Section R
Subcontracting

The whole difference between construction and creation is exactly this: that a thing constructed can only be loved after it is constructed; but a thing created is loved before it exists.

Gilbert Keith Chesterton, Preface to Dickens's Pickwick Papers

Reasons for subcontracting are as follows:

  • The specialist nature of the work
  • A weakness in one's own organization
  • In order to share or reduce risks
  • Productivity of the labour force
  • Competitive advantage.

Subcontracting (see Part III, Section C Issuing an Enquiry) will be the responsibility of either engineering for specialist design services or construction for site work. Both situations require the project manager's (and maybe the client's) approval, and the following questions should be addressed.

1 Questions to Ask Before Subcontracting

1.1

Are you certain that the proposed work is outside the resources of the company?

1.2

Could the company hire temporary resources to plug the deficiencies?

1.3

Are there a sufficient number of competent subcontractors capable of performing the proposed work?

1.4

Will the company have adequate experienced personnel, both technical and commercial, to supervise or manage the subcontracted work?

1.5

What additional work will the company have to perform in order to support the subcontractor?

1.6

Will the proposed construction methodology be acceptable to the subcontractor?

1.7

Can the subcontractor carry out the work in accordance with the project programme?

1.8

Will the use of a proposed subcontractor cause an industrial relations problem?

1.8.1

Will the subcontractor's management buy into your industrial relations policy?

1.9

Will the client want to get involved?

1.10

Will the client agree to the use of a proposed subcontractor, or will the client want their own choice to be used?

1.11

Is the proposed subcontract work within the budget? Can the project afford the extra costs involved in subcontracting?

1.12

The fundamental question(s) that must be answered is: what can the subcontractor do better than the company? Will the subcontractor be more effective and efficient than the company?

2 Contracting Checks

2.1

Key criteria in selecting subcontractors should be the application of innovative techniques and modularisation – not just the bottom‐line cost.

2.2

Make sure that the terms and conditions for subcontractors are prepared on the basis of the master project contract between the client and your company.

2.2.1

Insert a dispute clause that binds the subcontractor to the same dispute resolution process to which you are bound.

2.3

The subcontractors must be made aware, at the time that they are asked to tender, of any overriding labour agreements at the site, together with the facilities and common services to be provided.

2.4

Ensure that the subcontractor's management undertake safety inspection audits and that the contract and the safety plan responsibilities match up.

2.5

Get the subcontractor's input to the project schedule in order to get ‘buy in’ to meet the schedule.

2.6

Make sure that all matters have been finalised/released by the subcontractor before closing out with the client.

3 Management Issues

3.1

See paragraph 1.4 in Section Q.

3.2

Some companies use field engineers to manage subcontracts and some companies use quantity surveyors.

3.3

Make a register of authorized signatures and authority limits for subcontractor representatives.

4 List of Some Subcontracts

  1. a. Site survey
  2. b. Ground conditions survey
  3. c. Specialist ground treatment/piling
  4. d. Bore holes
  5. e. Construction of camp site
  6. f. Services for camp site
  7. g. Household and food supplies
  8. h. Security
  9. i. Transport/cars/minivans/busses
  10. j. Air freight
  11. k. Shipping
  12. l. Courier services
  13. m. Supply and maintenance of site office equipment
  14. n. Rubbish removal
  15. o. Medical services
  16. p. Emergency evacuation
  17. q. Laboratory testing for materials/water quality
  18. r. Site clearance
  19. s. Temporary facilities
  20. t. Construction equipment/supply of tools
  21. u. Scaffolding
  22. v. Heavy lift equipment
  23. w. Civil work
  24. x. Specialist civil work/cooling towers/chimneys
  25. y. Special foundations
  26. z. Concrete reinforcing bar
  27. aa. Rail sidings
  28. bb. Storage tanks
  29. cc. Pipework fabrication and installation
  30. dd. Radiography/welder testing
  31. ee. Equipment installation
  32. ff. Structural steel supply and erection
  33. gg. Electrical and instrumentation
  34. hh. Permanent buildings
  35. ii. Heating, Ventilating, and Air Conditioning – Refrigeration
  36. jj. Connections to public services
  37. kk. Cathodic protection
  38. ll. Insulation
  39. mm. Painting
  40. nn. Landscaping and Fencing.
..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset