Chapter 5
Practice Test 1

This practice exam can be used to simulate the actual CompTIA Project+ exam. The practice exam is balanced in the percentage and number of questions it includes in accordance with the mixture of questions that you will see on the actual exam, although the actual exam may have more questions. That breakdown is as follows:

Domain 1: Project Basics
Domain 2: Project Constraints
Domain 3: Communication and Change Management
Domain 4: Project Tools and Documentation
36%
17%
26%
21%

Set a timer for 75 minutes and attempt to complete this practice test without reference to other materials until the test is over.

  1. 1. What are two defining characteristics of a project? (Choose two.)

    1. Reworking an existing project
    2. An organized effort to fulfill a purpose
    3. Has a specific end date
    4. Routine activities to an organization
    5. Blueprints needed to construct a building
  2. 2. Why would a buyer issue a purchase order?

    1. To describe the quantity of goods and services needed and what price will be paid.
    2. To outline the intent or actions of both parties before entering a contract.
    3. To stop another company from using their intellectual property and to inform them not to do it again.
    4. The situation requires more flexibility and simplicity than a contract.
  3. 3. To which project-centric document would you refer to get a description of the project, find out the key deliverables, and gain an understanding of the success and acceptance criteria for the project?

    1. Project charter
    2. Project schedule
    3. Scope statement
    4. Meeting minutes
  4. 4. All of the following are forms of organizational change, EXCEPT

    1. Relocation
    2. Business demerger
    3. Organic shifts
    4. Business merger
  5. 5. When the schedule slips on a project because the work is taking longer than planned, what type of common project change does this represent?

    1. Funding change
    2. Timeline change
    3. Risk event
    4. Requirements change
  6. 6. Scrum is which one of the following?

    1. A phrase referring to the overcomplication of a project
    2. An Agile technique where backlogs are used
    3. Creating better, more detailed explanations for senior management
    4. The continuous modification and detailing of the project plan
  7. 7. The process of assigning numerical probabilities to each risk and the impacts on project objectives is known as which one of the following?

    1. Identify risk
    2. Quantitative risk analysis
    3. Qualitative risk analysis
    4. Risk categorization
  8. 8. What type of project management tool is depicted here?

    Graph showing the bars plotted for months from April to July versus activity numbers from 1 to 5. The longest bar is at 4 from April to June end and shortest is at 3 from May end to June end.
    1. Fishbone diagram
    2. Gantt chart
    3. Collaboration tools
    4. Process diagram
  9. 9. Which project role promotes the need and urgency of a project, as well as advertising the project’s success?

    1. Project scheduler
    2. Project manager
    3. Project sponsor or champion
    4. Project coordinator
  10. 10. The EV for a project is 800, and the AC is 1200. The CPI for the project would be which one of the following?

    1. 1.5
    2. 400
    3. .667
    4. 2000
  11. 11. As a part of a daily scrum meeting, the team seeks to share information in three areas. Which set of questions represents the topics of this knowledge sharing?

    1. What did I accomplish today? Who will you be working with today? What obstacles are preventing progress?
    2. What did I accomplish yesterday? What will I do today? What are the necessary next steps?
    3. What did I accomplish yesterday? What will I do today? What obstacles are preventing progress?
    4. What did I accomplish yesterday? Who will you be working with today? What obstacles are preventing progress?
  12. 12. Which document describes the goods or services an organization is interested in procuring from outside the organization?

    1. RFI
    2. SOW
    3. RFP
    4. RFQ
  13. 13. Members of a project team were recently replaced with consultants with more expertise in the subject matter. What type of organizational change disrupted this project?

    1. Internal reorganization
    2. Business split
    3. Outsourcing
    4. Relocation
  14. 14. What does SWOT stand for?

    1. Situation, work, open source, traceability
    2. Strengths, work, opportunities, traceability
    3. Situation, weaknesses, open source, threats
    4. Strengths, weaknesses, opportunities, threats
  15. 15. All of the following are common types of project changes, EXCEPT

    1. Scope changes
    2. Requirement changes
    3. Organizational changes
    4. Timeline changes
  16. 16. When considering the base communication model, what are the basic elements that are needed? (Choose three.)

    1. Transmission
    2. Receiver
    3. Inbox
    4. Sender
    5. Nonverbal communication
    6. Decoder
    7. Message
  17. 17. Cheryl is a technical lead on a project that is wrapping up remote work at a customer site. What is the best method to communicate the work efforts and next steps with the customer?

    1. Closure meeting
    2. Virtual meeting
    3. Kickoff meeting
    4. In-person meeting
  18. 18. The approved budget for given work to be completed within a specific timeframe is called which one of the following?

    1. Planned value
    2. Cost variance
    3. Earned value
    4. Actual costs
  19. 19. In what step would the make-or-buy decision occur?

    1. During the kickoff meeting
    2. During the design of the product or service
    3. In the execution of the project plan
    4. In the creation of the procurement plan
  20. 20. When should an employee’s performance expectations be set for a project?

    1. When the functional manager sets annual goals
    2. During the first meeting with a new team member
    3. During the stakeholder identification meeting
    4. During the employee performance review
  21. 21. When a project team is assigned to work solely on a project, it is an example of what type of resource?

    1. Dedicated
    2. Collocated
    3. Shared
    4. Physical
  22. 22. Developing contingency reserves to deal with risks, should they occur, is known as which one of the following?

    1. Active acceptance
    2. Passive acceptance
    3. Exploit
    4. Transfer
  23. 23. A project team based in Europe needs to conduct a job interview with a candidate in India. What is the best communication method to conduct the interview?

    1. In-person meeting
    2. Virtual meeting
    3. Social media
    4. Email
  24. 24. What are milestones?

    1. Characteristics of deliverables that must be met
    2. Major events in a project used to measure progress
    3. Checkpoints on a project to determine go/no-go decisions
    4. A measure of the distance traveled on a project
  25. 25. What type of project management tool is depicted here?

    Bar graph showing 	'Most reworked items	' on project management tool where the bar is drawn for findings versus requirements like exterior, kitchen, electrical, plumbing, paint, et cetera.
    1. Pareto chart
    2. Project schedule
    3. Histogram
    4. Gantt chart
  26. 26. At the beginning of a work period, or sprint, there is a sprint planning meeting. What does this meeting accomplish?

    1. Set a realistic backlog of items to be completed during this iteration
    2. Set the communication and quality plans for the project
    3. Prepare the project charter and kickoff meeting
    4. Get a head start of the work needed on the project
  27. 27. Which vendor solicitation method is best to use when more data is needed about the goods and services that need to be procured?

    1. Request for proposal (RFP)
    2. Request for quotation (RFQ)
    3. Request for information (RFI)
    4. Statement of work (SOW)
  28. 28. A large company is struggling with inconsistent results in hiring and retention because of a decentralized HR model. What type of organizational change could help this problem?

    1. Business split
    2. Outsourcing
    3. Relocation
    4. Internal reorganization
  29. 29. A systematic and independent examination of project procedures, documentation, spending, statutory compliance, and reporting is known as which one of the following?

    1. Audit
    2. Gate review
    3. SCRUM retrospective
    4. Project change
  30. 30. All of the following are examples of deliverables, EXCEPT

    1. Blueprints
    2. User documentation
    3. Finished product
    4. Signoff on the project charter
  31. 31. Which of the following are types of mutually binding documents? (Choose three.)

    1. SCRUM retrospective
    2. Agreements/contract
    3. Memorandum of understanding
    4. Issues log
    5. Purchase order
    6. Histogram
  32. 32. A company is struggling with timely billing of their customers, so they hire a consultant to help determine all of the steps and workflow needed to send a bill. Which tool would the consultant most likely use?

    1. Pareto chart
    2. Process diagram
    3. Project charter
    4. Project scheduling software
  33. 33. A company has procurement teams at each of their 22 locations, leading to potentially purchasing the same products from 22 different suppliers. To help save money, the company decides to centralize and standardize the reporting function. What type of business change is this?

    1. Internal reorganization
    2. Staff turnover
    3. Business process change
    4. Outsourcing
  34. 34. Once a change request is submitted, where should it be recorded and assigned an identification number for tracking purposes?

    1. Change request log
    2. Risk register
    3. Business process repository
    4. Issue log
  35. 35. Which of the following factors present challenges for a global project team located on different continents? (Choose three.)

    1. Language barriers
    2. Level of report detail
    3. Technological factors
    4. Time zones
    5. Cultural differences
    6. Criticality factors
  36. 36. All of the following would be updates to the risk register following the qualitative risk analysis, EXCEPT

    1. Watch list of low-priority risks
    2. Risks requiring near-term responses
    3. Causes of risks
    4. Numerical evaluation of each risk
  37. 37. What type of project management tool is depicted here?

    Flowchart showing project management tools having 	'Change Control Board	' to 	'Check the Change Form and 	'Customer	' to 	'Form Complete	' via 	'Change Request	'. 	'If yes	' then to 	'Implement Change	' via 	'Check the Change Form	' and 	'if no	' it goes back to 	'Customer	'.
    1. SCRUM retrospective
    2. Fishbone diagram
    3. Process diagram
    4. Risk register
  38. 38. What are project assumptions?

    1. Factors considered to be true for planning purposes
    2. Factors considered to be true for control purposes
    3. Internal or external factors affecting the project team
    4. Factors that restrict the project
  39. 39. Your friend has hinted that she would like a special gift for her birthday. The following steps are needed for the gift exchange:

    • Enjoyment of her gift
    • Put card on the gift
    • Wrap present
    • Choose gift
    • Give her the present
    • Make purchase
    • Fill out the card

    What is the correct sequence for project Happy Birthday?

    1. Choose gift; Make purchase; Put card on gift; Wrap present; Fill out card; Enjoyment of her gift; Give her the present
    2. Give her the present; Put card on gift; Wrap present; Make purchase; Fill out card; Enjoyment of her gift; Choose gift
    3. Put card on gift; Give her the present; Fill out card; Make purchase; Enjoyment of her gift; Choose gift; Wrap present
    4. Choose gift; Make purchase; Wrap present; Fill out card; Put card on gift; Give her the present; Enjoyment of her gift
  40. 40. A vendor is very strict on insisting upon formal change control on a project for a customer and few changes are actually getting approved. Which contract vehicle would cause a vendor to behave in this way?

    1. Fixed-price
    2. Request for proposal
    3. Time and materials
    4. Cost-reimbursable
  41. 41. The project team is required to attend a daily stand-up meeting to discuss the project activities and roadblocks. Which document lets the project team know that they need to attend this meeting?

    1. Project schedule
    2. Scope statement
    3. Communication plan
    4. Project charter
  42. 42. The joining of two businesses to come together and operate as one, single entity is known as which one of the following?

    1. Business acquisition
    2. Business merger
    3. Business process change
    4. Business split
  43. 43. A local cable company accidentally cuts the fiber-optic cables going into the project site, thereby disrupting communication. The team requests technicians from the company to repair the damage quickly. What is the trigger for this communication?

    1. Incident response
    2. Task initiation
    3. Risk register updates
    4. Business continuity response
  44. 44. An offshore team has issued a holiday schedule consistent with their customs to the project manager. The holiday schedule issued by the team differs from the company’s established holiday schedule. This is an example of which one of the following?

    1. Criticality factors
    2. Language barriers
    3. Time zones
    4. Cultural differences
  45. 45. A government agency has hired a firm to perform work on its sewer system. As a part of the RFP, the agency requires the successful vendor to carry insurance for errors and omissions. What type of risk strategy is this?

    1. Transfer, negative risk strategy
    2. Exploit, positive risk strategy
    3. Accept, negative risk strategy
    4. Share, positive risk strategy
  46. 46. In what stage of team development do team members begin to confront each other and vie for position and control?

    1. Adjourning
    2. Norming
    3. Forming
    4. Storming
    5. Performing
  47. 47. A project stakeholder has which of the following responsibilities?

    1. Documentation and administrative support, estimation of task duration, solicit task status from resources, expertise
    2. Documentation and administrative support, provides input and requirements, project steering, expertise
    3. Vested interest, provides input and requirements, project steering, expertise
    4. Vested interest, provides input and requirements, cross-functional coordination, expertise
  48. 48. What aspect of project management is shared with Agile and a traditional waterfall approach?

    1. Iterative approach
    2. Adaptive to new/changing requirements
    3. Sprint planning
    4. Self-organized and self-directed teams
  49. 49. What type of dependency is the obtaining of sign-off on the design of a product?

    1. Mandatory
    2. Discretionary
    3. External
    4. This is not a dependency
  50. 50. At the beginning of a movie project at a production facility, what document would an employee likely be asked to sign?

    1. Cease and desist letter
    2. Service-level agreement
    3. Nondisclosure agreement
    4. Request for proposal
  51. 51. What is the best tool for sharing information across an entire organization but shielding that information from those outside the organization?

    1. Collaboration tools
    2. Intranet sites
    3. Wiki pages
    4. Internet sites
  52. 52. What is the entity that reviews change requests, evaluates impacts, and ultimately approves, denies, or defers such requests?

    1. CAB
    2. MOU
    3. NDA
    4. CCB
  53. 53. A project coordinating the event for a product launch suffered a setback when a plumbing problem flooded the convention hall. Five thousand people are expected to be in attendance at the event, which is scheduled to start in four hours. What factor would influence the communication method?

    1. Relationship building
    2. Criticality factors
    3. Language barriers
    4. Time zones
  54. 54. Measuring the spending to date, determining the burn rate, and accounting for purchases is known as which one of the following?

    1. Expenditure tracking
    2. Expenditure reporting
    3. Estimate to Complete (ETC)
    4. Cost accounting
  55. 55. Which parts of a SWOT analysis are focused on issues external to the organization?

    1. Strengths and weaknesses
    2. Opportunities and weaknesses
    3. Strengths and threats
    4. Opportunities and threats
  56. 56. A large, well-established organization that has been in business for many decades would likely have which organizational structure?

    1. Weak-matrix
    2. Strong-matrix
    3. Functional
    4. Projectized
  57. 57. Which conflict resolution technique produces win-lose results for the parties?

    1. Forcing
    2. Attacking
    3. Avoiding
    4. Confronting
  58. 58. There is a question about a project decision made earlier in a project. Where should the project manager look to help recall the decision and the circumstances that were discussed?

    1. Meeting minutes
    2. Project charter
    3. Action items list
    4. Meeting agenda
  59. 59. The architectural design team has completed the blueprints for a new building and communicates this to the project manager. What type of communication trigger is this?

    1. Incident response
    2. Resource changes
    3. Task completion
    4. Task initiation
  60. 60. The activity that involves determining the usefulness of data gathered to evaluate risk is called which one of the following?

    1. Impact and probability matrix
    2. Risk urgency assessment
    3. Risk data quality assessment
    4. Risk categorization
  61. 61. Which project role is responsible for arranging resources between multiple projects?

    1. Project management office
    2. Project scheduler
    3. Project manager
    4. Project coordinator
  62. 62. In which document would a project manager refer in order to review the high-level scope, high-level risks, assumptions, and constraints, and to find out who the key stakeholders are?

    1. Project charter
    2. Scope statement
    3. Project management plan
    4. Meeting agenda
  63. 63. The project manager just completed a meeting with the steering committee and announces to the team that the project can move forward to the next phase. Which of the following initiated the communication?

    1. Milestones
    2. Business continuity response
    3. Resource changes
    4. Gate reviews
  64. 64. In which project phase would the brainstorming, evaluation, and impact of risk be assessed?

    1. Execution
    2. Closing
    3. Monitor and Control
    4. Initiation
    5. Planning
  65. 65. Which type of document would be given to a committee during a gate check?

    1. Pareto chart
    2. Communications plan
    3. Status report
    4. Change control plan
  66. 66. Which document will ensure the capture of all needed change request information so that it can receive proper consideration?

    1. SIPOC-R
    2. Project charter
    3. Template
    4. Meeting minutes
  67. 67. Interpersonal conflicts are starting to develop on a project. What is the best communication method to use when confronting the problem?

    1. Instant messaging
    2. Face-to-face meetings
    3. Email
    4. Videoconferencing
  68. 68. What are the two forms of acceptance when considering risk response strategies?

    1. Active
    2. Unintentional
    3. Deliberate
    4. Passive
  69. 69. Who is responsible for high-level risk identification?

    1. Project team
    2. Project champion
    3. Project manager
    4. Key stakeholders
  70. 70. The types of organizational structures include which of the following? (Choose three.)

    1. Functional
    2. Agile
    3. Co-location
    4. Projectized
    5. Matrix
  71. 71. The Closing phase includes all of the following, EXCEPT

    1. Monitoring the risks and issues log
    2. Release of project members
    3. Archiving of project documents
    4. Review of lessons learned
  72. 72. What are the three types of estimates used in three-point estimates?

    1. Fastest-Schedule, Least Resources, Most Desirable
    2. Fastest-Schedule, Optimistic, Most Desirable
    3. Most Likely, Least Resources, Fastest Schedule
    4. Most Likely, Optimistic, and Pessimistic
  73. 73. An animated movie project requires the following ordered steps: story idea, script, storyboard, voice talent, models, and sets construction, to name just a few. Storyboard has what relationship to script?

    1. It is a predecessor task.
    2. It is a discretionary task.
    3. It is a successor task.
    4. It is a mandatory task.
  74. 74. After a change in leadership, the new project manager wants to get a sense of the structure and reporting relationships of the project. Which document would give the manager this information?

    1. Lessons learned
    2. Project chart
    3. Meeting minutes
    4. Organizational chart
  75. 75. Which of the following are used to conduct virtual meetings? (Choose two.)

    1. Voice conferencing
    2. Face-to-face
    3. Videoconferencing
    4. Impromptu visits
  76. 76. What is the activity that determines how soon potential risks might occur and determines responses for those risks?

    1. Risk categorization
    2. Risk urgency assessment
    3. Impact and probability matrix
    4. Risk data quality assessment
  77. 77. A project manager has been asked to report on all expenditures to date on the project. What has the project manager been asked to provide?

    1. Expenditures and receipts
    2. Balanced scorecard
    3. Actual cost
    4. Cost variance
  78. 78. What factors should be considered when scheduling a video or telephone conference?

    1. Determining whether team members are introverted or extroverted
    2. Recognizing the different time zones and schedules being used
    3. Ensuring writing materials are available in the room
    4. Ensuring that the meeting room has sufficient seating
  79. 79. All of the following are cost-estimating techniques, EXCEPT

    1. SIPOC-R
    2. Bottom-up estimating
    3. Parametric estimating
    4. Analogous estimating
  80. 80. The work breakdown structure is created during which project phase?

    1. Monitor and Control
    2. Closing
    3. Execution
    4. Initiation
    5. Planning
  81. 81. In what organizational structure does a project manager have limited authority over people’s time and what they are assigned?

    1. Strong-matrix
    2. Weak-matrix
    3. Functional
    4. Projectized
  82. 82. A scope management plan contains which of the following elements? (Choose three.)

    1. Process for creating, maintaining, and approving the WBS
    2. Process for creating the budget
    3. Definition of how the deliverables will be verified
    4. Process for creating the schedule
    5. Process for creating the scope statement
  83. 83. Crashing is a project management technique involving which one of the following?

    1. Moving later deliverables to earlier phases to appease stakeholders
    2. Looking at cost and schedule trade-offs, such as adding more resources
    3. Removing critical path activities that are unnecessary
    4. Performing two tasks in parallel that were previously scheduled to start sequentially
  84. 84. The communication plan calls for weekly status updates to be emailed, monthly status meetings, and semiannual printed newsletters. This plan is laying out which one of the following?

    1. Criticality factors
    2. Level of report detail
    3. Tailor communication style
    4. Types of communication
  85. 85. Total expenditures for completed project work within a specific timeframe is known as which one of the following?

    1. Earned value
    2. Planned value
    3. Cost variance
    4. Actual cost
  86. 86. A major car company just completed the launch of a new vehicle. They have discovered a major safety flaw in the new product, and they need to communicate with the general public regarding a product recall. The following methods would be appropriate methods to use. (Choose two.)

    1. Text messaging
    2. Social media
    3. Instant message
    4. Distribution of printed media
    5. Fax
  87. 87. In what project phase is the influence of stakeholders the least effective?

    1. Execution
    2. Monitor and Control
    3. Initiation
    4. Planning
  88. 88. A construction company is in the middle of a project to build a bridge. The earned value for the project is $9,500, and the actual cost for the project is $7,000. Select the correct cost variance for the project and its meaning:

    1. $2,500 and the project is under budget
    2. $–2,500 and the project is over budget
    3. $2,500 and the project is over budget
    4. $–2,500 and the project is over budget
  89. 89. What is the indication of how fast a project is spending its budgeted money?

    1. Planned value
    2. Burn rate
    3. Cost variance
    4. Expenditure tracking
  90. 90. All of the following are phases of a project, EXCEPT

    1. Planning
    2. Closing
    3. Development
    4. Execution