CHAPTER 2

Project Initiating

Project leaders have responsibilities related to setting and enforcing priorities, ensuring that project details are planned and executed, and ensuring integration both within and outside the project. They are also responsible for the formal human resources and personal human relations aspects of acquiring, overseeing, and rewarding project personnel. Project leaders also need to promote the project in order to secure and maintain the commitments of key project stakeholders at each stage in the project lifecycle. These responsibilities are summarized in Table 2-1, with the initiating stage highlighted.

Chapters 25 cover the four project lifecycle stages. Each will be divided into the seven major categories of project leader responsibilities. Each section will start by demonstrating project leaders’ challenges using the fictitious example of the company introduced in the case study, California Semiconductor Manufacturers (CSM). The project leadership considerations will be presented to help project leaders use the CSM project to assist them in resolving real-life issues on their own projects.

TABLE 2-1 Project Leader Responsibilities: Initiating

Each section will be summarized with a project leadership lesson displayed inside a box. The lesson will be titled with the project stage column and the category of leadership task row that correspond to the specific cell shown in Table 2-1. For example, the first lesson applies to aligning the project with the parent organization. This deals with the initiating stage and the project priorities row, so it is labeled Initiating—Project Priorities.

Project leaders usually do not finish one responsibility before starting another; there is often considerable overlap and interaction between and among various responsibilities. For simplicity we will present project leaders’ responsibilities in as close to a logical order as possible. First we will concentrate on the task responsibilities: Leaders need to have an understanding of the project work before they know what type of personnel, how many, and when each will be needed. Each project stage will culminate in a commitment of some kind.

Our coverage of the first project stage, initiating, starts with the project priority task of aligning the project with the parent organization, the project detail task of performing a risk assessment, and the project integration task of justifying and selecting the project. Next is the human resources task of selecting key project participants and the human relations task of determining project team operating methods. Finally the project leaders must complete the project promotion task of securing top management support and the commitment task of securing the public and personal commitment of each key project participant, often in the form of a signed charter.

If a project leader successfully shepherds a project through these seven project initiation tasks, the project will be ready to proceed into the planning stage (covered in Chapter 3). If the project leaders cannot successfully complete all project initiation tasks, maybe it is a poorly conceived project that does not deserve to be planned and executed. One reason for the project initiation stage is to quickly (and inexpensively) weed out inferior projects, so the failure of some projects to proceed further should be expected.

ALIGN THE PROJECT WITH THE PARENT ORGANIZATION

Using our B2B case study as our working example, Terry (VP of worldwide sales and operations of Buslog Technologies) sent Bob (VP of sales and operations at CSM) an e-mail stating that they would like to implement an automated business-to-business processing system using CSM’s ordering systems. Since Buslog is one of CSM’s most important customers, this e-mail caught Bob’s attention. Terry also mentioned that they would provide a software license for CSM to use and would be willing to work with CSM’s technical and sales organization to implement this project. Terry invited Bob and his company’s executive team to attend a presentation by Buslog Technologies to its primary vendors to ask for their participation in reducing supply chain inefficiencies. Gary (CIO) and Bob attended the presentation.

After the presentation, Bob and Gary agreed that they would like to participate in the Phase I implementation and that CSM should be committed to this project. Mark (CSM’s CEO) scheduled an executive team meeting to discuss the project. Mark asked Gary and Bob to work together to come up with a short presentation of what the project could mean to CSM and why they should take it on. In their presentation Gary and Bob pointed out that this B2B project would be the beginning of a strategic customer integration initiative. This customer integration initiative would eventually include implementing an enterprise resource planning (ERP) system that could, in turn, yield many additional benefits to the company.

In summary, Bob and Gary proposed that, if the executive team selected this project, the project mission would be to develop automated B2B processing between the CSM and Buslog ordering systems.

Project Leadership Considerations

A project leader’s first task is to ensure that a project to be undertaken aligns with the parent organization. This consists of several activities, the first of which is to assess the culture, teamwork, risk tolerance, communications, decision-making, and trust levels in the overall organization to determine how capable the overall organization is in supporting project leadership. It is important to understand strengths and weaknesses and to develop ways to improve upon past performance. Apendix A contains a project leadership assessment tool that is designed to assist in analyzing and evaluating project leadership at the organizational level.

Effective project leadership requires proper attitudes, skills, and competencies. It is a willingness to take personal risk—to show genuine concern for the company, client, project, and everyone involved. The good news is that most of the skills and competencies required to be a successful project leader can be learned and that coaching and mentoring are instrumental in a leader’s development.

The individual, team, and organizational aspects of leadership are interdependent. Senior management support establishes a foundation for leadership success, but it is the application of leadership characteristics at the individual and team levels that makes it truly effective.

The assessment questionnaire provides a self-scored assessment of the state of project leadership at the organizational level. This is not designed to answer all the questions that need to be asked for effective project leadership, but rather to provide an indicator for further action.

Once it is determined that the organization is ready to support project leadership, the next step in alignment is to identify potential projects. Ideally, all leaders in an organization are continually searching for potential projects as part of their everyday work.

The third step is to assess each potential project. Some large organizations may have extensive assessment procedures, while some small organizations may have almost none. Regardless of the size of the organization or the complexity of the project, a few key questions should be asked to determine if a potential project might align well with the parent organization’s priorities:

•  What is the project’s vision?

•  What value does the potential project offer the organization?

•  Can the project be understood and articulated at different levels (as part of the larger organization, as a system itself, and as a combination of its parts)?

•  What level of human and other resources will the project potentially require?

•  What is the project’s priority in comparison with other projects?

•  How is work within the project prioritized?

•  How will the parent organization’s culture help or hinder the work of this project and vice versa?

CSM’s top officers acknowledged that several benefits could come from this project and that it was consistent with a company philosophy of partnering with customers. However, the leaders did not spend enough time assessing whether the company had and could use the human and other resources necessary to complete this project, nor did they assess the impact this project would have on CSM’s overall mission, vision, and goals. Many projects when considered in isolation appear to be a good fit; however, wise leaders consider potential projects in comparison with each other when making alignment decisions.

The automated B2B processing project under consideration at CSM appears to be a good fit in that it has the enthusiastic support of one of the company’s major customers and will have many other benefits to CSM. The executive team seems excited and willing to work hard to help the project succeed. Direct benefits to CSM include better shipment notice information and reduced product lead time, both of which will have a positive impact on customer service. Since the project appears to be a good fit, CSM’s project leaders are now ready to proceed into their second responsibility, which is to perform a risk assessment.

Project Leadership Lesson: Initiating—Project Priorities

A Project Leader Needs to:

Accept the strengths and weaknesses of both the parent company’s organization and this potential project

Have the courage to assess how well this project will actually help the parent company achieve its goals

Exercise the wisdom to accept or reject this project accordingly.

PERFORM RISK ANALYSIS

At CSM a special team of assessment experts independently performs risk analysis and makes project selection recommendations. This assessment team met with the executive team to identify project risks and their impact. The list of risks the team identified is shown in Table 2-2.

The steering committee argued that the risk of resources being pulled from the project prematurely is low because this is a high-priority project to which CSM is strongly committed. Nonetheless, the assessment team argued that, in the past, they have seen too many instances when team members were pulled from an “important project”—so they still felt this concern remained a high risk. The two teams reached a consensus that the issue of not pulling resources from the project needs would be mentioned in the charter.

TABLE 2-2 B2B Project Risk Level Assessments

Risks Team-Identified Impact Executives’ Tolerance
Technology constraint—getting software, hardware, partnered license High High
Pulling resources prematurely High Medium
Facility limitation Low Low
Availability of networking Low Low
Organizational constraints—people being pulled away for other projects High Low
Customer constraint—availability of customer to do connectivity, customer shelving the project High High

Project Leadership Considerations

Risk assessment should start with the key project participants who are already assigned identifying the different potential sources of risk. These risks may include:

•  Customer-associated

•  Contract

•  Project requirements

•  Business practice expertise

•  Project management

•  Work estimates

•  Project constraints

•  Complexity and scale of deliverables

•  Contractors.1

It is imperative that potential projects be assessed for risks by both management at a high level and technical experts at a detailed level. There are different schools of thought on the composition of assessment teams. Some argue that it is important to have a totally independent team make this assessment objectively and then play no other role on the project. Others argue that seamless transitions are preferable, and that those who will implement the project should be involved from the start. In an organization that values and trusts its associates and that attempts to maximize communications, we believe that the latter approach make more sense. Simultaneously, the executives involved should determine how much risk they are willing to tolerate for each identified category. Then the assessment team and the executives should together determine whether the risks appear to be acceptable.

Everyone needs to express their views candidly based upon their experience and expertise. In the end all parties must agree on the risk level in each category. Sometimes the project approach may need to be altered to reduce the risk levels in one or more areas to an acceptable level. The project leaders should ask themselves the following questions to determine if they are ready to proceed to their third responsibility, which is to justify and select the project:

•  Can we develop a sense of shared risk with the project team, client, suppliers, and upper management?

•  Have we started having useful discussions in identifying problems and approaches to solving them?

•  Have we prepared for the worst while hoping for the best?

•  Do we have the ability to identify risks soon enough to overcome them?

•  Are we consciously trying to understand who gives us good vs. bad advice?

•  Are we identifying opportunities along with risks?

•  Have we assessed risk using the categories shown above?

It is clear that in the B2B project we are using as an example, both executives and the assessment team met to assess project risks. What is not as clear is whether they were thorough enough to ensure that all potential sources of risk were considered. A wise project leader really explores the details when assessing risks. Many things look fine on the surface, but trouble lies buried beneath. Leaders want to find that trouble early enough to handle it.

Project Leadership Lesson: Initiating—Project Details

A Project Leader Needs to:

Accept necessary project risks

Have the courage to challenge risks that can be mitigated

Exercise the wisdom to understand the difference between these two types of risk.

JUSTIFY AND SELECT THE PROJECT

After considering a variety of options, the team narrowed them to two possible approaches. The first approach was to implement the order processing and shipping module of the ERP system and use the software provided by the customer to automate the process. The other approach was to implement the software provided by the customer to automate the process within its existing legacy system.

The next step was to perform a cost benefit analysis of both options. This is shown in Table 2-3.

The team selected the first option. This option was determined to be the superior solution in that it contained all the benefits of process automation, was relatively quick with the customer-supplied software, and gave the company a foothold into the ERP system, which it would need to start implementing within a year anyway.

Project Leadership Considerations

Project selection is similar whether a company is selecting one project or a portfolio of projects. Project leaders need to be able to articulate the business case for a potential project so that all key stakeholders can understand its value. In this situation, the project aligned so well with CSM’s mission that selection was almost a given. The more interesting decision in this project selection was which approach to take. CSM was appropriate in first considering several potential solutions and then looking hard at the last two when the others did not appear feasible.

TABLE 2-3 Potential Project Cost Benefit Overview

Solution Proposed Cost Components Related to Project Benefits
Implement order processing and shipping module of ERP system and use the software provided by the customer

Resource costs Training costs

(Software and hardware costs already budgeted under IT)

• Better visibility into the supply chain, reduced cycle time, inventory and inventory-related costs, seamless integration with customers, lays foundation for later to extend it to WIP, production schedules etc.

• Interfacing with the new system, which would be implemented over a time frame of one year and is going to integrate all their diverse systems

Implement the software provided by the customer with their legacy system

Resource costs

• Better visibility into the supply chain, reduced cycle time, inventory and inventory-related costs, seamless integration with their customers, lays foundation for later to extend it to WIP, production schedules etc.

This same approach can be used when there are many more potential choices. First a team needs to brainstorm all the potential approaches (which can sometimes be numerous). Each participant should feel free to offer any approach without fear that it will be criticized. This is important since some ideas that first appear impractical may later prove to be worthwhile. Moreover, this sets the tone for free and open discussion on the project.

Once all potential approaches are listed, the team needs to have a method of quickly screening a large number of choices down to a small number that can be analyzed in detail. Sometimes project participants perform this screening by asking questions about which approaches are not feasible. If there are quite a few choices to be considered, a second method worth considering is multi-voting. In multi-voting each participant can vote for whichever approaches he or she prefers. The group then progressively removes first the really impractical approaches and then the practical but not quite ideal approaches. A key to multi-voting is to try not to remove more than half of the potential approaches at one time, which can result in good choices being removed along with impractical ones.

Once there are few enough potential approaches left that it is practical to perform detailed analysis, each alternative should be examined based on relevant dimensions. The dimensions that are often considered include:

•  Strategic and/or commercial value

•  Risk

•  Stability of requirements

•  Competition

•  Opportunities for learning

•  Fit in the portfolio of current projects

•  Expected duration

•  Cost

•  Resource needs

•  Leadership needs

•  Training needs.

Before committing to a project, a company might use four different frames of leadership (political, human resources, traditional management, and symbolic) as lenses through which to view the project. Certainly an ethics check is necessary for all projects. A look at the broad picture or external environment is also necessary: Are there political, economic, or social issues? An internal look at the project’s impact on the development of resources and relationships between and among all stakeholders is also important: How does the project build expertise for associates? What impact will it have on suppliers? Regulators? Other customers? Competitors? It appears that none of these factors is an issue in this case.

Project Leadership Lesson: Initiating—Project Integration

A Project Leader Needs to:

Consider different potential projects or approaches based solely on their merits

Have the courage to accept or reject projects and approaches based on their merits

Exercise the wisdom to make the right choices.

SELECT KEY PROJECT PARTICIPANTS

Mark asked his executive team to select a project sponsor. The team agreed that Gary and Bob are the two strongest candidates. Profiles of each are shown in Table 2-4.

The executive team decided to select Bob as the project sponsor. They also created a steering team of Bob, Carl, Gary, Mark, and Peter.

TABLE 2-4 Profiles of Potential Sponsors

Bob’s Profile Gary’s Profile
Participative leadership style Technology initiator
Aware of organizational politics within the functional organizations Understands supply chain inefficiencies
Results-oriented Believes in ROI of IT projects
Great communicator Likes outdoor sports
Factual and thoroughly works out details Experience in being project sponsor

Bob mentioned to Gary that there were two possible candidates for the job of project manager. The qualifications of both candidates are shown in Table 2-5.

Bob told Gary that he needed someone who was confident, enthusiastic, logical, and who finds flaws in advance. After meeting with both candidates, Bob selected Uma as the project manager.

Bob and Uma selected the core team as shown in Table 2-6.

TABLE 2-5 Project Manager Candidate Qualifications

Qualifications Jack Donovan Uma Raman
Job Title Manager of business applications IT project manager
Education Degree in engineering Masters in computer science, MBA, PMP
PM experience 10 years 5 years
Last Project Selected ERP system for CSM Global project in an Internet company
Supervisor’s Comments Task-oriented, micromanages work breakdown structure (WBS), honesty, integrity, technically up-to-date. Strong interpersonal skills, great problem-solving capabilities, aggressive, has fun days in her project

TABLE 2-6 Core Team Members and Roles

Team Member Functional Role
Jeff Gardiner Southeastern regional sales director
Steve Alvarez Procurement manager
Rob Richard Responsible for advanced shipping notices
Rita Elliot Accounts receivable manager
Scott Brown Networking manager
Elizabeth Ramsey Operations manager
Paul Byrant QA manager
Sanjay Krishnan Technical lead
Chris Chin Lead business analyst

Project Leadership Considerations

A large part of the success of any project is determined at this point. In choosing key participants, the first goal is to find people who have adequate knowledge and skills in team-building, planning, communications, and decision-making to be effective project leaders. Appendix B is a self-scoring assessment of an individual’s project leadership potential. The key project leaders selected should in turn find people who will have a synergy among them, that is, who will work creatively together and whose efforts will complement and supplement each other. Key project participants typically include a steering team, project sponsor, project manager, project core team, and subject matter experts.

The steering team needs to include people of vision who see the project in perspective, who care about the project’s success, and who will provide overall guidance and support for the project. In some instances the organization’s existing management team serves this function. An advantage of this approach is that the steering team by definition has legitimate authority (clout). In other instances individuals are specifically selected to serve on the project steering team. An advantage of this approach is that the steering team may have more specific expertise and passion. CSM elected to select the steering team.

The sponsor is usually a member of the steering team and is the primary liaison between the steering team and the project, although many informal lines of communication may also exist between the steering team and the project. The sponsor is primarily responsible for securing resources, removing obstacles, and mentoring the project manager and the core team.

Bob appears to be a wise choice for sponsor since he understands organizations, communicates well, and works effectively with teams. While Bob’s technical expertise appears weaker than Gary’s, other participants can provide expertise. In a true team setting, the experts will lead within their competence. Bob’s willingness to ask detailed questions should help.

The project manager is the primary communicator both internally within the project and externally with many individuals and groups who have an interest in the project. When situations call for action, the project manager needs to be able to:

•  Advocate a project vision effectively

•  Keep attention focused on key issues

•  Listen well and speak clearly

•  Inspire confidence

•  Create a sense of urgency

•  Care for and protect people

•  Defend the core values of the organization and project

•  Lead change fearlessly

•  Coordinate a multitude of tasks

•  Make sensible tradeoff decisions.

Uma appears to be a good choice. Since the two key people have been chosen, it is now time for Uma (the project manager) to assess herself and Bob (the project sponsor) in terms of their personality types, their emotional intelligence, their team-building skills, their weaknesses, and their professional needs and desires. The project manager and sponsor will need to communicate effectively with many people, including the steering team, who will guide them, and the project core team, who will collectively make many project decisions and perform many of the project’s tasks.

A project core team is generally a small group of people who are assigned to the project during initiating and remain for the duration. They collectively make many project decisions and either perform or lead the performance of most of the project tasks. Bob and Uma decided that subject matter experts (SMEs) would not be members of the core team, but would be selected on a just-in-time basis.

Project core team members then need to be chosen based upon three general criteria: their technical competence, their ability to help the team function well, and their desire to do whatever it takes to complete the project successfully. This is a good situation for Uma. Since she is choosing several people at once and the positional leaders are known, she can balance her choices, perhaps accepting someone with a technical competence that is hard to find who lacks certain teaming skills and finding another person with those skills. Diversity is the key: She will want to choose people with different styles, experiences, and approaches to problem-solving to ensure that many possibilities are considered.

The project core team needs to comprise committed, qualified, and diverse people. It is wise to have a mix of very experienced individuals and some new players who can learn and be developed during this process. Bob and the steering team need to ensure that Uma sees the bigger picture and chooses people who will be effective in this project and in future projects. It does appear that a wide range of departments is represented on the project.

One key question to ask when deciding if someone should be on the core team is: Do we need this person’s expertise throughout the project or just part of the time? The core team ideally should remain intact for the entire project. Another key question is how big the core team should be. While many factors enter into this decision, one useful rule of thumb is that smaller teams communicate more easily. An offsetting factor is that different departments and units need to be represented when decisions are made.

The last major role is for SMEs. These individuals are brought onto the project as needed, and some may perform a little work on many projects. One challenge with SMEs is to get them to buy into the project. Since they have less involvement, often they have less commitment. While many SMEs are selected just-in-time, some critical resources are in such short supply that the need for their services should be identified and prioritized as far in advance as possible.

Project Leadership Lesson: Initiating—Human Resources

A Project Leader Needs to:

Accept the weaknesses and idiosyncracies of potential key project participants

Have the courage to select appropriate participants and reject inappropriate participants

Exercise the wisdom to make the right choices.

DETERMINE TEAM OPERATING METHODS

Bob, Uma, and the team gathered in the conference room. Bob invited Gary from the steering team to join them. Bob welcomed the group and introduced the steering team and the core team. Bob and Gary made the same presentation they gave to the executive team highlighting the importance of this project. Gary told them that the first task would be to come up with a couple of potential approaches and a project charter. Uma then addressed the team and said “I welcome you all. I hope that you all understand why you are part of this team. I am looking forward to working with you. Expect to be in meetings for the next couple of days.” As soon as she said that, Jeff started thinking that he would rather be out in the field selling and earning commissions instead of being stuck in meetings.

Uma sensed that the group might have questions about her, since not many of them had worked with her before. After the meeting Scott mentioned to Paul that the last time he had a woman project manager she was very emotional and controlling.

Uma decided to have the first meeting in an informal atmosphere at a park nearby where lunch would be served. She hoped that the offsite meeting would help the team get to know each other in an informal setting. When they all gathered at the park Uma welcomed each one of them, mentioning that all of them bring value to the team and that each is very important to the team. Uma asked each team member to introduce themselves and say what they like to do for fun. She also asked them to share their good and bad experiences on their previous projects and ask any questions they had about her.

After everyone introduced themselves, the team started dispersing into small groups. By the end of the day Scott thought that he should not compare Uma with his last woman project manager but should judge her on her own merits. Jeff, who had been very apprehensive, was having fun and enjoying the company of Elizabeth.

The next morning the entire team (including Bob, the sponsor) met in the conference room. The day’s agenda was to develop a team mission, identify roles and responsibilities, develop team operating methods, and formalize decision-making procedures. Bob quoted Stephen Covey: “An empowering organizational mission statement focuses on contribution, on worthwhile purposes that create a collective deep burning ‘Yes!’ … It contains both vision and principle-based values. It addresses the needs of the stakeholder.”2 He also said that the team has to deal with the five basic elements of desired results, guidelines, resources, accountability, and consequences.

Elizabeth stated, “In my last project, for each meeting we would assign a facilitator and a scribe. When the project manager could not attend, we assigned someone else to lead the meetings.” The team thought it was a good idea. Bob volunteered to be the facilitator and Elizabeth to serve as the scribe for this meeting.

After the mission was determined, Uma asked the team to discuss team operating methods and decision-making procedures. Paul said he had found team charters useful in the past and suggested they develop their own team charter to supplement the project charter. The team, however, decided to incorporate team methods into the project charter.

Project Leadership Considerations

By using an inviting approach, it appears that Uma has broken down many prejudices and assumptions and helped each team member get excited about her, the project, and other team members. It is important to establish a climate of openness, trust, and fun. This climate must recognize that individuals have different needs, concerns, and abilities to change. The project leader should honor each individual while establishing workable team operating methods. Appendix C is a project leadership assessment that can be used both now, while project team operating methods are being established, and during the project execution stage, when the project team is accomplishing its work.

The project’s parent organization may strongly influence the operating methods. At the more formalized end of the spectrum, some organizations have quite specific operating methods that all project teams are expected to follow. Organizations like these often have reminders mounted in conference rooms, templates in shared network files, trained facilitators to help new teams, and other measures to ensure that all project teams follow the prescribed operating methods. At the less formalized end, some organizations not only have no standards, but also have little patience for project teams that want to take time up front to establish operating methods. Many organizations fall somewhere between the extremes.

The reasons for having project team operating methods is to prevent some problems from occurring in the first place, smooth out difficulties, help the team use their time efficiently, and create an atmosphere for making decisions that minimize inappropriate conflict. Some of the more frequently developed operating methods include decision-making and meeting management.

Decision-Making

Several types of decision-making are useful in projects: consensus, leader-imposed, delegated, voting, and scoring models. Each method has its place. A wise leader learns when each is desirable and how to facilitate each decision-making method.

True consensus occurs when every person on the project team agrees that the decision makes sense and he or she will enthusiastically support it. Each project team member must be committed to supporting the decision even when it may not be his or her personal favorite. Achieving true consensus takes time, effort, and deep understanding of all the underlying issues (not just the stated positions) in a situation. Consensus should be used primarily when enthusiastic buy-in will be needed to implement a critical project decision.

Some project decisions must conform to organizational desires. When this is the case, leaders—especially the sponsor and the project manager—should make the decision and inform the team. Project leaders can also make many minor decisions.

A wise project leader, however, will delegate many of the minor decisions. This delegation accomplishes several desired outcomes. First, it unburdens the project leader, freeing him or her to spend more time and energy on issues that are important at the leader’s level. Second, it can be very empowering to project team members to make more of their own decisions. Third, especially if the decision involves technical details, a team member may be able to make a better decision. Delegating progressively more important decisions is a process in which the team member demonstrates an increasing ability to make sound decisions and the project leader actively mentors the team member. This delegation process is one of the important skills effective project leaders must develop.

Voting can be used in several ways. First, multi-voting can be used by a project team to quickly screen a large list of potential options to a manageable number of options that can be considered in more detail. Informal polling is sometimes useful when testing for consensus. In that sense, it can be part of the consensus development. Voting should rarely be used, however, for making final decisions because losers in the voting will probably not be enthusiastic supporters of the decision.

Scoring models, sometimes called weighted scoring models or prioritization matrixes, are useful when multiple criteria—some of which are more important than others—need to be considered. For example, before buying a car most people will consider several factors, such as cost, gas mileage, and style, and will weigh them differently. The scoring models are a formalized method for teams to make these kinds of decisions. A scoring model example is shown in Table 2-7.

When using a scoring model, the project team should:

1. Decide what criteria are important in the upcoming decision. In the example shown in Table 2-7, cost, schedule, risk, and buy-in were selected. (Cost and schedule are usually quantitative while buy-in is an example of a subjective criterion for which the group will need to decide on the rating.)

2. “Weight” the importance of each criterion. This is easily accomplished by deciding which criterion is most important and then determining the comparative importance of each of the other criteria. Sometimes a project sponsor will complete these first two steps to ensure that the decision supports what he or she feels is important. In this example, the criteria importance weights add up to 100 percent. Buy-in was determined to be the most important, followed by risk, cost, and then schedule. There can be a tie in importance—for example, cost and risk could both have been 25 percent.

TABLE 2-7 Scoring Model

3. Generate a list of alternatives. This is best accomplished after the criteria have been established and weighted since there is less temptation to manipulate the process at this point. These are shown as approaches A, B, and C.

4. Rate each alternative on each criterion. This is most easily accomplished if the team uses a simple scale of 1 to 5 (with 5 being the best). The project team should rate all alternatives on one criterion before moving to the second criterion. In this example, all three approaches should have been rated on cost before any other criterion is considered. Also, in this example note that Alternative C was rated 5, meaning it was the best, B was rated 3, meaning average, and C was rated 1, meaning worst.

5. Multiply the rating times the weight for each cell (that is, for each alternative on each criterion). For example, the cost cell on alternative B was rated 3 and worth a weighting of .2, for a weighted score of .6.

6. Add across the rows to get a total score for each alternative. The one with the highest weighted score wins.

Meeting Management

The project team will spend a great deal of time in meetings. Therefore, it is sensible to establish a meeting process and to work continuously to improve this process. This includes:

•  Creating and distributing advance agendas

•  Delineating roles such as leader, facilitator, and scribe

•  Recording and sharing useful meeting minutes

•  Evaluating the meeting process with an eye toward improvement

•  Completing agreed-upon tasks between meetings.

A project leader who would like to improve the meeting process can use the plan, do, check, act model3 to illustrate the process, as shown in Figure 2-1.

An agenda should be created and sent to the project team members before each meeting so they can be prepared for the meeting. Agendas are often also posted in shared folders or on intranets or otherwise distributed so other key project stakeholders are aware of what will be discussed at upcoming meetings. Figure 2-2 presents a meeting agenda template.

FIGURE 2-1 The Meeting Cycle

Bob and Uma were appropriate in performing the facilitator and scribe roles at the first core team meeting. As leaders it is wise to role-model behavior before insisting that others perform in the same fashion. To help the core team develop, both as individuals and as a team, Bob and Uma should set the expectation that other team members will serve as facilitator and scribe in future meetings.

Effective project teams also record important information shared, decisions made, upcoming issues identified, action items committed to, and improvements suggested in terse but accurate minutes. Figure 2-3 provides an example of a meeting minutes template.

A wise project leader will take a couple of minutes at the end of a project meeting to ask what went well at this meeting that we would like to repeat and what could be improved. A simple technique to capture this information is called “plus delta,” with plus representing positive items and delta representing items to be changed. It is important for a leader to respond to every suggestion and to follow up to ensure that helpful suggestions are implemented. The discerning project leader will develop a feel for how to respond to each suggestion. When conducting a plus delta evaluation, the project leader will usually use a flip chart or marker board to have it visible, but then have the scribe copy the results in the project team minutes.

FIGURE 2-2 Meeting Agenda

The final part of project meeting management is the work team members do in between meetings. Good project leaders develop a sense for what kind of conversations to have with each team member to ensure that their work is completed correctly and on time, but without overmanaging capable and willing workers.

Project Leadership Lesson: Initiating—Human Relations

A Project Leader Needs to:

Accept that individuals have needs that must be honored

Have the courage to develop project team operating methods that must be followed

Exercise the wisdom to know when each is appropriate.

FIGURE 2-3 Meeting Minutes

DEVELOP TOP MANAGEMENT SUPPORT

At this point Bob and Uma went before the steering team. Uma talked with passion about the project, highlighting how it was going to help build customer relationships. She did a good job convincing Mark and Gary. Peter raised the question, “Why is this project more important than a new research and development initiative which is being pushed to the next quarter?” Uma answered him, saying that this B2B project is important to our existing customers and is in alignment with our business philosophy of partnering with customers. Peter’s department (engineering) will gain help in automating the transfer of engineering drawings and expediting production schedules. Mark as CEO added his comments and vision for the future of the company and indicated that he felt that the project should be approved. At that point everyone on the executive team agreed.

Project Leadership Considerations

What we have observed in Bob and Uma’s meeting with the steering team is the culmination of an ongoing dialogue. It appears they have done a good job in laying the groundwork for top management support of their B2B project. The approval came quickly at this point, indicating that there was probably informal communication with the key leaders prior to this meeting. Uma’s skillful handling of Peter’s question, showing him how his department would benefit, left him no option but to agree and diffused his criticism. Possibly Peter’s question suggests that Bob and Uma may not have informally answered all of his concerns in advance. While project leaders try to head off problems, frequently a few questions remain.

Wise project leaders will open multiple informal channels of communication and keep them open. One key lesson is: Never surprise your boss. It is prudent for a project leader to think of the entire steering team as multiple bosses. While open communication is generally a good idea with supporters, there may be one or two members of the steering team who are so antagonistic to a particular approach that convincing evidence should be developed before communicating with them.

Developing top management support is vital since any senior executive who is hostile to a project may find a way to sabotage it. A project manager does not want a difficult project to be accepted by a vote of five executives for it and four executives against it.

Project managers often need to coordinate the efforts of various workers from different disciplines over whom they have no authority. While this may be challenging it is often a reality in modern leadership—and is also a helpful experience for moving up in the leadership ranks in an organization. The exposure that project managers have in developing top management support provides an excellent opportunity to develop their leadership skills and stature within an organization. Junior project managers should see this wooing of top management support as an opportunity for visibility and should make every effort to perform this responsibility well, both for the immediate sake of their project and for the long-term sake of their career.

Project Leadership Lesson: Initiating—Project Promotion

A Project Leader Needs to:

Accept the true concerns of various top managers in the parent organization

Have the courage to challenge top managers’ concerns that are the result of narrow or biased thinking

Exercise the wisdom to know the difference between these two types of concerns.

COMMIT TO THE PROJECT

Bob and Uma took the project charter that had been approved by the steering team back to the project core team for a signing ceremony. The steering team also recommended an incentive of 10 percent of salary for the successful on-budget, on-time completion of this vital project. Everyone enjoyed refreshments as they celebrated the successful close of the project initiating stage and prepared for the project planning stage. The project charter is shown in Figure 2-4.

Project Leadership Considerations

The initiating stage of a project is complete when the project team and the sponsor sign the charter. The charter is one of the most important project documents and, arguably, the one that project sponsors have the most personal involvement in creating. Project sponsors must ensure that other planning and control documents are completed, but they must be personally involved in the creation of a charter. Other project leaders (that is, the project manager and the core team members) will have extensive personal involvement in creating other planning and control documents in addition to the charter.

A project charter is a contract between the project core team and the sponsor (who represents both senior management of the organization and the outside customer). As with a contract, the people who sign the charter should ensure that they understand and agree to every detail within it. Either party (the sponsor or the project core team) can write the rough draft and then very candidly discuss each part of the charter with the other party. Sometimes the sponsor tells the core team right at the start which items are especially important, but more often either the team creates the rough draft or both parties develop it together. When both parties work together, the session is often facilitated by either an outside consultant or a disinterested executive from the parent organization (that is, one whose own area will not be substantially impacted by the project). Many organizations understand that serving as a project facilitator is a learning experience for rising executives and choose to assign this role to managers who show promise.

Essentially, a charter has two purposes. First, everyone involved in the upcoming project needs to develop a common understanding of what the project is all about. Second, each person needs to personally and formally commit to doing their best to achieve the agreed-upon project results—even when things do not go as planned. Many organizations have developed their own ideas of what must be included in a charter to accomplish these two goals. Organizations value speed and simplicity when creating charters. The charter is written to get a quick understanding of what is involved in completing the potential project with the knowledge that, if something is not acceptable, the project may not get approved. In many organizations projects are not considered official until a charter is completed and signed.

FIGURE 2-4 B2B Project Charter

Listed below are some of the typical key sections that are included in a project charter. For ease of remembering, we present these sections as the three “W”s to be accomplished, subject to the three “H”s, by using the three “C”s. We briefly define each section and list popular alternative names. Note that while the intent of most of these sections is included in many charters, many organizations combine sections or leave out one or two. As long as the two purposes of the charter (agreement and commitment) are accomplished, the exact format is certainly negotiable.

Typical Elements of a Charter

•  The Three Ws:

Why—also known as mission, purpose, objectives, or business case. This is the reason for undertaking the project. It is hard to commit to something unless you understand why it is important.

What—also known as scope overview or deliverables. This describes what will be accomplished.

When—also known as milestone schedule. This lists when key portions of this project should be completed. Critical success factors or metrics are a brief listing of what should be monitored closely to ensure that the project is making adequate progress; they are often the basis for the milestone schedule.

•  The Three Hs:

How much—also known as budget or spending authority. This shows how much the project is expected to cost and may include limits on specific aspects.

Hazards—also known as risks and assumptions. This identifies what might go wrong, how likely each risk is, the consequences if the risk happens, and what the project team plans to do about each risk.

How—also known as team operating principles or methods. This describes how the team will function. Organizations often have this established for all project teams and incorporate it by reference.

•  The Three Cs:

Communication plan—also known as reviews, approvals, and reports. This describes who needs to know what information, when, and in what format.

Collection of knowledge—also known as lessons learned and lessons shared or post mortems. This describes how this project team will perform this project better based upon what they learned from at least one previous project. A wise sponsor will not sign a charter until the project team has convinced her that they have learned from studying previous projects.

•  Commitment—also known as signature block or roles and responsibilities. This lists who is involved and often describes the extent to which each person can make decisions. It also is how the project team members publicly and personally show their commitment to the project by signing the charter.

The B2B team did the most important thing by constructing the charter that each team member and the sponsor representing top management publicly signed. The charter is pretty good as far as it goes.

The purpose statement includes two of the Ws: what and why. The deliverables expand on the what and the milestone schedule addresses the last W: when.

The three Hs are also covered, but are not very complete. The budget is how much (although it often must have more detail and support). The risks are the hazards. While these are listed, having three high-risk items should raise come concerns about the project approach. Team operating principles (the how) such as “team members will trust each other” seem pretty simplistic and hard to enforce.

Notably missing are most of the Cs. Commitment is the most important C and that is included in the roles and responsibilities. However, the communication plan and the collection of knowledge are entirely missing. Collection of knowledge (lessons learned and shared) will help a project team make better plans based upon the successes and mistakes of previous projects. These lessons learned should also be in the charter. Project teams often put the communication plan off until the planning stage. That is also acceptable—as long as it is accomplished. It is very important to remember who needs project information, when, and in what format, and then to provide that information. When people do not have the information they need, they are likely to guess and the rumors they spread will frequently cause problems for a project. A wise project leader will try to balance the needs for these W, H, and C elements for their charter with their interest in keeping things simple and keeping them moving.

Project Leadership Lesson: Initiating—Commitment

A Project Leader Needs to:

Accept his or her responsibilities as a project leader

Have the courage to help other project participants accept their responsibilities

Exercise the wisdom to understand the difference between these two types of responsibility.

Now that the charter is approved, the project team is ready to move into detailed project planning. The role of senior project leaders (sponsors) may diminish somewhat as they oversee the details rather than plan them personally; the role of the junior project leaders (all others) remains high during planning. Depending on the needs of each project, the amount of time that project leaders need to personally spend will sometimes diminish during project execution and closing.

NOTES

1. Paul S. Royer, Project Risk Management: A Proactive Approach (Vienna, VA: Management Concepts, Inc., 2002), p. 18.

2. Stephen R. Covey et al., First Things First (New York: Simon & Schuster, 1994), p. 222.

3. Timothy J. Kloppenborg and Joseph A. Petrick, “Meeting Management and Group Character Development,” Journal of Managerial Issues 11, no. 2 (1999), 166-179.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset