Chapter 47

Worked Example 1

Bungalow

Keywords

AoA; AoN; Design and construction philosophy; EVA; Labour curve; Network programmes
The previous chapters described various methods and techniques developed to produce meaningful and practical network programmes. In this chapter, most of these techniques are combined in two fully worked examples. One is mainly of a civil engineering and building nature and the other is concerned with mechanical erection – both are practical and could be applied to real situations.
The first example covers the planning, man-hour control and cost control of a construction project of a bungalow. Before any planning work is started, it is advantageous to write down the salient parameters of the design and construction, or what is grandly called the ‘design and construction philosophy’. This ensures that everyone who participates in the project knows not only what has to be done, but why it is being done in a particular way. Indeed, if the design and construction philosophy is circulated before the programme, time- and cost-saving suggestions may well be volunteered by some recipients which, if acceptable, can be incorporated into the final plan.

Design and Construction Philosophy

1. The bungalow is constructed on strip footings.
2. External walls are in two skins of brick with a cavity. Internal partitions are in plasterboard on timber studding.
3. The floor is suspended on brick piers on an oversite concrete slab. Floorboards are T & G pine.
4. The roof is tiled on timber-trussed rafters with external gutters.
5. Internal finish is plaster on brick finished with emulsion paint.
6. Construction is by direct labour specially hired for the purpose. This includes specialist trades such as electrics and plumbing.
7. The work is financed by a bank loan, which is paid four-weekly on the basis of a regular site measure.
8. Labour is paid weekly. Suppliers and plant hires are paid 4 weeks after delivery. Materials and plant must be ordered 2 weeks before site requirement.
9. The average labour rate is £5 per hour or £250 per week for a 50-hour working week. This covers labourers and tradesmen.
10. The cross-section of the bungalow is shown in Fig. 47.1 and the sequence of activities is set out in Table 47.1, which shows the dependencies of each activity. All durations are in weeks. The network in Fig. 47.2 is in activity on arrow (AoA) format and the equivalent network in activity on node (AoN) format is shown in Fig. 47.3.
The activity letters refer to the activities shown on the cross-section diagram of Fig. 47.1, and on subsequent tables only these activity letters will be used. The total float column can, of course, only be completed when the network shown in Fig. 47.2 has been analysed (see Table 47.1).
Table 47.2 shows the complete analysis of the network including TLe (latest time end event), TEe (earliest time beginning event), total float and free float. It will be noted that none of the activities have free float. As mentioned in Chapter 21, free float is often confined to the dummy activities, which have been omitted from the table.
image
Figure 47.1 Bungalow (six rooms).

Table 47.1

Activity LetterActivity–DescriptionDuration (Weeks)DependencyTotal Float
AClear ground2Start0
BLay foundations3A0
CBuild dwarf walls2B0
DOversite concrete1B1
EFloor joists2C and D0
FMain walls5E0
GDoor and window frames3E2
HCeiling joists2F and G4
JRoof timbers6F and G0
KTiles2H and J1
LFloorboards3H and J0
MCeiling boards2K and L0
NSkirtings1K and L1
PGlazing2M and N0
QPlastering2P2
RElectrics3P1
SPlumbing and heating4P0
TPainting3Q, R and S0

image

0 = Critical.

To enable the resource loading bar chart in Fig. 47.4 to be drawn, it helps to prepare a table of resources for each activity (Table 47.3). The resources are divided into two categories:
1. Labourers
2. Tradesmen
This is because tradesmen are more likely to be in short supply and could affect the programme.
The total labour histogram can now be drawn, together with the total labour curve (Fig. 47.5). It will be seen that the histogram has been hatched to differentiate between labourers and tradesmen, and shows that the maximum demand for tradesmen is eight men in weeks 27 and 28. Unfortunately, it is possible to employ only six tradesmen due to possible site congestion. What is to be done?
The advantage of network analysis with its float calculation is now apparent. Examination of the network shows that in weeks 27 and 28 the following operations (or activities) have to be carried out:
Activity QPlastering3 men for 2 weeks
Activity RElectrics2 men for 3 weeks
Activity SPlumbing and heating3 men for 4 weeks
image
Figure 47.2 Network of bungalow (duration in weeks).
image
Figure 47.3 Network diagram of bungalow AoN format.
The first step is to check which activities have floats. Consulting Table 47.2 reveals that Q (plastering) has 2 weeks float and R (electrics) has 1 week float. By delaying Q (plastering) by 2 weeks and accelerating R (electrics) to be carried out in 2 weeks by 3 men per week, the maximum total in any week is reduced to 6. Alternatively, it may be possible to extend Q (plumbing) to 4 weeks using 2 men per week for the first 2 weeks and 1 man per week for the next 2 weeks. At the same time, R (electrics) can be extended by 1 week by employing 1 man per week for the first 2 weeks, and 2 men per week for the next 2 weeks. Again, the maximum total for weeks 27–31 is 6 tradesmen.
The new partial disposition of resources and revised histograms after the two alternative smoothing operations are shown in Figs 47.6 and 47.7. It will be noted that:
1. The overall programme duration has not been exceeded because the extra durations have been absorbed by the float.
2. The total number of man weeks of any trade has not changed, i.e., Q (plastering) still has 6 man weeks and R (electrics) still has 6 man weeks.
If it is not possible to obtain the necessary smoothing by utilizing and absorbing floats, the network logic may be amended, but this requires a careful reconsideration of the whole construction process.
The next operation is to use the EVA system to control the work on site. Multiplying for each activity, the number of weeks required to do the work by the number of men employed yields the number of man weeks. If this is multiplied by 50 (the average number of working hours in a week), the man-hours per activity can be obtained. A table can now be drawn up listing the activities, durations, number of men and budget hours (Table 47.4).

Table 47.2

abcdeFgh
Activity LetterNode No.DurationTLeTEeTEbd-f-c Total Floate-f-c Free Float
A1–2222000
B2–3355200
C3–5277500
D4–6176510
E5–7299700
F7–951414900
G8–1031412920
H11–12220161440
J13–14620201400
K14–15223222010
L14–16323232000
M16–17225252300
N16–18125242310
P19–20227272500
Q21–23231292720
R21–24331302710
S22–25431312700
T26–27334343100

image

image
Figure 47.4 Resource loaded bar chat.

Table 47.3

Labour resources per week.

Activity LetterResource A LabourersResource B TradesmenTotal
A66
B426
C246
D44
E22
F246
G22
H22
J22
K235
L22
M22
N22
P22
Q134
R22
S134
T44

image

image
Figure 47.5 Histogram and ‘S’ curve.
As the bank will advance the money to pay for the construction in four-weekly tranches, the measurement and control system will have to be set up to monitor the work every 4 weeks. The anticipated completion date is week 34, so that a measure in weeks 4, 8, 12, 16, 20, 24, 28, 32 and 36 will be required. By recording the actual hours worked each week and assessing the percentage complete for each activity each week the value hours for each activity can be quickly calculated. As described in Chapter 32, the overall percent complete, efficiency and predicted final hours can then be calculated. Table 47.5 shows a manual EVA analysis for four sample weeks (8, 16, 24 and 32).
In practice, this calculation will have to be carried out every week, either manually as shown or by computer using a simple spreadsheet. It must be remembered that only the activities actually worked on during the week in question have to be computed. The remaining activities are entered as shown in the previous week’s analysis.
image
Figure 47.6 Resource smoothing ‘A’.
image
Figure 47.7 Resource smoothing ‘B’.

Table 47.4

abcd
Activity LetterDuration (Weeks)No. of Menb × c × 50 Budget Hours
A26600
B36900
C26600
D14200
E22200
F561500
G32300
H22200
J62600
K25500
L32300
M22200
N12100
P22200
Q24400
R32300
S44800
T34600
Total8500

image

For purposes of progress payments, the value hours for every 4-week period must be multiplied by the average labour rate (£5 per hour) and when added to the material and plant costs, the total value for payment purposes is obtained. This is shown later in this chapter.
At this stage it is more important to control the job, and for this to be done effectively, a set of curves must be drawn on a time base to enable the various parameters to be compared. The relationship between the actual hours and value hours gives a measure of the efficiency of the work, while that between the value hours and planned hours gives a measure of progress. The actual and value hours are plotted straight from the EVA analysis, but the planned hours must be obtained from the labour expenditure curve (Fig. 47.5) and multiplying the labour value (in men) by 50 (the number of working hours per week). For example, in week 16, the total labour used to date is 94 man weeks, giving 94 × 50 = 4700 man-hours.
The complete set of curves (including the efficiency and percent complete curves) is shown in Fig. 47.8. In practice, it may be more convenient to draw the last two curves on a separate sheet, but provided the percentage scale is drawn on the opposite side to the man-hour scale; no confusion should arise. Again, a computer program can be written to plot these curves on a weekly basis as shown in Chapter 32.

Table 47.5

PeriodWeek 8Week 16Week 24Week 32
BudgetActual Cum.%VActual Cum.%VActual Cum.%VActual Cum.%V
A600600100600600100600600100600600100600
B900800100900800100900800100900800100900
C600550100600550100600550100600550100600
D20022090180240100200240100200240100200
E2001104080180100200180100200180100200
F150012008012001550100150015501001500
G300300100300300100300300100300
H20018060120240100200240100200
J60040050300750100600750100600
K500500100500550100500
L30025080240310100300
M20010060120180100200
N100504040110100100
P200220100200
Q400480100400
R30016060180
S80060080640
T6001001060
Total8500228027.823604450524420611070.66000792090.47680
Efficiency103999896
Estimated final hours8201855786548761

image

image
Figure 47.8 Control curves.
Once the control system has been set up, it is essential to draw up the cash flow curve to ascertain what additional funding arrangements are required over the life of the project. In most cases where project financing is required, the cash flow curve will give an indication of how much will have to be obtained from the finance house or bank and when. In the case of this example, where the construction is financed by bank advances related to site progress, it is still necessary to check that the payments will, in fact, cover the outgoings. It can be seen from the curve in Fig. 47.10 that virtually permanent overdraft arrangements will have to be made to enable the men and suppliers to be paid regularly.
When considering cash flow, it is useful to produce a table showing the relationship between the usage of a resource, the payment date and the receipt of cash from the bank to pay for it – even retrospectively. It can be seen in Table 47.6 that
1. Materials have to be ordered 4 weeks before use.
2. Materials have to be delivered 1 week before use.
3. Materials are paid for 4 weeks after delivery.
4. Labour is paid in the same week of use.
5. Measurements are made 3 weeks after use.
6. Payment is made 1 week after measurement.

Table 47.6

Week Intervals12345678
Order date
Material delivery
Labour use
Material use
Labour payments
Pay suppliers
X
X
X
X
O
MeasurementM
Receipt from bank
Every 4 weeks
Starting week no. 5
R
First week no.32112345

image

Table 47.7

ActivityNo. of WeeksLabour Cost per WeekMaterial and Plant per WeekMaterial Cost and Plant
A21500100200
B3150012003600
C215007001400
D11000800800
E25005001000
F5150014007000
G35006001800
H25006001200
J65006003600
K2130012002400
L35007002100
M2500300600
N1500200200
P2500400800
Q21000300600
R35006001800
S410009003600
T31000300900
Material total33,600

image

The next step is to tabulate the labour costs and material and plant costs on a weekly basis (Table 47.7). The last column in the table shows the total material and plant cost for every activity because all the materials and plant for an activity are being delivered 1 week before use and have to be paid for in one payment. For simplicity, no retentions are withheld (i.e., 100% payment is made to all suppliers when due).
image
Figure 47.9 Resource bar chart.
image
Figure 47.10 Cash flow curves.
A bar chart (Fig. 47.9) can now be produced, which is similar to that shown in Fig. 47.4. The main difference is that instead of drawing bars, the length of the activity is represented by the weekly resource. As there are two types of resources – men and materials and plant – each activity is represented by two lines. The top line represents the labour cost in £100 units and the lower line the material and plant cost in £100 units. When the chart is completed, the resources are added vertically for each week to give a weekly total of labour out (i.e., men being paid, line 1) and material and plant out (line 2). The total cash out and the cumulative outflow values can now be added in lines 3 and 4, respectively.
The chart also shows the measurements every 4 weeks, starting in week 4 (line 5), and the payments 1 week later. The cumulative total cash is shown in line 6. To enable the outflow of materials and plant to be shown separately on the graph in Fig. 47.10, it was necessary to enter the cumulative outflow for material and plant in row 7. This figure shows the cash flow curves (i.e., cash in and cash out). The need for a more-or-less permanent overdraft of approximately £10,000 is apparent.
..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset