires these amounts to be given separately. However, given our view (discussed at 4.3.6 above) that only the charge for unwinding of the discount should be classified as a finance cost, with any further charge or credit that arises if discount rates have changed being recorded in the same line item that was used to establish the provision, it would make sense to disclose these items separately. It is also interesting that there is no specific requirement in the standard to disclose the discount rate used, especially where the effect of using a different discount rate could be material, such as in the measurement of a decommissioning provision. However, entities should remember that IAS 1 requires disclosure of information about major sources of estimation uncertainty that have a significant risk of resulting in a material adjustment to the carrying amounts of assets and liabilities within the next financial year. [IAS 1.125].

One of the important disclosures which is reinforced here is the requirement to disclose the release of provisions found to be unnecessary. This disclosure, along with the requirement in the standard that provisions should be used only for the purpose for which the provision was originally recognised, [IAS 37.61], is designed to prevent entities from concealing expenditure by charging it against a provision that was set up for another purpose.

In addition, for each class of provision an entity should disclose the following:

  1. a brief description of the nature of the obligation and the expected timing of any resulting outflows of economic benefits;
  2. an indication of the uncertainties about the amount or timing of those outflows. Where necessary to provide adequate information, an entity should disclose the major assumptions made concerning future events, as addressed in paragraph 48 of the standard (discussed at 4.4 above). This refers to future developments in technology and legislation and is of particular relevance to environmental liabilities; and
  3. the amount of any expected reimbursement, stating the amount of any asset that has been recognised for that expected reimbursement. [IAS 37.85].

Section D of the implementation guidance to the standard provides examples of suitable disclosures in relation to warranties and decommissioning costs.

Most of the above disclosures are illustrated in the extract below, which includes the disclosure of provisions determined in accordance with IAS 37, contingent consideration provisions which would be determined in accordance with IFRS 3, and employee provisions (included within Other provisions) which would be determined in accordance with IAS 19.

The standard states that in determining which provisions may be aggregated to form a class, it is necessary to consider whether the nature of the items is sufficiently similar for a single statement about them to fulfil the requirements of (a) and (b) above. An example is given of warranties: it is suggested that, while it may be appropriate to treat warranties of different products as a single class of provision, it would not be appropriate to aggregate normal warranties with amounts that are subject to legal proceedings. [IAS 37.87]. For entities disclosing restructuring costs, this requirement could result in material components of the costs being disclosed separately. However, materiality will be an important consideration in judging how much analysis is required.

As indicated at 6.1.1 above, IAS 37 emphasises that when a restructuring meets the definition of a discontinued operation under IFRS 5, additional disclosures may be required under that standard (see Chapter 4 at 3). [IAS 37.9].

7.2 Contingent liabilities

Unless the possibility of any outflow in settlement is remote, IAS 37 requires the disclosure for each class of contingent liability at the end of the reporting period to include a brief description of the nature of the contingent liability, and where practicable:

  1. an estimate of its financial effect, measured in accordance with paragraphs 36‑52 of IAS 37 (discussed at 4 above);
  2. an indication of the uncertainties relating to the amount or timing of any outflow; and
  3. the possibility of any reimbursement. [IAS 37.86].

Where any of the information above is not disclosed because it is not practicable to do so, that fact should be stated. [IAS 37.91].

The guidance given in the standard on determining which provisions may be aggregated to form a class referred to at 7.1 above also applies to contingent liabilities.

A further point noted in the standard is that where a provision and a contingent liability arise from the same circumstances, an entity should ensure that the link between the provision and the contingent liability is clear. [IAS 37.88]. This situation may occur, for instance, when an entity stratifies a population of known and potential claimants between different classes of obligation, and accounts for each class separately. For example, an entity's actions may have resulted in environmental damage. The entity identifies the geographical area over which that damage is likely to have occurred and recognises a provision based on its ‘best estimate’ of value of claims it expects to be submitted from residents in that geographical area. In addition, there is a chance (albeit possible rather than probable) that the pollution is found to have had an effect beyond the geographical area established by the entity. As noted at 3.2.1 above, the latter, ‘possible but not probable’ obligation meets the definition of a contingent liability for which disclosure is required.

Another example of when a provision and a contingent liability may arise from the same circumstance would be where an entity is jointly and severally liable for an obligation. As noted at 4.7 above, in these circumstances the part of the obligation that is expected to be met by other parties is treated as a contingent liability.

It is not absolutely clear what is meant by ‘financial effect’ in (a) above. Is it the potential amount of the loss or is it the expected amount of the loss? The cross-reference to the measurement principles in paragraphs 36‑52 might imply the latter, but in any event, disclosure of the potential amount is likely to be relevant in explaining the uncertainties in (b) above.

7.3 Contingent assets

IAS 37 requires disclosure of contingent assets where an inflow of economic benefits is probable. The disclosures required are:

  1. a brief description of the nature of the contingent assets at the end of the reporting period; and
  2. where practicable, an estimate of their financial effect, measured using the principles set out for provisions in paragraphs 36‑52 of IAS 37. [IAS 37.89].

Where any of the information above is not disclosed because it is not practicable to do so, that fact should be stated. [IAS 37.91]. The standard goes on to emphasise that the disclosure must avoid giving misleading indications of the likelihood of income arising. [IAS 37.90].

One problem that arises with IAS 37 is that it requires the disclosure of an estimate of the potential financial effect for contingent assets to be measured in accordance with the measurement principles in the standard. Unfortunately, the measurement principles in the standard are all set out in terms of the settlement of obligations, and these principles cannot readily be applied to the measurement of contingent assets. Hence, judgement will have to be used as to how rigorously these principles should be applied.

7.4 Reduced disclosure when information is seriously prejudicial

IAS 37 contains an exemption from disclosure of information in the following circumstances. It says that, ‘in extremely rare cases, disclosure of some or all of the information required by [the disclosure requirements at 7.1 to 7.3 above] can be expected to prejudice seriously the position of the entity in a dispute with other parties on the subject matter of the provision, contingent liability or contingent asset’. [IAS 37.92].

In such circumstances, the information need not be disclosed. However, disclosure will still need to be made of the general nature of the dispute, together with the fact that, and the reason why, the required information has not been disclosed. [IAS 37.92].

The following example, from the implementation guidance to the Standard, provides an example of the disclosures required where some of the information required by the standard is not given because it is expected to prejudice seriously the position of the entity.

As it can be seen in the above example, an entity applying the ‘seriously prejudicial’ exemption is still required to describe the general nature of the dispute, resulting in a level of disclosure that many entities might find uncomfortable in the circumstances.

References

  1.   1 IASB Work Plan, June 2019.
  2.   2 IFRIC Update, July 2014, p.7.
  3.   3 IFRIC Update, September 2017.
  4.   4 IASB Agenda Paper 22 Provisions – Education Session – Scope of possible project to amend IAS 37, May 2019.
  5.   5 IASB Agenda Paper 22 Provisions - Education Session – Scope of possible project to amend IAS 37, May 2019.
  6.   6 FASB ASC Topic 450, Contingencies, para. 450‑20‑30‑1.
  7.   7 Discounting in Financial Reporting, ASB, April 1997.
  8.   8 Discounting in Financial Reporting, ASB, April 1997, para. 2.10.
  9.   9 IFRIC Update, March 2011, p.4.
  10. 10 IFRIC Update, January 2015.
  11. 11 IFRIC Staff Paper – Negative interest rates: implication for presentation in the statement of comprehensive income, January 2015, p.6.
  12. 12 Exposure Draft ED/2013/5: Regulatory Deferral Accounts, IASB, April 2013, para. BC15.
  13. 13 IASB Update, September 2012, December 2012.
  14. 14 IASB Meeting June 2019, Agenda paper 9A.
  15. 15 IASB work plan, June 2019.
  16. 16 IAS 19, Employee Benefits, Example illustrating paras. 159‑170.
  17. 17 Exposure Draft ED/2018/2 Onerous Contracts – Costs of Fulfilling a Contract.
  18. 18 IASB Update, May 2019.
  19. 19 IASB work plan, June 2019.
  20. 20 Exposure Draft ED/2018/2 Onerous Contracts – Costs of Fulfilling a Contract, BC15.
  21. 21 IASB work plan, June 2019.
  22. 22 IFRS 9 replaced IAS 39, effective for annual periods beginning on or after 1 January 2018. IFRS 9 applies to items that were previously within the scope of IAS 39.
  23. 23 IFRIC 3, Emission Rights, IASB, December 2004, para. 6.
  24. 24 IFRIC 3.5.
  25. 25 IFRIC 3.6.
  26. 26 IFRIC 3.7.
  27. 27 IFRIC 3.8.
  28. 28 IASB Update, June 2005, p.1.
  29. 29 IASB Update, June 2005, p.1.
  30. 30 IASB Update, May 2012, p.8.
  31. 31 IASB Update, January 2015, p.10.
  32. 32 IASB Work Plan 2017‑2021 Feedback Statement on the 2015 Agenda Consultation, November 2016.
  33. 33 Directive 2002/96/EC of the European Parliament and of the Council of 27 January 2003 on waste electrical and electronic equipment and Directive 2003/108/EC of the European Parliament and of the Council of 8 December 2003 amending Directive 2002/96/EC on waste electrical and electronic equipment.
  34. 34 IFRIC Update, March 2018.
  35. 35 IFRIC Update, May 2018.
..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset