CHAPTER 3

Project Planning

Project planning is the second of the four stages in the project lifecycle model (as highlighted in Table 3-1). This is when detailed planning of the project is completed. During this stage of the project lifecycle, the scope, activities, resources, communications, and budget are planned. Large, complex, unfamiliar projects will require more in-depth planning than small, simple, and familiar projects. Depending on the size of the core team, different subteams may plan details and then the core team will integrate all the individual sections to create a complete project plan.

TABLE 3-1 Project Leader Responsibilities: Planning

Regardless of the size and complexities of the project, all projects share common project leadership tasks during project planning. These include:

•  Understand and respond to the customer

•  Oversee detailed plan development

•  Integrate the overall project plan

•  Select remainder of project participants

•  Develop communications plan

•  Motivate all participants

•  Secure stakeholder approval.

UNDERSTAND AND RESPOND TO THE CUSTOMER

As the CSM project manager, Uma felt that some of the team members were concerned that they did not know all the requirements of the project. Since Uma had not yet initiated conversation with her counterpart at Buslog Technologies, she asked Bob, as the CSM project sponsor, to schedule a meeting of the project core teams at Buslog and CSM. Bob arranged for a conference call with Terry Andrews, project sponsor, Cecil Jones, project manager, and the other key people from Buslog.

Bob facilitated the call and introduced everyone. He conveyed to Buslog that CSM is committed to working with them to make the project successful. He also mentioned that the interface between the two companies would start in a couple of months, after CSM completed its project plan. Bob mentioned that the CSM project team would like to work with Buslog to create the project plan for the B2B implementation. Terry concurred. Bob explained that the purpose of this meeting was to understand the customer’s high-level needs. Various Buslog people discussed their expectations. After the call the CSM core team felt that they generally understood the needs of the people within the customer organization.

Uma facilitated the meeting, using the supplier-input-process-output-customer (SIPOC) model to identify customer needs. She explained that the SIPOC is a tool that can be used to improve the project process by clearly identifying relationships among suppliers, inputs, processes, outputs, and customers. She said that they would work backwards from the customer’s needs. They identified the needs of Buslog and then the internal stakeholders for the order processing system. The B2B project SIPOC model is shown in Figure 3-1.

The team thought that this would provide them the input they needed for the scope definition. Since an error in a single transaction could cost millions of dollars, there could be no compromise in the quality of the B2B system.

FIGURE 3-1 B2B Project Supplier-Input-Process-Output-Customers (SIPOC) Model

Bob began by setting the priorities for the team. He told the group that quality could not be traded off. Cost could be traded off only if the steering committee approved.

Uma had another conversation with her counterpart Cecil to get more specific inputs on project priorities. Cecil mentioned that the go-live date is a hard one and Buslog can’t compromise on that. From his perspective, the only thing they can trade off is the scope of the project.

Project Leadership Considerations

Documentation is needed for all meetings, both internal and external, and everyone needs a chance to respond to and correct errors or misunderstandings.

There are several aspects to understanding and responding to the customer, and this project team did a good job on most of them. First, the team needs to understand who the various customer groups are. The SIPOC model is very useful for this task. Working backward from the identification of all the customer groups, the core team can discover much useful planning information regarding customer needs. The SIPOC model should also serve as a starting point in the prioritization process.

Typically, a project is planned assuming that if everything goes right, the project team can successfully deliver all four customer priorities: the full project scope, on the agreed-upon schedule, at the agreed-upon cost, with the agreed-upon quality. However, on most projects unexpected things happen that either allow a project team to improve upon one or more of these four customer priorities or prevent the full attainment of one or more of these priorities. The project leaders should have frank discussions with the key customer groups (often this means both the external paying customer and one or more key internal stakeholders within the parent organization). The focus of these discussions needs to be which of the customer priorities take precedence.

For example, if things are going very well, should the project team try to lower cost, speed up the schedule, add more features to the project scope, or improve the quality of the project deliverables? The same understanding must be developed if things go poorly: Which of the customer priorities can be compromised and by how much? Many customers will tell a project leader that all four must be achieved. The wise project leader should respond that if all goes according to plan, that will happen, but as a responsible leader, she wants to make the same kind of decisions the customer himself would make if he were on the jobsite every day.

One area in which the project team could have done a better job is in documenting the conversations with the customer. In Chapter 2, simple minutes forms were introduced for use in project meetings. The intent of these minutes is to capture important information shared, decisions made, upcoming issues identified, commitments agreed to, and a meeting evaluation. The same type of information is appropriate to capture from other kinds of customer contacts such as conversations. After a conversation with a customer, a simple email to the customer confirming this information can be sent and a copy kept as project documentation.

Whenever possible, the first meeting with the project customers should be in person. Much of communication is reading and interpreting body language, and this is not possible by phone. A videoconference might be a useful compromise. Also, it is often wise to have a first meeting with the senior players: the project sponsors and managers from both companies. It may well make sense later on for members of the project teams to talk with each other directly, but a phone conversation with seven plus people is not an ideal way to start.

Project Leadership Lesson: Planning—Project Priorities

A Project Leader Needs to:

Accept that the customer has multiple, often conflicting wants

Have the courage to prioritize the customer’s true needs

Exercise the wisdom to understand the difference between wants and needs.

OVERSEE DETAILED PLAN DEVELOPMENT

Uma reiterated to the team in a memo that they would use a lessons-learned process at every stage of the project. Uma wanted the team to brainstorm lessons learned from the planning stage of similar projects.

Sanjay realized that among the first tasks was choosing the hardware and software. Gary, as the CIO, needed to make these decisions. He also needed to select and hire consultants. However, this could not be accomplished until the schedule was developed.

Uma wanted the team to develop a risk plan detailing all the risks that were discussed in the initiation stage. This risk plan would include an assessment of the probability of each risk event happening, the consequences if it did happen, and contingency plans where needed. Some of the team members argued that they had already discussed the risk at the initiation stage and that was enough information for them to move forward with preparation of the work breakdown structure (WBS). She reminded the team that a WBS is a detailed listing of all the project work. They could include a contingency plan later in their schedule.

Uma sensed that the team was getting restless and wanted to get on with the project. She made it clear that she understood that some of the team members felt that they were not using time wisely, but she felt that time spent on risk planning was crucial. A mistake at this point could create a major problem later.

When the project charter was developed, the team had to develop time estimates for the major phases of the project. Now, as the team got ready to create the WBS, they decided the first step was to work on a major milestone plan and identify the deliverables at every milestone that would be shared with stakeholders for their approval. The milestone plan is shown in Table 3-2.

Having completed the major milestones, the core team began constructing the WBS. As they developed the WBS, they assigned resource requirements to every item. Estimated hours of resource requirements are summarized in Table 3-3.

Chris wanted more time allocated for design and Paul wanted more time allocated for quality assurance (QA). Uma then asked each of the team members to have a meeting with their subject matter experts (SMEs) separately to complete the WBS detail for their subteam’s work. She also wanted them to show all dependencies and to input this into a schedule using Microsoft® Project. Then Uma took their individual schedules, merged all of them into a schedule for the entire project, and presented it to the whole team, including the SMEs. After much discussion and various requests, a schedule emerged that everyone felt was reasonable.

TABLE 3-2 B2B Project Milestone Plan

Milestone Delivery week Deliverable
Project planning and initiation Week 2 Project charter, project scope definition, work breakdown structure, project budget plan, communications plan
Requirements analysis, system design specification and architecture Week 5 Systems requirements document, use case document, functional specifications, technical architecture design document
Technical design and network design Week 7 Technical design specification document, network design document
Development and configuration Week 15 Order processing system ready for integration testing, documentation of configuration, customized user manuals, training materials
System acceptance testing Week 18 Test plans used for testing, results of regression testing
Training Week 19 Training manuals
Transition and transition support Week 21 Transition document detailing roles and responsibilities in the day-to-day maintenance of the system

TABLE 3-3 B2B Project Resource Requirements

WBS category Resource Hours
Requirements analysis Consultant 80
System design and architecture Consultant 60
Technical and network design Consultant 80
Internal 160
Development 5 full-time internal 2000
2 consultants

Bob and Uma then used the schedule as input for their detailed budget. They broke down costs into the major components of internal resources, subcontractors, consultants, training, travel and administration, and cost of the project office. They assigned costs to major WBS components and decided to track actual costs against their estimates. Then Bob and Uma shared their results with the team.

Project Leadership Considerations

Uma acted responsibly as a project leader in overseeing the detailed plan development. She kept the customer’s priorities in mind and worked in a logical order for the most part. Some project leaders would prefer to work through more of the WBS before finalizing the risk plan. Uma worked through the higher levels of the WBS with her core team, then had each core team member develop the details of their respective areas with their SMEs, and finally integrated the entire plan with anyone on the complete team making recommendations where there were conflicts. By using this method, Uma achieved efficiency in the work process and a more empowered workforce.

Once the WBS and risk plans were complete it was time to determine who should perform each identified task, what the durations and predecessors should be for each task, and how all this information should be combined into a workable schedule. Project leaders need to facilitate this activity, but do not have to perform it all personally. Technical leads, schedulers, and others should be able to perform much of this work. Nonetheless, project leaders need to understand what questions to ask, when to offer help, when to take over, and when to back off.

A final component of detailed project planning is the project budget. Top leadership in an organization sees a budget as a tool to assist in prioritizing organizational goals. Through the budget, top leaders allocate resources to selected projects, with more resources going to higher priority projects, and no (or few) resources going to low priority projects. Thus, as projects serve as means of accomplishing the goals of an organization, budgeting serves as the means of prioritizing those goals.

Project leaders can develop their detailed budget only if they have an understanding of the project WBS and schedule. Once these are understood, it is possible to determine the cost. If the expected cost is significantly different from the spending authority granted in the project charter, a serious discussion needs to take place. This could involve using a different approach, changing the project’s scope or schedule, or canceling the project.

It was surprising and problematical that the detailed budget was shared with the whole team. While ideally teams share all information, it is debatable whether or not detailed budgets of other people’s areas should be shared with the project team.

As project leaders oversee the development of the detailed project plans rather than get caught up in the details themselves, they need to:

•  Understand who gives good advice on the project plan and who gives poor advice. Some project team members will have a much better understanding of how to plan than others.

•  Ensure that risks continue to be uncovered and addressed. Hiding risks may be tempting to secure project approval, but gaining acceptance of a project with buried risks may be a Phyrric victory.

•  Encourage the project team to pursue innovative approaches where appropriate and to reuse or adapt approaches developed previously as appropriate.

•  Understand that project team members both remember best and commit to those things that they “discover” on their own. Orchestrate the plan development process so that team members can make “discoveries.”

•  Realize that by active listening and following, a wise project leader both gains influence with her team and encourages the team to self-manage.

Before this step was complete, it was very important that Uma ensure that everyone fully understood and was comfortable with the details of their own budget so that they could take “ownership” of their part of this project as well as the entire project.

Project Leadership Lesson: Planning—Project Details

A Project Leader Needs to:

Accept that the project team and SMEs will develop large parts of the project plan

Have the courage to challenge planning details

Exercise the wisdom to know when to trust and when to question.

INTEGRATE PROJECT PLANS

Uma then developed the integrated project plan to submit to the steering team and other stakeholders. The integrated project plan included the WBS, schedule, risk plan, and cost estimates. Uma wanted to create management plans for scope, time, and cost. Bob told Uma that they could work on these factors once the project was kicked off. He wanted to get the project started as there was pressure from Mark to get it going.

Project Leadership Considerations

Uma was facing a common project leadership dilemma. She was being pressured by powerful stakeholders to move forward, yet her core team members had stated they were not ready yet. This was a “leadership moment.” She needed to recall the project priorities. In this case the non-negotiables were quality and time. Since she was within the allocated time, it became her responsibility to consider pushing back because moving too quickly could create an unacceptable risk.

While the key issue in developing integrated project plans is to ensure that the various components have consistency, sometimes there is time pressure to move along and iron out details later. This often creates problems that could have been easily handled with just a little more time in planning, but if discovered during execution, are much more disruptive to the project. The issue that faced the core team was whether they had enough information to complete the planning process. While very few teams feel they have all the information they would like, one component of project leadership is to know when the team has enough information to proceed.

Project leaders should remember a few key principles of project leadership planning at this time:

•  Understand a project at different levels—as part of a larger system, as a system itself, and as a collection of parts. This understanding requires that the various parts of a project “fit” together in the integrated plan and reduces unpleasant surprises during project execution.

•  Remember that both numbers and ideas are important in an integrated project plan. Many project participants primarily want to see or use either numbers or issues, but not both. An effective project leader needs to be comfortable with both.

•  Analyze complex tradeoffs and understand their potential consequences. This can be helpful when making integration decisions.

•  Understand cause and effect relationships so issues can be identified that, when improved, will also improve other areas. This also helps in making integration decisions.

•  Know when to make decisions and when to allow decision-making by the project team or by certain stakeholders. Enlightened project leaders try to push the decision-making process to as low an organizational level as practical. This helps all project participants—the project team and other stakeholders—develop a sense of shared risk and reward. This ownership of decisions often is the extra intangible that helps project participants achieve a little more when faced with challenges during project execution.

Project Leadership Lesson: Planning—Project Integration

A Project Leader Needs to:

Accept that others can sometimes make better decisions than I can

Have the courage to make the decisions I should make

Exercise the wisdom to know which are which.

SELECT REMAINDER OF PROJECT PARTICIPANTS

Bob and Uma met with the core team members to discuss the remainder of the team. Uma had already sent an e-mail to the core team members asking them to consider people they would need for the rest of the project. Bob had identified the key project stakeholders who would need to play an active role if the project was to be successful. Based on the project plan, the team came up with subteams (listed in Table 3-4).

Sanjay said that he wanted to schedule the five consultants as soon as the project schedule was approved; he didn’t want to lose good candidates because they were not scheduled soon enough. Uma wanted all the core team members to give her their subteam members’ names and responsibilities. She wanted to prepare a responsibility matrix.

TABLE 3-4 B2B Project Subteam Responsibilities

Subteam and Leader No. of Subteam Members Responsibilities
Networking team—Scott 1 network administrator
1 systems administrator
Take care of network, security, firewall issues, systems, user management
Technical team—Sanjay 3 developers
2 contractors
3 consultants as needed at various stages
Programming and implementation
QA team—Paul 1 quality assurance engineer
2 testers at a later stage
Develop procedures for quality testing and prepare test plans
Business analysis team—Chris 4 business analysts Work with different functional people to come up with requirements

Project Leadership Considerations

Project leaders should realize that selecting appropriate people for subteams has a great deal to do with project success. The comments on selecting key project participants made in Chapter 2 also apply here. However, at this level, technical competence may be more important. Many project managers and sponsors try to act in a collaborative manner with the members of the core project team and others in the organization as the remainder of the project participants are selected, but some do not. The subteam leader usually is in the best position to identify people who have the expertise needed. However, the sponsor or project manager may need to use their political acumen to actually get the person they want assigned to the project. Project leaders want to ensure that they are not simply “stuck” with workers that functional managers want to unload or with whoever happens to be available regardless of whether they are the best people for the job.

By totally delegating the responsibility of choosing subteam members to her core team, Uma abdicated responsibility. She could have empowered her core team by working collaboratively with them. The best long-term method of ensuring the ability to recruit eager and competent people is for a project leader to take care of both the projects and the people they are responsible for; such a project leader’s reputation will spread. Wise project leaders want to be able to say convincingly, “If you work with me, you will be successful both on this project and after it. I can say that because that is what has happened to the people and the projects I have been associated with.” In effect, the project leader is recruiting based upon both past success and future potential. Everyone wants to work with a winner. If a project leader and a project both appear to be winners, willing and competent participants will be much easier to find.

One of the key aspects of the detailed project plan is assigning responsibility. If this is done clearly, it helps with identifying and recruiting the additional participants that are needed. The more specifically a project leader can delineate what a participant will be doing, when, under what conditions, etc., the easier it will be to find the right people for the project. Team needs and diversity of input also must be considered.

Project Leadership Lesson: Planning—Human Resources

A Project Leader Needs to:

Accept that we may not be able to have assigned to our project the particular subject matter experts we really want

Have the courage to understand the full range of the company’s personnel needs

Exercise the wisdom to ensure that both project and other organizational needs are met.

DEVELOP COMMUNICATIONS PLAN

Uma decided to create the communications plan based on her prior experiences and then review it with the team. She decided that she would create a separate area in the company’s intranet that would be accessible to the project team, steering committee, and stakeholders. The meeting minutes project folder would be available at every team meeting. Uma’s communication plan is shown in Table 3-5.

TABLE 3-5 B2B Project Communications Plan

Uma then invited all the team members to discuss the communication plan. Jeff asked Uma, “What about the meeting minutes? Do we copy everybody on the team?” Uma answered that subteam meeting minutes need to be sent to the core team members. The team leads could then decide if they need to copy the meeting minutes to any other stakeholders. The core team agreed to keep the communication channels open but not overloaded. Uma would also provide a weekly update to Bob. Steering team approval will be required at every milestone of the project. Uma and Bob shared the thought that it is their task to encourage the steering committee to periodically update the user community on the project’s status and what to expect. Uma would be the primary communicator to Buslog.

Project Leadership Considerations

While much of what Uma did in developing the communications plan was appropriate, she missed a fundamental concept of good communication. The concept behind effective project communications is simple, even if the implementation is almost always a challenge. The concept is to first understand who needs to know what, in what format, at what time, under what circumstances. The rest of the concept is to construct a plan to give the various stakeholders the information they need in a timely fashion. Too much communication can be a problem, just as too little usually is. To understand what various stakeholders need to know, ask them! Uma did not ask anyone what they needed.

Project leaders should keep the following points in mind when developing a communications plan:

•  Project leaders need to continually articulate their vision to all stakeholder groups.

•  Project leaders should ensure that team members have regular, complete, and effective contact with their counterparts in the customer’s organization. Engineers should talk with engineers, accountants with accountants, and programmers with programmers, etc. There may be a need to filter certain information, but that should not come at the expense of limiting important contacts.

•  Project leaders need to develop well-grounded explanations for all questions that may arise. When possible, these should be developed before the need arises.

•  The project communications plan should include clear guidelines for team meetings.

•  The project communications plan should address the professional development of individuals as well as of the project team.

•  The project communications plan should be an efficient means of organizing data and reporting results.

•  Different people have different communication needs at different times. Keep asking if the current flow of information is adequate.

Project Leadership Lesson: Planning—Human Relations

A Project Leader Needs to:

Accept the fact that different project stakeholder have very diverse information desires

Have the courage to uncover and meet their true information needs

Exercise the wisdom to understand the difference between these desires and needs.

MOTIVATE ALL PARTICIPANTS

Bob realized the team had been working hard to develop the project plan and get the project rolling. He decided it was time to have some fun. He decided that they all would go out for dinner to a nice restaurant and then go out and play some pool. He asked his administrative assistant and Uma to plan some games and also invited the steering team to the dinner. Since Mark could not make it, he asked Gary to say a few words of appreciation to the team and emphasize what the project means to the company. Uma and Bob agreed that they will have some fun activities during every stage of the project (e.g., cookouts, different culture days, unannounced pizza parties). At every milestone the team members will be shown appreciation for the work done.

At dinner, Gary addressed the team by congratulating them on their success and said that he and every member of the steering team appreciated their contribution. He also made them feel that they had accomplished an important milestone and thanked them for that.

Project Leadership Considerations

Having a variety of “fun” activities is often a terrific idea; however, it is usually wise to let the group plan their own activities. Different people have very different ideas of “fun.”

Throughout the project, project leaders have ongoing responsibilities to develop commitment in all stakeholders; the first part of this commitment is the unofficial desire or motivation on the part of everyone to do what is necessary. The second part is to publicly and officially commit. Motivating all participants is the unofficial commitment work that should take place during project planning in anticipation of everyone formally committing at the end of the planning stage.

Bob, Gary, and Uma focused their informal commitment efforts on the morale of the project team. While that is important, it is only one component. Each project leader should be articulating the benefits and excitement of the project and conveying the “what’s in it for me” message. To motivate people it is wise to help them understand that the work they are doing is important, it is likely to be successful, and they will be rewarded fairly for their efforts. In this case Gary did articulate the vision for why the project is important. He could have told the team why he thought the current project approach would be successful.

We know the project team is celebrating, but what about all of the other project stakeholders? Have all the customer groups—internal and external—been involved in celebrating thus far? Do they share the project leaders’ enthusiasm for the importance of the project?

Have all other stakeholders who could interfere with the project been communicated with? In some cases it may be difficult to excite them about the project. (Think of unwilling neighbors of a major construction project.) Have the project leaders at least dampened the negative feelings of those people who could be disruptive to the project if they were sufficiently antagonized?

If the project leaders have been communicating effectively and unofficially all along with all project stakeholders and key influencers, and if trust, integrity, and reciprocity have been established with them, then securing their formal approval should not be in doubt.

Project Leadership Lesson: Planning—Project Promotion

A Project Leader Needs to:

Accept the need to motivate all project participants

Have the courage to continually articulate the project vision and reasons it will succeed (especially to the reluctant participants)

Exercise the wisdom to understand how to motivate each participant.

SECURE STAKEHOLDER APPROVAL

Uma scheduled an internal project kickoff meeting, inviting all internal stakeholders, the steering team, the project core team, and all SMEs. The agenda for the meeting was to go through the detailed project plans, including the WBS, risks, schedule, and responsibilities with all stakeholders. Questions and answers would be a key part of this kick-off meeting.

A stakeholder from the accounting department was very upset with the partial implementation of the ERP system. Her assumption was that the accounting department may have to do dual data entry into both the legacy system and the new system for payments and invoices. She also said, “Every time IT says that they will automate something, then we have to learn a totally new system. By the time you get comfortable with it, it’s time for them to implement something new again. When will they settle on one system?” Uma then explained, “This is a very strategic project for the company. The technical team will minimize the inconveniences by automating data transfer between the legacy system and the new system. The old legacy system has been customized heavily and documentation is not up to date; hence the users face problems if a new functionality is added. The new system is state-of-the art technology and it has the new functionalities we need, as our business has grown in the past couple of years. There will be user-friendly manuals to ease the implementation process.” Bob confirmed that fact and pointed to the project activities that address those issues.

At the end of the internal project kick-off meeting, all internal stakeholders (including the steering team) approved the project plan. Then Bob, Uma, and the core team met with their customer counterparts in an external project kick-off meeting.

At the end of this meeting the team had also secured approval from Buslog, the external customer.

Project Leadership Considerations

Project planning often culminates in a formal project kick-off meeting with the intent of answering all questions and securing approval from all stakeholders to proceed. If all the other project leaders’ planning tasks have been carried out well, the chances of securing approval are quite high. It is not uncommon for the project core team to first meet with all internal stakeholders to ensure that each of them fully understands and commits to the project plan. Then it is time to meet with the customer for concurrence.

In an ideal world the concerns of various stakeholders have been considered and there are no “surprises” at the kick-off meeting. In Uma’s interaction with the accounting representative, she needed to be careful not to promise more than the project can deliver.

Project leaders should demonstrate that they understand the details in each area, but that they are concerned primarily with the overall project instead of any one portion. The project leaders often must convince reluctant stakeholders that their particular area may not get exactly what they prefer, but the project as a whole will be well served. Good communications planning and effective work on motivating these reluctant stakeholders in advance should help avoid disruption at the kick-off meeting.

Project Leadership Lesson: Planning—Commitment

A Project Leader Needs to:

Accept the fact that many diverse stakeholders must approve the project plan

Have the courage to secure acceptance by each

Exercise the wisdom to promise only what the team can deliver.

Once everyone has publicly and personally committed to the detailed project plan, the team is ready to begin project execution! Actually, on many projects, tasks and resources that require long lead times were probably preapproved in anticipation of the project plan being accepted. Time is an important factor to project leaders and they cannot afford to squander it.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset