8.4. Recycling Technologies and Processes: Case Study

8.4.1. Recycling Project of C&D Waste in Shangrao City

Recycling project of the C&D waste in Shangrao city is a comprehensive project started in 2014. The annual treatment planning in the first stage is 300,000 t of C&D waste and 50,000, 80,000, 120,000, and 60,000 t of recycled aggregate, renewable powder, recycled fine sand, and recycled construction materials, respectively. The whole process is able to reduce the spread of dust, while also using source separation process which aimed at separating solids and reusing for the production of raw materials. The waste water being removed of solid substances after precipitation is reused as wash water. Meanwhile, the heavy metal–contaminated construction waste is sorted, separated, and eluted of harmful substances in the relevant sections, to achieve zero emissions in the whole process, as demonstrated in Fig. 8.29. The process is divided into six sections: pretreatment and stacking section, clean waste crushing and sorting section, heavy metal pollution control section, classified storage section, deep processing combined with grinding section, and manufacturing section of products.

8.4.1.1. Pretreatment and Stacking Section

Primary crushing, manual sorting, and stacking of raw material are performed in this section.
After being transported from off-site to the disposal site into the working area, the C&D waste is sent into the jaw crusher. In this period, large blocks of waste are primarily crushed to facilitate the crushing and separation of reinforced concrete blocks in subsequent sections. The approaching working area is to provide space for the transport of vehicles, also being capable of storing a small amount of waste.
The crushed waste is then sent to the manual sorting platform for the separation of larger iron blocks, cloth, plastic, fabric, etc. Due to the complex components of C&D waste, manual sorting is able to ensure the successful separation of large blocks while making the subsequent process more efficient.
image
Figure 8.29 Process of construction and demolition waste recycling project of Shangrao City.
The materials are transported into automatic enclosed stacking system through a manual sorting platform. The stacker is able to store 18,000 m3 waste, which could meet the demand for the storage amount of a week, and is a transition and buffer between the storage and disposal of C&D waste. This section is necessary due to the discontinuous collection of C&D waste.

8.4.1.2. Crushing and Sorting Section of C&D Waste

This section is the major process in which C&D waste is produced into aggregates, and is aimed at finely crushing and separating the impurities. This section is equipped with impact crusher, powerful iron drawer, mud remover, wind-conveyor sorting machines, and circular sieve.
The materials are first transported into the impact crusher, of which the outlet particle size is less than 40 mm. Then they are sent to the three-layer mud sieve by belt conveyor. The slim reinforced bars, steel nails, and other metals (not including heavy metal pollutants) are also removed in this section.
The linear mud sieve is aimed at removing the materials of particle size less than 1 mm. Most of these wastes contain mud, which is hard to be recycled. The materials above the sieve are sent back to the crusher, whereas those in the middle are transported to the next sorter.
Wind-conveyor sorting machines are used to sort the light waste like wood. Then they are screened in the circular sieve and are classified into four different classes based on the particle size. Dust removers are also equipped in this section.

8.4.1.3. Treatment Section of Heavy Metal–Contaminated C&D Waste

Surface Stripping
About 3–6 mm of the surface of C&D waste contaminated by high concentrations of heavy metals is stripped off and immersed in commercial caustic soda solution of industrial 2–8 M grade. Electrolysis treatment is performed upon the leaching solution to recycle the heavy metals.
Crushing
The C&D waste obtained in procedure a is crushed to particles of size less than 4–5 mm.
Washing and Solid–liquid Separation
The crushed C&D waste is washed with water (liquid:solid = 5:1) and is solid–liquid separated. The wash water is treated by adding nano-iron powder (20 nm). The washed C&D waste is eluted with glyphosate according to procedure d.
Eluting With Glyphosate and Solid–liquid Separation
Glyphosate is added into the washed C&D waste (liquid:solid = 2:1) and eluted one to three times. Most heavy metal ions would be combined with glyphosate and transformed into the nonleachable and stable phase. Solid–liquid separation is performed after the pH has been adjusted to neutral. The waste water is treated while the eluted C&D waste is sent for further washing.
Eluted C&D Waste
Eluted C&D waste is washed with water (liquid:solid = 5:1) before solid–liquid separation is performed. C&D waste is dried and sent for heavy metals detection.
image
Figure 8.30 Process of deep processing and combined grinding section.

8.4.1.4. Classified Storage Section

The materials in this section are semifinished products, which are divided into four classes: 0–5, 5–15, 15–22, and 22–31.5 mm. The storage capacity of each room of the warehouse is 350 m3, the functions of which are continuous feeding for the combined grinding and loading for sale of semifinished products.

8.4.1.5. Deep Processing and Combined Grinding Section

A detailed process of this section is demonstrated in Fig. 8.30. The materials has already been sorted and removed of mud, impurities, and iron and are high in quality and the mud content is less than 1% before being set into the combined grinding system. They are first transported into the roll press and grinded to particles less than 5 mm. These small particles are then sent to thermal whirlcone conical grinder with dryers. The high-speed rotating grinding parts are able to crush by stirring, rolling, and vibrating. The front of this grinder is crushed by mainly hitting and the back by mainly squeezing. The low-intensity waste like sintered bricks and cement stones are ground to powder, which are high-activity metakaolin, whereas the high-intensity waste like natural rocks or river sand are ground to fine sand.
The ground materials are classified into three classes: 0–0.08, 0.08–0.16, and 0.16–2.36 mm and are collected in the tanks, respectively.

8.4.1.6. Manufacturing Section of Products

Detailed process of manufacturing section of products is demonstrated in Fig. 8.31. Recycled aggregates in the crushing and sorting section are used as raw materials, those of 0–5 and 5–15 mm are generally selected. Main products include recycled blocks, recycled bricks, road bricks, permeable bricks, and wall materials.
The overall layout distribution and the land coverage of each section are listed in Table 8.23.
The main pollutants in the manufacturing process are the inorganic mineral dust generated in the transportation of materials. In this project, sealed storage warehouse is adopted while dust caps are equipped on the belt conveyors. The inlet and outlet sections of materials are equipped with steel covers along with bag filters for dust catching. All crushing facilities are equipped with fully enclosed soundproofed rooms in which negative pressure is generated. Meanwhile, the rotation speed and gap between transfer stations are minimized to strengthen the airtight thus controlling the spread of dust.
image
Figure 8.31 Process of manufacturing section of products derived from construction and demolition waste.

Table 8.23

General Layout and Land Coverage of This Project for Annual Treatment Scale of 300,000 t of Construction and Demolition Waste

No.ItemLand Coverage (m2)Building Construction Area (m2)Structure Construction Area (m2)
1Stack area of demolition waste403403
2Pretreatment stack area49439886
3Crushing, sorting, and classified storage workshop28895778
4Deep processing workshop10992198
5Metal pollutants disposing workshop5501100
6Storage warehouse of recycled micropowder320900
7Repair shop, warehouse763763
8Controlling center479479
9Test building10083024
10Multifunctional building10083024
11Product storage yard5000
12Guard room4046

image

Sand and gravel separation facilities are adopted in the wastewater treatment system. The solid materials separated from this section can be used as producing raw materials while the wastewater deprived of solid substances is also reused.
Main facilities and their parameters for the production of recycled products using C&D waste are listed in Tables 8.248.27.

8.4.1.7. Labor Organization

Labor organization information of this project is introduced below.
Annual working days: 252–300 days;
Main manufacturing posts: two shifts;
Auxiliary manufacturing posts: one shift;
Working time per shift: 8 h.
Information of labor force involved is listed in Table 8.28.

8.4.2. Centralized Disposal and Recycling Project of C&D Waste in Nantong City

8.4.2.1. General Introduction of This Project and Its Processes

The annual treatment planning in the first stage is 1,000,000 t of C&D waste and 100,000 m3 of recycled concrete aggregate, 200,000 t of premixed mortar, 200,000 t of cementing materials, and 400,000 t of recycled aggregate (sand, gravel). A comparison of the disposal process and recycled products is listed in Table 8.29.

Table 8.24

Facilities in Pretreatment Section for Annual Treatment Scale of 300,000 t of Construction and Demolition Waste

FacilityStyleParameterPowerQTYFunction
Vibrating feederZSW600 × 130

1. Size: 3800 × 960 mm

2. Max feed size: 500 mm

3. Rotation speed of eccentric shaft: 500–710 r/min

4. Feeding capacity: 96–160 t/h

15 kW1Jaw crushing, feeding
Jaw crusherPESS5010-220220 kW1Coarse crushing
Electromagnetic iron separatorRCDD-8

1. Rated lifting height: 300 mm

2. Material thickness: ≤250 mm

3. Magnetic intensity: ≥70 mT

3.0 kW2Removal of the residual steel
Mechanical iron removal platformL2m1Iron removal work
Manual sorting platformL5m1Manual sorting work
Straight vibrating sieve for C&D wasteBST183615 kW1
Plate chain bucket elevatorNE150

1. Max size: 80 mm

2. Material lifting speed: 0.5 m/s

3. Unit weight: 0.6–1.8 t/h3

4. Production capacity: 150–180 m3/h

15 kW1Lifting of materials to windrow after manual sorting to save land
Belt stockerDBJD5001Stack volume: 14,000 m337 kW + 5.5kW + 2.2 kW × 21Stacking of the material after coarse crushing
Pneumatic unloading valveDriven by cylinder and controlled by solenoid valve9Unloading
Air pumpPiston5.5 kW1Supply of air for pneumatic valve
Ridge conveyor beltB800L100m37 kW1Feeding of materials into the crushing and sorting section

image

QTY, quantity.

Table 8.25

Facilities in Crushing and Sorting Section for Annual Treatment Scale of 300,000 t of Construction and Demolition Waste

FacilityStyleParameterPowerQTYFunction
Electromagnetic iron removerRCDD-8

1. Rated lifting height: 250 mm

2. Material thickness: ≤200 mm

3. Magnetic intensity: ≥70 mT

2.2 kW2Iron removal
Impact crusherPFY1214

1. Inlet size: 1430 × 400 mm

2. Max feed size: 350 mm

3. Discharging size: 20–60 mm

4. Production capacity: 90–145 t/h

132 kW1Fine crushing
Straight vibrating screen3ZK1860

1. Screen size: 6000 × 1800 mm

2. Max feed size: 400 mm

3. Layers: three

22 kW4Mud removal, classification
Air duct tape sorterDBF-80Size: 5550 × 2660 × 4290 mm15 kW2Removal of light materials
Dust catcher for solid wasteKZHS96-7

1. Air volume: 65,200–87,000 m3/h

2. Filtration velocity: 1.2–1.7 m/min

3. Number of filter bags: 96 × 7

4. Allowable inlet dust concentration: ≤200 g/Nm3

5. Outlet dust concentration: ≤50 mg/Nm3

45 kW1Dust removal for straight screen, circular screen and air duct tape sorter
Plate chain bucket elevatorNE150

1. Max size: 60 mm

2. Material lifting speed: 0.5 m/s

3. Unit weight: 0.6–1.8 t/h3

4. Production capacity: 50–60 m3/h

11 kW4Lifting of materials to conveyor belt after circular screening
Belt conveyorB650L30m11 kW1Transfer of materials to classified storage section
Belt conveyorB650L25m11 kW1
Pneumatic unloading valve4Unloading in storage house
Air pumpPiston4 kW1Supply of air for pneumatic valve
Storage house for semiproductSteel structure4Storage of semiproducts

image

QTY, quantity.

Table 8.26

Facilities in Deep Processing Section for Annual Treatment Scale of 300,000 t of Construction and Demolition Waste

FacilityStyleParameterPowerQTYFunction
Coal gas producer1Drying
High-pressure rolling machineG1260

1. Max inlet size: <30 mm

2. Outlet size: <5 mm

3. Production capacity: 100–120 t/h

2 × 90 kW1Pregrinding
Bucket elevatorNE10015 kW1Lifting of materials from roller to grinder
Thermal whirl conical grinder with dryersDBJM5001

1. Max feed size: ≤50 mm

2. Max feed water content: <20%

3. Outlet water content: <1–2%

4. Production capacity: 100 t/h

132 kW1Grinding
Heat-resistant air locking unloaderYJD-AE1From the elevator to dryer
Multipowder concentratorJND-V

1. Disposal capacity: 100–130 t/h

2. Disposal airflow: 50,000 m3/h

3. Rotation speed of rotor: 180–260 r/min

45 kW1Classification
Dust catcher for solid wasteKZHS96

1. Air volume: 5200–7000 m3/h

2. Filtration velocity: 1.2–1.7 m/min

3. Number of filter bags: 96

4. Allowable inlet dust concentration: ≤200 g/Nm3

5. Outlet dust concentration: ≤50 mg/Nm3

45 kW1Dust removal for grinding in deep processing section
Storage tank1000TStorage capacity: 1000 t3Storage of recycled powder and sand

image

QTY, quantity.

Table 8.27

Facilities in Product Manufacturing Section for Annual Treatment Scale of 300,000 t of Construction and Demolition Waste

No.ItemModel & SpecificationQTY
1Ingredient storage bin 3 × 4 m3 (body fabric)Aggregate storage bin4 m33
Measuring bin1200 kg ± 2%1
SensorCST-20004
CylinderSC80 × 300-S-CB-Y3
VibratorB-0.53
Motor7.5 kW1
BeltB500 × 17.1 m1
FrameSteel structure1
2Blender (body fabric)Blending barrelJS7501
Motor reducer30 kW1
Lifting motor7.5 kW1
Lubrication system1
CylinderSC160 × 300-S-TC-M-Y1
3Cement measuring system (body fabric)Cement weighing hopper350 kg ± 1%1
SensorCSB-2503
Butterfly valveDN2501
VibratorB-0.251
4Water measuring system (body fabric)Water measuring cylinder200 kg ± 1%1
Transmission pump2.2 kW1
Pipeline2″1
SensorCST-5001
Butterfly valveDN801
Filling valveDN251
5Belt conveyor (body fabric)Flat beltB600 × 8 m (center distance)1
Planet-cycloid retarder4 kW1
Table Continued

image

No.ItemModel & SpecificationQTY
FrameSteel structure1
Tightener1
Receiving hopper1
6Grading station 1 × 4 m3 (plus material)Aggregate storage bin4 m31
Measuring bin800 kg ± 2%1
SensorCST-10004
CylinderSC80 × 300-S-CB-Y1
VibratorB-0.51
Motor2.2 kW1
BeltB500 × 5 m1
FrameSteel structure1
7Vertical blender (plus material)Blending barrelJN3501
Motor reducer7.5 kW1
Lifting motor4 kW1
CylinderSC80 × 250-S-TC-Y1
8Cement measuring system (plus material)Cement weighing hopper150 kg ± 1%1
SensorCSB-2503
Butterfly valveDN2501
VibratorB-0.251
9Water measuring system (plus material)Water measuring cylinder80 kg ± 1%1
Transmission pump1.1 kW1
Pipeline1 1/4″1
SensorCST-2501
Butterfly valveDN801
Filling valveDN251
Table Continued

image

No.ItemModel & SpecificationQTY
10Belt conveyor (plus material)Flat beltB500 × 7 m (center distance)1
Planet-cycloid retarder2.2 kW1
FrameSteel structure1
Tightener1
Receiving hopper1
11Block molderHost machineQT10-151
Vibrating motor (with frequency conversion, without independent fans)11 kW2
Distributing motor4 kW1
Pallet conveyor1
Hydraulic system22 kW1
Random mold1
12Plus material device1
13Heat insulating board conveying device1
14Wet product conveyor lineSweeping motor0.18 kW1
Frame1
Spacing device1
15Elevator 10FFrameSBJ101
Motor power7.5 kW1
Lifting device1
Table Continued

image

No.ItemModel & SpecificationQTY
16Lowerator 10FFrameSBJ101
Motor power7.5 kW1
Lifting device1
17Composite vehicleConveyor (carrier)1
Actuating device for conveyor3 kW1
Subequipped vehicle (10 floor)1
Actuating device for subequipped vehicle3 kW1
Speed control device1
Positioning device1.5 kW1
18Dry product conveyor lineFrame1
Sweeping machine0.18 kW1
Spacing device1
19Plate recycling linePlate turnover machineSF101
Gear motor0.75 kW1
Overpass1
20Stacking machineWalking device1.1 kW1
Clamp device1
Lifting device1
Rotation device0.55 kW1
Prestack device1
Hydraulic system15 kW1
21Pitch conveyorTank chain7.5 kW1
22Wood tray separatorWood tray2.2 kW1
Table Continued

image

No.ItemModel & SpecificationQTY
23Processing line hydraulic systemTriphase asynchronism motorY180L-4 22 kW1
24Electronic controlling systemElectric cabinet3
Control console4
Industrial computer19″ LED display2
PLC4
Touch screenTP-177A (Siemens)3
Transmission instrumentGM8802F6
Connecting cable1
25Control room6000 × 2250 × 25001
26Packaging systemHorizontal packing machine1
Packaging machine1
Winding machine1
Transporting line2.5 m4
Packaging control console1
27Pneumatic systemAir compressor5.5 kW1
Pipe1
FR, FRL1
28Spiral conveyorXL219φ219 × 6 m1
XL165φ165 × 5.5 m1

image

FR, filter + regulator; FRL, filter + regulator + lubricator; QTY, Quantity.

Table 8.28

Number of Labor Force

DepartmentNumber of Staff
Day ShiftMorning ShiftSwing ShiftNight ShiftNon ShiftTotal
Construction & demolition waste pretreatment3317
Crushing and sorting4419
Deep grinding process3317
Storage and loading22
Product manufacturing55111
Mechanical maintenance22
Technical production (experiment)2114
Guard1113
Logistics, administration314
Financing33
Management55
Total2311171557

image

Table 8.29

Comparison of Handling Process and Recycled Products in Nantong City Project

No.ItemPlan 1Plan 2Plan 3
1Resource productsConcrete products, mortar, concrete aggregate and cementing materialsConcrete products, mortarRoad material (cushion)
2PretreatmentMultistage crushing, screeningMultistage crushing, screeningSingle-stage crushing
3Separation of bricks, gravel, concreteRelatively completeRelatively completeMixed
4Usage of recycled aggregate
4.1StoneVarious classes (5–25 mm), able to be produced into concrete products and aggregateVarious classes (5–25 mm), able to produce into concrete products and aggregateThose particle size larger than 25 mm account for more than 60%, can only be produced into road construction materials
4.2Grit0–5 mm, able to be produced into concrete products and premixed mortar0–5 mm, able to be produced into concrete products and premixed mortar
4.3Powder≤0.16 mm, specific surface area of about 3000 cm2/g, can be used as cementing (blending) material
5Variety of recycled productsDiversifiedSmallSingle (very small)
6Sales of recycled products
Table Continued

image

No.ItemPlan 1Plan 2Plan 3
6.1Annual treatment capacity of 300,000 tSmooth, low market shareRisk existing, large amount which will hit the marketRisk existing
6.2Annual treatment capacity of 500,000 tSmooth, low market shareLarge risk, cannot be accommodated in marketLarge risk
6.3Annual treatment capacity of 800,000–1,000,000 tSmall risk, diversified marketHuge riskHuge risk
7Environmental pollutionLittleLittleMuch
8Installed capacityVery largeLargeSmall
9Land occupationLargeLargeSmall
10InvestmentVery largeLargeSmall
11Technical sophisticationVery highHighLow
12ReliabilityHighHighHigh
13Value of recycled productsVery highHighLow
14SustainabilityGoodNormalBad

image

Table 8.30

Components of Projects and Their Functions and Construction Area for Annual Treatment Scale of 1,000,000 t of Construction and Demolition Waste in Nantong City Project

No.SectionFunctionConstruction Area (m2)
1No. 1 combined workshopProduction of recycled powder and sand12,606
2Product manufacturing and steam curing workshopProducts manufacturing1730
3Comprehensive buildingOffice work2700
4Technical centerResearch work2700
5OfficeDork business228
6Maintenance workshopMaintenance of facilities48
7EntranceInspection48
8CanteenDinner1238
9No. 2 combined workshopManufacturing of recycled aggregates3230
Total24,528

image

Table 8.31

Material Balance of Annual Production of 100,000 m3 Recycled Concrete Products in Nantong City Project

MaterialUnit Consumption, t/m3Hourly Consumption, tDaily Consumption, tAnnual Consumption, t
Cement0.306.6710030,000
Sand0.153.335015,000
Recycled fine aggregate0.8518.9283.385,000
Recycled coarse aggregate0.451015045,000
Additive0.0030.0671300
Water0.1846018,000

image

The general construction area of each section is listed in Table 8.30.

8.4.2.2. Material Balance

The material balance of the annual production of 100,000 m3 recycled concrete products is listed in Table 8.31.
The material balance of the annual production of 100,000 m3 recycled concrete is listed in Table 8.32.

Table 8.32

Material Balance of Annual Production of 100,000 m3 Recycled Concrete in Nantong City Project

MaterialUnit Consumption, t/m3Hourly Consumption, tDaily Consumption, tAnnual Consumption, t
Cement0.2811.211228,000
Stone0.6252525062,500
Sand0.357.78116.735,000
Recycled fine aggregate0.357.78116.735,000
Recycled coarse aggregate1.252525062,500
Fly ash0.0652.6266500
Mineral powder0.0843.3633.68400
Additive0.00590.2352.36590
Water0.228.88822,000

image

Table 8.33

Material Balance of Annual Production of 200,000 t of Premixed Mortar in Nantong City Project

MaterialProportion, %Hourly, t/hDaily, t/dayAnnual, t/year
Cement207.56113.340,000
Recycled fine aggregate5624.8373.3112,000
Sand146.2293.328,000
Fly ash104.4466.720,000
Additive0.30.1332600

image

The material balance of the annual production of 200,000 t of premixed mortar is listed in Table 8.33.

8.4.2.3. Main Facilities

Main facilities involved in this project are listed in Table 8.34. The facilities are classified into six groups according to the different producing sections.

8.4.2.4. Layout and Structures

Engineering Project
The engineering design elevation is ±0.000, the interior height difference of manufacturing workshop is 150 mm, and the interior height difference of nonmanufacturing workshop is 450 mm.

Table 8.34

Main Facilities Involved in This Project for Annual Treatment Scale of 1,000,000 t of Construction and Demolition (C&D) Waste in Nantong City Project

No.FacilityStyle & SpecificationDisposing (Producing) CapacityQuantityNote
1C&D waste pretreatment section
1)FeederSEFTG-490140 t/h2
2)Primary crusherSEFPE-750100–150 t/h2
3)Secondary crusherSEFPF-1315100–150 t/h2
4)Tertiary crusherSEFPY-1300100 t/h2
5)Metal separatorSEFF10006
6)Screening deviceSEF3YK2460200 t/h6
7)Fine material grading deviceSEFYK185416 t/h2
8)Plenum pulse dust collectorXLPM6A12,000 m3/h6
9)Plenum pulse dust collectorXLPM2A3000 m3/h6
10)Belt conveyorB650-100050–60 t/h26
11)LoaderZL503
2Storage and transportation section for recycled aggregate
1)Belt conveyorB650-100050–00 t/h10
2)Batching system6
3)Plenum pulse dust collectorXLPM2A3000 m3/h8
3Recycled products manufacturing section
1)Measuring and batching system2
2)Blender2 m330 m3/h2
3)Fabric material blender350 L2
4)Blender0.5 m31
Table Continued

image

No.FacilityStyle & SpecificationDisposing (Producing) CapacityQuantityNote
5)Plenum pulse dust collectorXLPM2A3000 m3/h2
6)Building block molderQT10-152
7)Elevator2
8)Lowerator1
9)Palletizer1
10)Multifunctional large extruding machineSEF90-120 × 120040,000 m3/a2
11)Curing device1
12)Packaging machineJHDKB1
13)Forklift2 t3
4Concrete production section
1)Blender2 m3120 m3/h1Theoretical capacity
2)Sand separating and recycling system1
5Premixed mortar
1)Sand drying machineΦ2.5 × 5.4 m35 t/h15% water
2)Vibrating screen1
3)Blender6 m330 t/h2
4)Packaging machine2
5)Bag filter6000 m3/h1
6Cementing material production section
1)Rolling machineGM800Throughput: 48 t/h1
2)Powder concentratorO-X50020–40 t/h1
3)Bag filter36,000 m3/h1
4)Bag filter4500 m3/h1

image

General Layout
1. General layout should possibly take advantage of terrain conditions and surrounding facilities, and should have a clear functional partition. The material storage area, production areas, and administrative welfare facilities must be separated, whereas the latter should be located at the upwind of the prevailing wind direction.
2. Make full use of terrain elevation, the direction of terrain height variation should be correlative to the process flow of the project to avoid useless work and to shorten the transportation distance, thus making the process more compactly and reasonably arranged.
3. Layout of the process should comply with the arrangement order from raw materials to finished products. The location of storage house of materials should be close to the users to shorten the transportation distance.
4. The arrangement of buildings and structures should be in line with the fire prevention interval and meet the fire requirements.
5. The site elevation and road elevation should be conducive to the discharging of rainwater and sewage. In the premise of meeting the requirements regulated in relative standards, integrated arrangement of each facility should be performed on basis of the whole process, fire, health, wind direction, transportation, and maintenance requirements.
6. The amount of site leveling work should be possibly minimized, balanced earthworks should be achieved.
Construction Materials and Structures
1. Construction for productive purposes
    Wall: Reinforced concrete (or masonry brick, block) is used in the materials of the structures between fundamentals to the window, whereas those above the window are constructed by profiled steel sheets.
    Door and window: PVC steel doors and windows and normal light steel doors are applied except those in substations or with dust and sound prevention.
    Floor: Various floors are designed based on load of different floor like storage, workshop, yard, and other ground.
    Roof: Unorganized free drainage and increased roof slope is applied to facilitate and promote drainage.
2. Construction for nonproductive purposes
    Wall: Solid blocks are used in walls below ±0.000, whereas hollow block infilled walls are used in those above ±0.000.
Door and window: PVC steel doors and windows.
Floor: Fine concrete aggregate surface is generally applied, whereas special floors such as those in laboratories or toilets are made of antislip tile surface.
Roof: Organized drainage with UPVC pipes.
Features of Main Construction Buildings
1. C&D waste pretreatment workshop
    The C&D waste pretreatment workshop is built on the basis of the initial height difference on the site and is constructed using fully enclosed structure. Crushing and grading of C&D waste are performed in this workshop.
2. Storage of recycled fine aggregate
    Enclosed circular structure is applied in storage house of recycled fine aggregate. The upper part is composed of six steel plates of diameter 10 m, whereas the lower part are two layers of reinforced concrete frame structure. The first layer is used as power distribution room and the other is used as batching room.
3. Recycled aggregate storage house
    Reinforced concrete retaining walls are applied around and below the house while light steel structure is used on the upper portion of the house.
4. Recycled aggregate processing workshop
    Product processing and curing sections are the two main processes in this workshop, which are of concrete frame structure. Concrete roof with solar panel and hot water supply system is applied in product processing section while several curing rooms are separated in the curing section.
5. Laboratory
    The laboratory, which is also the technical and production scheduling control center in this project, is constructed by two layers of reinforced concrete and infilled walls. The first floor is the detection station for raw materials and product quality with different manufacturing, curing, and detecting equipment, and the second floor is product researching laboratory.
6. Production control center
    Production control center is constructed by two layers of reinforced concrete and infilled walls. The first floor is used as canteen and bath room and the second floor is for production scheduling and office.
7. The buildings of production control center and laboratory are of energy conservation design.
Structure
1. Seismic fortification
    The seismic fortification intensity is set as 6 degree for the region, and the basic earthquake acceleration value designed is 0.05 g.
2. Design load adopted
    Basic wind pressure: 0.45 kN/m2.
    Load of productive structures is provided by the engineering process.
    Load of nonproduction workshops are adopted according to Load code for the design of building structures (GB 50009-2012).
3. Structure selection and application
a. The C&D waste pretreatment workshop is applied with the reinforced concrete column frame-bent structure with light steel roofs.
b. The recycled aggregate storage house is applied with the reinforced concrete column frame-bent structure with light steel roofs and retaining wall around it.
c. The storage house of recycled fine aggregate is applied with steel plate silo structure, which is sustained by two layers of cast-in-site reinforced concrete framework.
d. The mortar and concrete workshop is applied with the reinforced concrete column frame-bent structure with light steel roofs.
e. The recycled aggregate production workshop is applied with the reinforced concrete column frame-bent structure with light steel roofs.
f. The cementing material production workshop is applied with the reinforced concrete column frame-bent structure with light steel roofs.
g. The control center is applied with three layers of cast-in-site reinforced concrete framework.
h. The laboratory is applied with two layers of cast-in-site reinforced concrete framework.
i. The mechanic maintenance workshop, warehouse, substation, and guard are applied with one layer of cast-in-site reinforced concrete framework.
j. The car washing and water treatment buildings are applied with cast-in-site reinforced concrete framework structure.
k. The C&D waste storage yard is applied with the reinforced concrete column frame-bent structure with light steel roofs.
There are two entrances (primary and secondary entrance) in the project to shunt the traffic flow and people. The main entrance is located in the southwest of the plant, the width of entrance is not less than 14 m and is connected with the planned roads. The road in the plant is the circular road around the main producing workshop. The main roads are 14–10 m wide and the turning radius is not less than 9 m. The other roads are 7–4 m wide and the turning radius is not less than 6 m. The roads are all city roads with road traffic stones and gullies for drainage. The cross slope of the road is 1% and the longitudinal slope is not less than 0.3%.

Table 8.35

Main Index of General Layout of This Project for Annual Treatment Scale of 1,000,000 t of Construction and Demolition Waste in Nantong City Project

No.ItemUnitQuantityNote
1Land occupation of this projectm2107,060
2Land occupation of buildings and structuresm234,653Not including the area of storage yards
3Construction area of buildings and structuresm241,790Not including the area of storage yards
1)Administrative auxiliary facilitiesm23,069
2)Industrial buildingsm238,721
4Area of storage yardsm215,826
5Building density%32
6Floor area ratio0.39
7Building coverage%47Including the area of storage yards
8Road aream220,880
9Landscaping aream221,410
10Landscaping ratio%20
11Parking space12Small
12Length of bounding wallsm1,250
13Earthwork volumem3
1)Amount of excavationm3
2)Amount of fillingm343,000

image

Cement concrete is the main material of the roads. The structure is 22 cm of C30 concrete layer, 30 cm of gravel fundamental layer, and 5 cm of sand-gravel cushion.
The main index of general layout of this project is listed in Table 8.35.
Main Buildings and Construction Structure in Nantong City Project
Main buildings and construction structure in this project for annual treatment scale of 1,000,000 t of C&D waste are listed in detail in Tables 8.368.38.

Table 8.36

Main Buildings and Construction Structure in Nantong City Project (1–5)

ItemC&D Waste Storage YardC&D Waste Pretreatment WorkshopRecycled Aggregate Storage HouseRecycled Fine Aggregate Storage HouseConcrete Workshop
No.12345
aConstruction gradeVVVVV
aFireproof endurance ratingIIIIIIIIII
bSeismic precautionary intensity6 degree6 degree6 degree6 degree6 degree
Main structureReinforced concrete column frame-bent structureReinforced concrete column frame-bent structureReinforced concrete column frame-bent structureReinforced concrete column frame-bent structureReinforced concrete column frame-bent structure
Storey, total heightOne, 9.6 mOne, 14 mOne, 14 mThree, 27 mFour, 24 m
Base area (m2)6768356430601260300
Total construction area (m2)6768356430603840309
Structure and decorationWallColor steel plate, concrete retaining wallColor steel sandwich panelColor steel plate, concrete retaining wallConcreteConcrete
GroundConcreteConcreteConcreteConcreteConcrete
FloorConcreteConcrete
RoofColor steel sandwich panelColor steel sandwich panelColor steel sandwich panelColor steel sandwich panelColor steel sandwich panel
DoorSteelSteelSteelSteelSteel
WindowPVC steelPVC steel

image

C&D, construction and demolition.

a Regulated in Code for design of building fire protection (GB 50016-2014).

b Regulated in Code for seismic design of buildings (GB 50011-2010).

Table 8.37

Main Buildings and Construction Structure in Nantong City Project (6–10)

ItemMortar WorkshopCementing Material WorkshopCementing Material WarehouseRecycled Aggregate Production WorkshopCar Washing and Water Treatment
No.678910
aConstruction gradeVVVVV
aFireproof endurance ratingIIIIIIIIII
bSeismic precautionary intensity6 degree6 degree6 degree6 degree6 degree
Main structureReinforced concrete column frame-bent structureReinforced concrete column frame-bent structureReinforced concrete column frame-bent structureReinforced concrete column frame-bent structureReinforced concrete structure
Storey, total heightFour, 24 mFour, 24 mThree, 27 mOne, 8.4 m
Base area (m2)374814408509775528
Total construction area (m2)4460178026008641
Structure and decorationWallConcreteColor steel plateUpper: SteelColor steel sandwich panelReinforced concrete
Lower: Porous concrete block concrete
GroundConcreteConcreteConcreteConcreteReinforced concrete
FloorConcreteConcreteReinforced concrete
RoofColor steel sandwich panelColor steel sandwich panelConcreteConcrete, color steel sandwich panel
DoorSteelSteelSteelSteel
WindowPVC steelPVC steelPVC steelPVC steel

image

a Regulated in Code for design of building fire protection (GB 50016-2014).

b Regulated in Code for seismic design of buildings (GB 50011-2010).

Table 8.38

Main Buildings and Construction Structure in Nantong City Project (11–16)

ItemMechanic MaintenanceSubstationLaboratoryProduction Control CenterGuard (I)Guard (II)
No.111213141516
aConstruction gradeVVV
aFireproof endurance ratingIIIIIIIIIIII
bSeismic precautionary intensity6 degree6 degree6 degree6 degree6 degree6 degree
Main structureFrame structureFrame structureFrame structureFrame structureFrame structureFrame structure
Storey, total heightOne, 8 mOne, 5.5 mTwo, 8 mThree, 11.6 mOne, 3.6 mOne, 3.6 m
Base area (m2)840315100810082025
Total construction area (m2)840315201630242025
Structure and decorationWallReinforced concreteReinforced concretePorous concrete blockPorous concrete blockPorous concrete blockPorous concrete block
GroundReinforced concreteReinforced concreteConcrete, ground tileConcreteConcreteConcrete
FloorReinforced concreteReinforced concreteReinforced concreteReinforced concreteReinforced concreteReinforced concrete
RoofReinforced concrete, ground tileReinforced concrete, ground tile
DoorSteelSteelPVC steelPVC steelPVC steelPVC steel
WindowPVC steelPVC steelPVC steelPVC steelPVC steelPVC steel
Inner wallInner wall coatingsInner wall coatingsInner wall coatingsInner wall coatingsInner wall coatingsInner wall coatings
Outer wallOuter wall coatingsOuter wall coatingsOuter wall coatingsOuter wall coatingsOuter wall coatingsOuter wall coatings

image

a Regulated in Code for design of building fire protection (GB 50016-2014).

b Regulated in Code for seismic design of buildings (GB 50011-2010).

image
Figure 8.32 Process of construction waste disposal and production of recycled aggregate in Nantong city project.
The process of construction waste disposal, production of recycled aggregate and premixed mortar is demonstrated in Figs. 8.32 and 8.33, respectively.
An overview of the engineering project is demonstrated in Fig. 8.34.
image
Figure 8.33 Production process of premixed mortar for construction and demolition waste in Nantong city project.
image
Figure 8.34 Overview of centralized disposal and recycling project in Nantong city project.
image
Figure 8.35 General electronic control system of construction and demolition waste processing line.
image
Figure 8.36 Pretreatment section control system.

8.4.2.5. Design of Electronic Control System

General Proposal of Electronic Control System
The core control unit of the electronic control system is PLC control of Siemens S7-300 series. The whole system includes PLC network operating system, touch screen and intelligent host monitoring systems, industrial TV monitoring systems, centralized control, and decentralized stand-alone control system (divided into three module control system, shown in Figs. 8.368.38). The general structure of the system is shown in Fig. 8.35. The control functions include “Environmental protection control without secondary dust generation,” “intelligent production line process control,” “intelligent diagnostic control of key devices,” and “industrial system control.”
PLC network operating system is applied with the structure of one main station and multiple substations. The main station is settled in the central control room, and the substations are located in different sections of the combined production line (for instance, the pretreatment section, fine crushing and sorting section, and recycled powder material production section). The data exchange between the main station and substations is achieved using the network communication.
image
Figure 8.37 Crushing and sorting section control system.
Control and monitoring of the whole production line can be operated in the main station, where countercurrent sequence start control and downstream parking control can also be performed. In substations, the control and monitoring of different modules and sections can be achieved. Operation boxes are equipped for debugging and maintenance of each module.
image
Figure 8.38 Deep processing combined grinding section module control system.
Control of each device and its data collection can be obtained by PLC control through sensors. Physical and mathematical models can be established according to process requirements to achieve the best control effect.
PLC control system is capable of remote diagnostic via the observation and analysis of each input port, output port, and intermediate parameters among the electronic control system. Completely intelligent surveillance monitoring can be achieved in this system.
Each substation is equipped with touch screens, whereas host machine is set in the main station. Dynamic display of the equipment operating status and parameters in each station is reflected on the touch screen (voltage, current, bearing temperature, humidity, vacuum, etc.). Dynamic display of the operating status and parameters of equipment in all production lines equipment can be reflected on the PC screen in the master station.

Table 8.39

Main Products Manufactured in Nantong City Project

ProductRecycled Powder MaterialRecycled Fine SandRecycled Product
Annual production capacity (t)150,000250,000100,000

image

Table 8.40

Main Features and Index of Recycled Building Materials

ProductSize (mm)Performance IndexStandard Consulted
Recycled micropowder material0–0.075Fineness (45 μm square mesh residue) <20%GB/T 1596-2005
Water content <1.0%
Water requirement ratio <105%
Loss on ignition <8.0%Fly ash used for cement and concrete
7 d activity >60%
28 d activity >70%
Recycled fine sand0.16–2.36Micropowder content <3%GB/T 25176-2010
Clay lump content <0.5%
Light material content <0.5%
Firmness <8%Recycled fine aggregate for concrete and mortar
Crushing index <25%
Apparent density >2450 kg/m3
Fineness module 1.90–2.60
Recycled fine aggregate0–5Micropowder content <7%GB/T 25176-2010
Clay lump content <1%
Light material content <1%
Firmness <10%Recycled fine aggregate for concrete and mortar
Crushing index <25%
Apparent density >2350 kg/m3
Fineness module 2.30–3.00
Recycled aggregate5–15Micropowder content <1%GB/T 25177-2010
Clay lump content <0.5%
Recycled aggregate15–22Water absorption <5%
Impurities <1%Recycled coarse aggregate for concrete
Recycled aggregate22–31.5Firmness <10%
Crushing index <12%
Apparent density >2350 kg/m3

image

Terminal of the industrial TV monitoring system is located in the central control room. The complete set of equipment includes display screen, image segmentation, camera, optical terminal, and cable. Either centralized control in central control room and centralized control or independent, decentralized local control is applicable.

8.4.2.6. Products

The main products manufactured in this project include recycled aggregate, recycled powder materials, recycled sand, and gravel. Recycled aggregate is the primary intermediate product and can be used as raw materials for the production of recycled powder materials and other products. Meanwhile, it can also be sold directly as finished products based on the real market condition. Main products manufactured in this project are listed in Table 8.39.
Main products are recycled micropowder material and recycled fine sand. All the products should meet the regulation that is listed in detail in Table 8.40.
Recycled micropowder is the recycled material produced after the grinding of waste clay and waste cement debris in C&D waste, the particle size of which is less than 0.075 mm. Recycled micropowder is of hydration activity and can be used as supplementary cementitious material. The activity index reaches 70% and the surface area exceeds 410 m2/kg, meaning it can partially replace the cement or fly ash in concrete. It is also suitable as a kind of cement admixture, which can effectively reduce the energy consumption and save the cost of cement.
Dry sand is the main raw material in dry mortar production. River sand and manufactured sand should generally be dried in the process. The less than 1% water content of recycled fine sand avoids the drying procedure and thus save the project investment. Meanwhile, the circular particle size of recycled fine sand is suitable as the raw material of mortar production.

8.4.2.7. Water Engineering

Water Supply
Production water (except that outside the mixing station) and domestic water is directly supplied from the municipal water supply network (an inlet pipe DN150, water pressure ≥0.25 MPa). To ensure the reliability of production water, a 150-t homogenize tank is set near the product manufacturing workshop. The production water in this plant is delivered by the pump next to the tank.

Table 8.41

Detailed Amount of Water Used in Nantong City Project

No.Water UsedAmount of water (m3)Pressure (MPa)Note
Day & NightAverage (h)Maximum (h)
1Production water
1.1Concrete workshop888.88.80.252 shift production
1.2Washing6.40.640.6410% water supply
1.2.1Washing of mixing station161.61.60.2Recycled use
1.2.2Washing of mixing vehicle484.84.80.4–0.5Recycled use
1.3Product manufacturing workshop60442 shift production
1.4Hot water for product curing (85°C)532.22.23 shift production
1.5Curing water (sprinkling)131.631.631 shift production
1.6Laboratory130.822.042 shift production
Subtotal233.418.119.4
1.7Unforeseen demand: 10%23.41.811.94
Total256.820.021.4
2Domestic water
2.1421.754.38300 people/day
2.2Subtotal421.754.38
2.3Unforeseen demand: 10%4.20.180.44
Total46.21.934.82
3Firewater
3.1Outdoor1447272Once, 2 h
3.2Indoor1085454Once, 2 h
Total252126126

image

Maximum daily water amount used: 303 m3/d (not including firewater).

The automatic water softener is equipped for the disposal of hot water in product curing section to reduce the hardness of water.
Hot Water
The main methods of preparation of hot water for product curing are: the solar heat collector + air-source heat pumps + hot water tank set on the roof of recycled aggregate production workshop, with heating tubes inside the tank for auxiliary heating.
The preparation of hot bathing water is similar to that of hot water for product curing, the main methods are: the solar heat collector + air-source heat pumps + hot water tank set on the roof of production control center.
The detailed amount of water used in listed in Table 8.41.
Drainage Engineering
1. The combined sewage and wastewater discharged from the domestic facilities after being treated through septic tanks, along with the kitchen water with oil after being treated through the oil separating tank, is discharged into the municipal sewage systems on the south of the plant with an emission flow rate of about 41 m3/d.
2. The car washing waste water is recycled for reuse after solid–liquid separation to save water.
3. The rainwater and washing water in the production field is collected through the drainage ditch and discharged into the riverway in the west side of the plant.
4. No production waste water is discharged during the whole production process.
5. The rainwater is calculated using the rainstorm intensity calculation formula in Nantong city: q = 2007.34 (1 + 0.752 lgp)/(t + 17.9)0.71.
P = 2.0 (years), t = 15 min, ψ = 0.60, the discharging amount is about 1323 L/S.
Other Materials and Facilities Involved in Water Engineering
1. Pipes
a. Water supply:
    Indoor: PVC steel composited pipes and PP-R pipes.
    Outdoor: Steel mesh skeleton plastic composited pipe for water supply (SPE)
Fire prevention: Steel mesh skeleton plastic composited pipe for water supply (SPE)
b. Drainage:
    Indoor: UPVC pipes.
    Outdoor: Reinforced UPVC pipes.
2. Facilities
a. Stable high-pressure water pump set for outdoor fire fighting
    Main pump: XBD3/20-KDB (two pumps, one for backup)
    Q = 20 L/S, H = 30 m, P = 11 kW.
    Pressure-Stabilizing Pump: XBD3.2/5-KDB (two pumps, one for backup)
    Q = 5 L/S, H = 32 m, P = 4 kW.
    Scale of diaphragm air pressure tank: SQL%%C400 × 1400–1.6 V = 70L
b. Water pump set for indoor fire fighting
    XBD5.4/15-DL (two pumps, one for backup)
    Q = 15 L/S, H = 54 m, P = 15 kW.
c. Roof stainless steel firewater tank (12 t, 3 × 2.5 × 2 m) One
d. Hot water for product curing
    Flat-plate solar collector: 300 m2
    Air-source heat pump set:
    MWV-L200T2/S One.
    MWV-L1200T2/S One.
    8.25-t stainless steel heating water tank (2 × 2.5 × 2 m) One.
    33-t stainless steel heat preservation water tank (4 × 5 × 2 m) One.
    Power: 105 kW, 380 V/3N-50 Hz.
e. Hot bathing water preparation
    Flat-plate solar collector: 150 m2
    Air-source heat pump set: FM-20Q (R) One.
    15-t stainless steel heat preservation water tank (3 × 2.5 × 2.5 m) One.
    Power: 46.3 kW, 380 V/3N-50 Hz.
f. Automatic water softener: JDRF-S180T-600/J942T-600 One
    Q = 4–6 t/h Resin loading: 375 kg.

8.4.2.8. Dust Prevention and Removal

The main dust pollutant in the production line of material manufacturing process is the inorganic mineral dust produced in the transportation section. To control its emissions, series of measures are taken, including closed material storage reservoir, pneumatic conveying of powder in pipes strictly sealed, application of pipe screw conveyors, and belt conveyor (with cover) used for bulk material transportation while minimizing the gap between the speed and transfer points.

Table 8.42

Dust Controlling Devices Involved in Nantong City Project

Dust Collecting PointDust CatcherQTYAir Volume (m3/h)Emission Concentration (mg/m3)Emission AmountNote
kg/hkg/d
PretreatmentBag filter612,000≤302.1630.24
PretreatmentBag filter63000≤301.3518.9
Recycled fine aggregate warehouseBag filter83000≤300.456.32 for regular use
Mortar, concreteBag filter23000≤300.182.52
Recycled aggregate productionBag filter23000≤300.182.52
Cementing materialBag filter160,600≤301.81843.63
Cementing materialBag filter112,000≤300.368.64
Cementing materialBag filter63000≤300.4510.85 for regular use
Total326.95123.55

image

QTY, Quantity.

1. Wet construction work should be applied while prevention caps are equipped to prevent the diffusion of dusts.
2. Dust catchers are set in the pretreatment and screening sections.
3. Pneumatic conveying equipment are used for the unloading of bulk powder materials, sealed pipes are used throughout the whole process.
4. Bag filters are equipped on top of the powder material warehouse.
5. Spiral pipe conveyors are used for the powder materials transportation.
6. Bag filters are equipped in the blending device of recycled product manufacturing section.
7. Dust prevention caps are covered on the belt conveyors.
8. Enclosed structures are applied in the pretreatment workshops and recycled aggregate warehouses.
9. Bag filters are equipped on top of the recycled aggregate warehouse.
10. The material drop distance should be minimized.
Thirty-two dust catchers (for 32 dust production points) are set throughout the plant and the dust collecting efficiency can be up to 99.5% and the dust emission is less than 30 mg/Nm3. The dust controlling devices involved in this project are listed in Table 8.42.

8.4.2.9. Labor Organization

The shift arrangement in this project is listed below:
252–300 annual working days;
The main production posts: two shifts, three shifts;
The auxiliary production posts: one-shift;
Eight working hours per shift.
Information of labor force involved in this project is listed in detail in Table 8.43.

8.4.3. Utilization Center of Recycled Resources Produced by C&D Waste in Suzhou City

8.4.3.1. General Introduction

Annual generation amount of C&D waste in Suzhou city is about 5 million tons. The annual handling capacity of this project is 1,000,000 t while the generation of recycled products is about 900,000 t.

8.4.3.2. Main Structures and Processes

Main structures including office buildings and manufacturing workshops are listed in Table 8.44.

Table 8.43

Information of Labor Force Involved in Nantong City Project

DepartmentLabor
Day ShiftMorning ShiftSwing ShiftNight ShiftNonshiftTotal
C&D waste storage111115
C&D waste pretreatment1111628
Recycled aggregate warehouse1113
Recycled fine aggregate warehouse1113
Recycled aggregate production88622
Product curing22228
Mortar88622
Concrete44412
Cementing material555520
Cementing material storage house333312
Mechanic, auto maintenance5222213
Storage yard for finished products222118
Technical (including experiments)61119
Guard122229
Car washing and water pool1113
Driver (forklift)2772624
Driver (mortar and concrete vehicle)555520
Logistics2421110
Financing33
Administration4228
Management33
Total3570681953245

image

C&D, construction and demolition.

Table 8.44

Main Structures Including Office Buildings and Manufacturing Workshops for Annual Handling Capacity of 1,000,000 t Construction and Demolition Waste in Suzhou City Project

No.ItemLand Occupation (m2)Construction Area (m2)Note
1Comprehensive office building40012003 floors
2Mechanical repair workshop2102101 floor
3Distribution room1201201 floor
4Fire-fighting pool and pump house9212 (pump houses)Pool area 480 m3
5Guard room24241 floor
Metering room24241 floor
6Exhibition area for recycled building materials1566
7Exhibition area for finished building materials11,926
8Storage area for raw materials12,950
9Pretreatment and brick production workshop54005400Partially exposed basement, 12 m height
10Recycled mortar production workshop45004500Partially exposed basement, 12 m height

image

image
Figure 8.39 Whole process of construction and demolition waste disposal of utilization center in Suzhou city project.
image
Figure 8.40 Process of manufacturing of recycled blocks and bricks in Suzhou city project.
Comprehensive disposal of C&D waste in this project includes unloading, pretreatment (crushing, magnetic and air sorting, screening, etc.), manufacturing of and curing of recycled blocks and bricks, production of recycled cement mortar, and building materials. C&D waste is sent into the storage area for unloading and stacking. Feeders and enclosed belt conveyors are equipped in this section, whereas excavators are used for loading of raw materials into feeders and transporters, in which C&D waste is conveyed to the pretreatment section. The first process is crushing; materials coming out of the outlet are classified into different sizes so that they can meet the demands for the subsequent recycled products. The crushed materials are removed of iron and metal substances and then sent for air sorting, where light materials like plastics and wood are separated. Materials are classified into five different groups based on their size through the vibrating screener (≤4.75, 4.75–9.5, 9.5–20, 20–31.5, and ≥31.5 mm). These aggregates are sent to isolated storage pits through belt conveyors. The whole process is demonstrated in Fig. 8.39.
image
Figure 8.41 Material balance of the whole utilization project in Suzhou for annual handling capacity of 1,000,000 t construction and demolition waste in Suzhou city project.
Materials of size below 4.75 mm are fine aggregates and can be used as raw materials for recycled cement mortar, blocks, and bricks production. Materials of size between 4.75 and 9.5 mm are coarse aggregates and can be used as raw materials for recycled blocks. Materials of size between 9.5 and 20 mm, 20 and 31.5 mm, and above 31.5 mm can be used as road materials like stable layer of water below the pavement.
Process of manufacturing of recycled blocks and bricks is introduced below and demonstrated in Fig. 8.40.
The crushed C&D waste is used as raw materials and is mixed with certain ratio of water, cement, and paint. Then it is sent through an automatic process line including proportioning, mixing, molding, curing, splitting, and stacking. Main manufacturing equipment are proportioning and mixing process line, concrete product molders, conveyors, curing plates, and molders for recycled products.

8.4.3.3. Material Balance

The material balance of the whole utilization center of recycled resources produced by C&D waste in Suzhou city is demonstrated in Fig. 8.41.

8.4.3.4. Layouts and Land Coverage

Land coverage of unloading and storage area is 12,950 m2 in which the hopper and enclosed belt conveyors are equipped. Excavators are used as loading machines for waste and materials. Land coverage of pretreatment and brick manufacturing workshop is 90.00 × 60.00 m, which is separated into pretreatment area, classified storage area of aggregate, brick manufacturing facilities area, and steam curing area. The pretreatment area is about 40.00 × 30.00 m in size with crushers, magnitude and airblow separators, vibrating screens, and belt conveyors.
The temporary storage area consisted of five separated storage pits and its coverage area is about 45.00 × 15.00 m. (1) Storage pit for aggregate of size less than 4.75 mm, land coverage 5.00 × 15.00 m, storage volume 200 m3, (2) Storage pit for aggregate of size 4.75–9.5 mm, land coverage 7.50 × 15.00 m, storage volume 300 m3, (3) Storage pit for aggregate of size 9.75–20.00 mm, land coverage 10.00 × 15.00 m, storage volume 400 m3, (4) Storage pit for aggregate of size 20.00–31.50 mm, land coverage 12.50 × 15.00 m, storage volume 500 m3, (5) Storage pit for aggregate of size larger than 31.50 mm, land coverage 10.00 × 15.00 m, storage volume 400 m3.
Land coverage of brick manufacturing workshop is 45.00 × 30 m, in which additive storage house, mixing system, twin-shaft mixer, brick producer, stacker, and composite carts are equipped. Land coverage of steam curing workshop is also 45.00 × 30 m, in which steam curing kiln and boilers are installed. Oil-fired boilers are used of which the steam volume is 2 t/h and the steam pressure is 0.20–0.25 MPa.

Table 8.45

Comparison of Two Dust Removal Methods

Bag FilterMicron Dry Fog Spraying
Energy costHighLow, less water consumption
OperationComplexEasy
Land coverageLargeSmall
InstallationHeavy machines, large size of wind tubes, complex installationEasy
InvestmentLargeSmall
Removal effectLow for small particlesHigh for comprehensive treatment, especially PM 2.5

Table 8.46

Main Dust Removal Facilities Involved

No.ItemStyleQTYNote
1Centrifugal fanGas flow 2000 m3/h, air pressure 400–600 Pa, rotation speed 1400 r/min, N = 2.2 kW3
2Pulse bag filterN = 5 kW1
3Flue pipe320 × 120 mm320PVC
160 × 120 mm480PVC
φ400 mm120Galvanized steel
4Cover1000 × 1000 mm12Stainless steel
5Micron dry fog dust removal systemSauter mean diameter SMD: 1–10 μm, with host device, gas tank, electric controlling system, spray tank, heating and insulation systems2
6Remote fog spraying systemApproximately 50–100 μm2

image

QTY, quantity.

Waste, materials, and aggregate are transferred to recycled mortar workshop from pretreatment section through belt conveyor, the land coverage of this workshop is 90.00 × 50.00 m, in which ingredients storage house, dryers, and mixers are equipped. All the transportation facilities are fully enclosed. Meanwhile, coverage of storage house of products and demonstration area of recycled products is 11,926 and 1566 m2.

8.4.3.5. Dust Controlling System

Dust controlling system is also an important section in this project. The main process is “micron dry fog spraying at initial + bag filter at terminal,” the comparison of the two methods is listed in Table 8.45. The equipment used includes centrifugal blower (CF-11, 2000 m3/h, pressure 400–600 Pa, rotation speed 1400 rpm, N = 2.2 kW), pulse-jet bag series dust filter (N = 5 kW), micro dry fog spraying system (Sauter mean diameter SMD: 1–10 μm), and remote spray system (50–100 μm).
Main dust removal facilities involved are listed in Table 8.46, including three centrifugal fans, a pulse bag filter, flue pipes, covers, micron dry fog dust removal systems, and remote fog spraying systems.

Table 8.47A

Main Facilities Throughout the Utilization Project for Annual Handling Capacity of 1,000,000 t Construction and Demolition Waste in Suzhou City Project

No.ItemStylePower (kW)UnitQTY
Feeding Section
1ExcavatorVolume 1.5 m310Set2
2Hopper2800 × 2800Set3
3Belt conveyorsSuit1
Pretreatment Section
1CrusherCPSJ-40355Set3
2Electromagnetic separatorsRCDD-12Set3
3WinnowingSet2
4Vibration sieve4.75 mm/9.5 mm/20 mm/31.5 mmSet3
5Belt conveyorsSuit1
Temporary Storage Section for Aggregates
1Double flap grabbers (2 t)DS2 (1.0) 1.2–0015Set2
2Fabric machine (with belt)500 × 1000Set2
Brick Production Section
1Host computerMT130-70S200Suit2
2Fully automatic brick molding machineMT130-70SSuit2
3Lifting and transportation sectionMT130-70S MaticSuit2
4Palletizing sectionMT-CUBER-STSuit2
5Ingredients mixing sectionMP1500/1000 MP500/300Suit2
6Automatic cart pitsMT130/70S LSCSuit1
7Steel pallets2592 palletsSuit2
8Wood pallets10,000 palletsSuit2
9Conservation kilnSuit2
10Excavator2
11Forklift2
12Scraper4
13Steam boiler2 t/hSuit1
Manufacturing Section for Recycled Mortar
ARaw material storage section170
1Aggregate warehouse3 m38
2Accessories warehouse2.5 m35
3Feeding beltVariable frequency, B = 600 mmSet3
Table Continued

image

No.ItemStylePower (kW)UnitQTY
BDrying sectionTumble dryer, D = 1.5 mSet1
CScreening and lifting system for thermal materials
1Screw conveyorSet1
2Vibratory screening machineD = 2.5 mmSet1
3Central chain bucket elevatorSet1
DClassified sieving machine0.3 mm/0.6 mm/1.2 mmSet1
EIntensive mixerEvenness 1:100,000Set1
FPneumatic systemSuit1
GElectronic controlling systemSuit1
HDust removal sectionSuit1
Corollary Facilities
1Crane8 t13Set1
2LoaderVolume 5 m32
3Dump truck12 t4
4Mobile crushing facilityDisposal capacity 80 t/h, gas/electric80Set1
5Mobile screening facilityDisposal capacity 80 t/h, gas/electric50Set1
Mechanic Repair Facilities
1LatheCD6140 ASet1
2Bench drillZ520-2 ф12.7Set1
3GrinderS35L-250Set1
4WelderBX3-550Set1
5ViseSet2
6Gas welding systemSet1
7ChargerGCA804/0–160VSet1
8PlanerBD6063Set1

image

QTY, quantity.

Table 8.47B

Main Facilities Throughout the Utilization Project for Annual Handling Capacity of 1,000,000 t Construction and Demolition Waste in Suzhou City Project

No.ItemStyle/SpecificationQuantityNote
1Centrifugal air blowerCF-11, flow rate 2000 m3/h, air pressure 400–600 Pa, rotation speed 1400 r/min, N = 2.2 kW32 for use, 1 for backup
2Pulse bag filterN = 5 kW1
3Flue pipe320 × 120 mm320PVC
160 × 120 mm480PVC
φ400 mm120Galvanized steel
4Collecting cover1000 × 1000 mm12Stainless steel
5Micro dry atomized dust suppression systemAtomization particle size 1–10 μm, host machine, gas tank, electric control system, spray tank assembly, sprayer with universal joints, electric tracer, and heat preservation system2
6Remote atomized spraying systemParticle size of about 50–100 μm2

image

Table 8.48

Features and Quality Requirements of the Recycled Cement Mortar

MortarStrength GradeConsistency (mm)Water Retention Rate (%)14 d Tensile Bond Strength (MPa)Frost Resistance
Strength Loss Ratio (%)Mass Loss Ratio (%)
Masonry mortarM2.5/M5/M7.5/M10/M1550–90≥82-≤25≤5
Plastering mortarM5/M10/M1570–100≥82≥0.15≤25≤5
Ground mortarM1530–50≥82-≤25≤5

image

Table 8.49

Compression Strength Grade of the Recycled Water Permeable Road Bricks

Compression Strength GradeAverage (MPa)Minimum of Single Block (MPa)
Cc20≥20.0≥15.0
Cc25≥25.0≥20.0
Cc30≥30.0≥25.0
Cc35≥35.0≥30.0
Cc40≥40.0≥35.0
Cc50≥50.0≥42.0
Cc60≥60.0≥50.0

8.4.3.6. Main Facilities

The main facilities throughout the utilization project are listed in Table 8.47, which include all manufacturing sections like pretreatment, storage, sorting, and recycling processes. This table can be consulted to as a reference in other C&D waste recycling and utilization projects.

8.4.3.7. Products

The final products in this engineering project can be classified into four groups: Recycled cement mortar, recycled water permeable road bricks, recycled wall blocks, and recycled roadbed materials. The features and quality requirements of the four products are introduced below.
1. Recycled cement mortar. Recycled cement mortar using the recycled fine aggregate after presorting in this project can be produced into masonry mortar, plastering mortar and ground mortar (cannot be used as ground surface layers). The features and quality requirements of the recycled cement mortar are listed in Table 8.48.
2. Recycled water permeable road bricks. These are the road bricks with large water permeability produced using the C&D waste recycled aggregate and cement as raw materials along with proper amount of admixture; they are then molded and formed with mixture of water and naturally or steam curing is finally performed. The compression strength grades of the recycled water permeable road bricks are listed in Table 8.49.
Features and quality requirements of the water-permeable road brick produced by recycled aggregate are listed in Table 8.50.
3. Recycled wall blocks. The nominal diameter of aggregate used for recycled wall blocks should be less than 10 mm and the requirements are the same as those discussed earlier. The compression strength of recycled wall blocks is listed in Table 8.51.

Table 8.50

Features and Quality Requirements of the Water-Permeable Road Brick

ItemFeatures and Requirements
Maximum projection size of frontal adhesive skin and defect parts (mm)≤10
Maximum projection size of losing angle/corner (mm)≤15
CrackMaximum projection size of the nonpenetrating cracks (mm)≤10
Penetrating cracksNot allowed
DelaminationNot allowed
Variegated color, color deviationNot obvious
Abrasion resistancePit length not large than 38 mm
Water-retaining propertyNot less than 0.6 g/cm2
Water permeation coefficientWater permeation coefficient (15°C)  0.01 cm/s
Frost resistanceStrength loss should be less than 20.0% after 25 freezing–thawing cycles

image

Table 8.51

Compression Strength of Recycled Wall Blocks

Strength GradeAverage (MPa)Minimum of Single Block (MPa)
MU3.5≥3.5≥2.8
MU5≥5.0≥4.0
MU7.5≥7.5≥6.0
MU10≥10.0≥8.0
MU15≥15.0≥12.0
MU20≥20.0≥16.0

Table 8.52

Features and Quality Requirements of the Recycled Wall Blocks

ItemFeatures and Requirements
Minimum wall thickness (mm)As load-bearing walls≥30
Not as load-bearing walls≥16
Rib thickness (mm)As load-bearing walls≥25
Not as load-bearing walls≥15
Defected cornerNumber≤2
Minimum projection size in three directions (mm)≤20
Accumulative extended projection size of cracks (mm)≤20
Bend (mm)≤2
Frost resistance index (D25)Mass loss ratio (%)≤5
Strength loss ratio (%)≤25

image

Features and quality requirements of the recycled wall blocks are listed in Table 8.52.
4. Roadbed materials. Those particles of size larger than 31.5 mm coarse aggregate can be used as the roadbed materials like the water stable layer under the sidewalk, or the lower cushion of the roadbed. The compression strength should meet the demand regulated in Technical guidelines for construction of highway road bases (JTJ034-2000).

8.4.4. Demonstration Project of C&D Waste Resource Reuse in Xi'an City

The annual disposal capacity of this project in Xi'an city is 1,000,000 t, whereas the generation of recycled aggregate, premixed mortar, cement admixture, building blocks, and wallboards products is about 500,000, 200,000, 40,000, 200,000, and 200,000 t, respectively.

Table 8.53

Main Materials Consumed in This Project for Annual Handling Capacity of 1,000,000 t Construction and Demolition (C&D) Waste in Xi'an City Project

ProductRecycled Coarse AggregateRecycled Fine AggregateCement AdmixturePremixed MortarBuilding BlocksWallboard/
Annual yield334,000 t253,000 t40,000 t200,000 t100,000 m3 × 2 lines200,000 m2/
Total
Coarse aggregate33.4/4.0/12.31.350
Fine aggregate/25.3/13.49.10.948.7
Powder materials////1.20.11.3
Cement///5.53.10.38.9
Other materials///1.11.90.23.2
Annual C&D waste consumed33.425.34.013.422.62.3100

image

image
Figure 8.42 Overall process of construction and demolition waste disposal in Xi'an city project.
Enclosed workshops are applied in this project while multiple dust and noise prevention method are used. For instance, the crushing workshops are located underground, finished aggregated are stored in enclosed tanks, covers are equipped around the belt conveyors, PPDC pulse bag filters are set near the dust emission spots. Meanwhile, the double-layer walls and acoustic insulating material are also added to the structure of the workshop.
The main materials consumed are listed in Table 8.53.

8.4.4.1. Engineering Technical Process

The overall disposal process is demonstrated in Fig. 8.42. The whole demonstration project includes storage field of C&D waste, recycled aggregate production workshops, premixed mortar and concrete products manufacturing workshops, storehouse for finished products, test building, office building, and residual area.
Recycled aggregates that are able to replace natural sand and gravels are produced in this project through classified crushing and screening. Some of these aggregates can be applied as raw materials in deep processing process and are used to produce premixed mortar, cement admixture, and concrete. The rest are sold as commercial aggregates to concrete mixing stations, mortar plants, and backfilling of road base. The fine powder sorted is used in concrete production while the loess screened out is directly supplied to garden department as soil.
image
Figure 8.43 General process of aggregate production in Xi'an city project.
image
Figure 8.44 Process of premixed mortar production in Xi'an city project.
The recycled products should meet the demand required in relevant standards, including those of aggregates, gravel, concrete units, mortar, and wallboards. General process of aggregate production is demonstrated in Fig. 8.43.
Wood, paper, plastic, and iron blocks are separated manually after C&D waste is transferred into the mixing house. Then the waste is conveyed to aggregate production workshops for deep processing. The 5–31.5 mm coarse aggregate, 0–5 mm fine aggregate and powder materials are delivered separately.
Process of premixed mortar production is demonstrated in Fig. 8.44.
Process of concrete production in this project is demonstrated in Fig. 8.45.
Fine aggregate and powder material belts are operated on and used to transport them directly to the mortar production workshop. The water content can be reduced to below 0.5% using horizontal drying machines. Cement is added based on the target strength and application.
image
Figure 8.45 Process of concrete product manufacturing in Xi'an city project.
Process of wallboard production in this project is demonstrated in Fig. 8.46.
The main facilities used in this project are crushing, screening, transporting, gravel manufacturing, drying, mortar dry premixing, and wallboard and bulk components manufacturing sections, which are listed in detail in Table 8.54.
Annual disposal capacity of construction and demolition waste is 1 million tons in this project. A stockpile for raw materials of size 175 × 110 × 15 m is equipped to ensure the continuity and stability of production. The stockage volume is 182,000 m3 and holding capacity of C&D waste is 182,000 × 1.3 = 240,000 t based on 10 m of stack height, 40 degrees of natural repose angel of C&D waste, and 1.3 t/m3 of stacking density. The land coverage area is 175 × 110 = 19,250 m2, and the stockage area is divided into four districts, namely, waste brick warehouse, waste concrete warehouse, and two mixed warehouses. All these warehouses are enclosed steel framework structures with concrete walls to prevent the rain and dust.
image
Figure 8.46 Process of wallboard production in Xi'an city project.
The land coverage area of aggregate manufacturing workshop is 120 × 50 m = 6000 m2, and that of mortar and wallboard-component combined manufacturing workshops are 100 × 50 = 5000 m2, and 220 × 70 = 15,400 m2, respectively, with a sum of 26,400 m2.
Silo structures are used in aggregate warehouses to improve land utilization ratio. The volume of the 31.5-mm coarse aggregate warehouse, for instance, is Φ40 × 20 m = 25,000 m3 (storage capacity of about 3.5 million tons), which covers an area of 1256 m2. As for other warehouses, the volume, storage capacity, and land coverage area can be consulted to Table 8.53.
Silo structures are also used in premixed mortar warehouses, which include the decorative mortar warehouse (storage capacity of 1500 t, land coverage 114 m2), masonry mortar warehouse (storage capacity of 1800 t, land coverage 266 m2), and packed decorative and masonry mortar warehouses. The detailed features are listed in Table 8.55. All these warehouses are enclosed steel framework structures with concrete walls to prevent the rain and dust.

Table 8.54

Main Facilities Involved and Their Parameters for Annual Handling Capacity of 1,000,000 t Construction and Demolition Waste in Xi'an City Project

No.ItemBuilding Dimensions (m)Storage Volume (t)Land Coverage (m2)Total (m2)Architectural Style
1Stockpile for raw materials175 × 110240,00019,25019,250Frame-shear wall structure
2Aggregate manufacturing workshop120 × 50/60006000Frame-shear wall structure
3Mortar manufacturing workshop100 × 50/50005000Frame-shear wall structure
4Concrete product manufacturing workshop220 × 70/26,40026400Frame-shear wall structure
5Aggregate warehouse///6000/
5.13.15-mm coarse aggregate warehouseΦ40 × 2035,0001256/Steel silo
5.210-mm coarse aggregate warehouseΦ31.4 × 2020,000744/Steel silo
5.35-mm coarse aggregate warehouseΦ31.4 × 2020,000744/Steel silo
5.42.5-mm coarse aggregate warehouseΦ16 × 205200201/Steel silo
5.5Earth material warehouseΦ16 × 205200201/Steel silo
5.6Fine powder warehouseΦ16 × 205200201/Steel silo
6Mortar warehouse///5000/
6.1Decorative mortar warehouseΦ12 × 201500114/Steel silo
6.2Masonry mortar warehouseΦ13 × 201800266/Steel silo
6.3Masonry mortar warehouseΦ13 × 201800266/Steel silo
Table Continued

image

No.ItemBuilding Dimensions (m)Storage Volume (t)Land Coverage (m2)Total (m2)Architectural Style
6.4Packed decorative mortar warehouse20 × 6500111/Frame-shear wall structure
6.5Packed masonry mortar warehouse20 × 121000222/Frame-shear wall structure
7Curing room///18,525Frame-shear wall structure
8Office, residual, gardening area210 × 70//14,700Frame-shear wall structure
9Road///7150/
Total land coverage100,875 m2

image

Table 8.55

Main Facilities Involved for Annual Handling Capacity of 1,000,000 t Construction and Demolition Waste in Xi'an City Project

No.Main FacilitiesStylePower (kW)Unit Cost (Dollar)Total (Dollar)Note
Recycled Aggregate Workshop
1Vibrating feederZSW490 × 1101512,71212,712
2Jaw crusherPE900 × 1200110103,188103,188
3Simmons cone crusherCSB240240209,368209,368
4Centrifugal impact crusherVS I 114040086,73886,738
5Circular vibrating screen2YA21603020,93720,937
6Circular vibrating screen3YA21607422,43244,8652 screens
7Vibrating feederGZD200 × 1204.452345234
873.4483,041
Premixed Mortar Workshop
1DryerHorizontal50/
2Mortar processing lineSHEF-20SJ200747,742747,742
250747,742
Wallboard-Component Combined Workshop
150 blending stations × 429,910119,639
2Recycled aggregate board processing lineSHEF-20BC120747,742747,742
3Recycled aggregate board processing lineSHEF-10 KC220299,097299,097
3401,166,477
Other
1Belt conveyor650 mm5.51,944,129/m74,774
25 loadersWheel XG951-III16259,819299,097
167.5373,871
Total1630.92,786,086

image

Table 8.56

Typical Mix Proportion of C30 Concrete

MaterialCementSandStoneFly Ash
Amount, kg/m33007001100100

image

The land coverage of wallboard-component combined workshop is 18,525 m2.
The residual and office area is divided into office building, laboratory building, restaurant, dormitories, staff area, gardening districts, etc. The total land coverage area is 210 × 70m = 14,700 m2.
The total land coverage area of the plant in this project is 100,875 m2.

8.4.4.2. Main Facilities Involved

The main facilities involved in this demonstration project are listed in detail in Table 8.55.

8.4.4.3. Economic Performance of C&D Waste Resource Reuse in This Project

Recycled Aggregate
Studies on the recycled aggregate reveal that those produced by C&D waste are mainly cracked concrete, mortar, and bricks. Production from recycled aggregate to concrete of high strength is unpractical due to its complex components and diversified material strength, but production of C30 and below C30 concrete is feasible. Take C30 as an example (Table 8.56).
..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset