2
Forming the contract

2.1 As noted in the previous chapter, the RIBA Building Contracts are most likely to be used on projects that follow a traditional procurement route, with possibly a degree of contractor and/or subcontractor design input. The decision to use a RIBA Building Contract will normally be made at an early stage in the project, and certainly by the end of the RIBA Plan of Work Stage 3,1 as it affects issues such as the distribution of design responsibility between consultants and the contractor and the degree to which the client can control which subcontractors may be used.

2.2 Between the selection of the contract and the start of work on site, various processes will need to be undertaken: preparing the tender package and tendering; post-tender negotiations and appointment of the contractor; and formal execution of the contract. There will also be a pre-contract meeting, at which various matters are agreed. This chapter outlines these processes and considers particular matters that arise in relation to the RIBA Building Contracts.

Tendering

2.3 It can’t be overemphasised that, when a project is sent out to tender, the contractor should be given full and detailed information regarding the project requirements. This is the principal means by which a designer can ensure that the quality of detailing, finish and workmanship will reach the required standards. If the project is not to be fully designed by the client’s consultants, the contractor will require full information about the design that it is to provide, including any performance specifications.

2.4 Most importantly, full details should be given about which standard building contract is to be used, the particular conditions to be applied and any special terms. Consultants tend to focus on the design, technical and budget aspects, but clarity on the terms of the contract is just as important to the tenderer as these will affect the tender price. It is not advisable to introduce matters such as special contract provisions after a long tendering period, or after negotiations on price have been concluded: if they are not acceptable to the contractor, it will be in a very strong bargaining position. Furthermore, if contract documents are never formally executed, the details included in the tender package may subsequently form the basis of the contract between the parties (see para. 2.33).

Implications of the Consumer Rights Act 2015

2.5 This Act applies to contracts and notices between a ‘trader’ and a ‘consumer’. A ‘consumer’ is defined as ‘an individual acting for purposes that are wholly or mainly outside that individual’s trade, business, craft or profession’ (section 2(3)). For tendering purposes, it should be noted that it gives consumers a certain amount of protection with regard to discussion that might be held during the tendering period. Essentially, any statements or promises that are made by the tenderer to the consumer prior to the contract being entered into, and which the consumer relies on, may be treated by the consumer as a binding term of the contract, whether or not they are ultimately embodied in the contract. Therefore, a great deal of care needs to be taken to ensure that any promises made during or after the tender are recorded and included in the eventual contract, or alternatively, if withdrawn by the tenderer, that the parties agree that they will not be included. Ideally the client should not enter into detailed discussions with separate tenderers – this should all be handled through their team of advisers.

Tendering procedures

2.6 Normally, for projects of the scale for which the RIBA Building Contracts are intended, one of two methods will be used: competitive tendering with a small number of contractors, or negotiation with a single contractor. The client’s consultants will normally suggest which contractors should be considered, but the client may have worked successfully with firms before, or may have been recommended a firm by others, in which case those firms can also be included.

2.7 With competitive tendering, all tenderers should, of course, be sent identical information, so that they are competing on an equal basis. The tenders are then examined by the client’s consultants, and normally the lowest priced one is accepted. With negotiated tendering, only the identified contractor will submit a tender, which is usually subject to discussion before acceptance.

2.8 An alternative method is a two-stage process: initially, a small number of contractors are asked to tender on the basis of less than complete information. Negotiations will then take place with the one that makes the most attractive submission. This method is frequently used where the contractor is expected to have a significant design input but the client wishes to approve this design before entering into the main contract; the selected contractor can then work with the client’s consultants in finalising the design. It is unlikely that a two-stage tender would be used for a project based on one of the RIBA Building Contracts but, if it is, an agreement will be needed to cover the contractor’s liability to the client for its contribution to the design process.

2.9 Full guidance on tendering procedures can be found in the NBS Guide to Tendering: For Construction Projects (Finch, 2011), JCT’s Tendering Practice Note 2017 (JCT, 2017) and the RIBA Job Book (Ostime, 2013), but the most important aspect for the purposes of this chapter is what to include in the tender documents.

Information that must be included in tender documents

2.10 The information included in the tender documents will eventually form the basis of the contract itself. Therefore, clearly, the tenderers must be told which version of the contract will be used, i.e. CBC or DBC, and whether it will be entered into as a deed or as a simple contract. It must also be clear which of the tender documents are to be priced by the contractor and, if the documents are to have a priority, what that priority is (see para. 2.16 below).

2.11 The identity of the client (including whether it is acting as an individual or a company) must be crystal clear, as should the nature of the works, the location of the site and any restrictions on its use and access. In fact, all matters that will later be entered in the ‘Contract Details’ (located at the front of the two contracts) should be set out in the tender documents. A full list of the items included in the Contract Details is given in Table 2.1.

Table 2.1 Contract Details

2.12 Whoever is responsible for arranging the contract (usually the contract administrator) should discuss and agree all of this information with the client prior to tender. Some items are particularly important to raise at an early stage, so that the client has time to consider the matter and take advice, for example insurance and dispute resolution. Most are discussed in detail in other sections of this Guide (see the references in Table 2.1), but a brief introduction to key items in CBC and DBC is given here. There is also helpful information in the guidance notes to the contracts.

Whether the contract will be executed as a deed (Agreement: both contracts)

2.13 The decision as to whether the contract will be executed as a deed or as a simple contract (sometimes referred to as ‘under hand’) will affect the length of time the contractor will be held liable for a breach of the contract. Under the Limitation Act 1980, in the case of a simple contract the time limit for bringing an action for any breach is six years from the date of the breach, and in the case of a contract entered into as a deed it is 12 years. In the latter, the contractor’s risk is obviously greater, which may result in higher tender prices. If no entry is made, the default will be six years.

The site, and whether the building will be occupied (item C: both contracts)

2.14 If the building is to be occupied during construction, this will have significant implications for the contractor’s programme and the contract price. It is almost always slower, and more expensive, to work around partial occupation than it is if given a free run of the site. For example, added health, safety and security measures will be needed, such as the provision of protected access routes to the occupied parts. It will not be sufficient to simply indicate ‘yes’ as required: full details of the planned occupation will be needed (see para. 4.2). As well as indicating occupation, the client is also required to indicate any working hour restrictions (item E), and which facilities (electricity, parking, etc.) the contractor may use free of charge (item F, cl. 2.5).

Contract documents (item D, both contracts)

2.15 All the documents that will form the contract bundle should be clearly identified in the tender package. Many of these will have been prepared by the contract administrator and other consultants identified above, however there are some exceptions. If a contractor’s design proposal is required, this will also be a contract document, and details of what is required from the contractor at tender stage, and possibly post-tender but before the contract is executed, should be set out (this should be referenced here and also under item P, see para. 2.27 below). The tender documents may include documents prepared by a required specialist, or by other consultants who are not listed.

2.16 In the 2014 edition the parties were invited to rank the documents in order of priority. Although this was optional, it was a sensible provision, and the parties could consider adding in a ranking, provided the ranking is carefully thought through and practical (feedback on the 2014 edition suggested it was not being applied properly). Ranking helps to avoid arguments later when, as is almost inevitable on most projects, it is discovered that there are inconsistencies between them (note that it would still be possible for a lower priority document to supplement the material in a higher priority document, however it would not be able to contradict it: see RWE Npower Renewables v JN Bentley Ltd). The two matters to consider are, of course, quality and quantity, and it may be that the ranking is different for both these, e.g. the specification being the key document for defining quality, and the bill of quantities for amount. It will be particularly important, where the contractor is undertaking design, to state whether the client’s requirements for the design (probably included in the specification) or the contractor’s design proposals prevail. Effectively this will determine whether, in cases of conflict, the contractor’s primary obligation is to meet the specification requirements, or merely to provide what was set out in the contractor’s proposals, even if it is later discovered that those proposals do not meet the client’s design requirements. Normally a client would prefer the former approach.

The contract administrator and other appointments (items G and H, both contracts)

2.17 The names of the firms engaged by the client should be set out, rather than the individuals, although the main point of contact within each firm could be noted. The contract administrator has a key role in the contract (see Chapter 3) and, although identified, is not a party to the contract (cl. 5.1). The client may replace the contract administrator with another firm at any time, provided it notifies the contractor (cl. 1.3). The contract administrator may not be the only appointment; the client may also have engaged engineers, quantity surveyors and, possibly, a project manager. These should be listed under item H, and the client must inform the contractor of any later appointments as set out in cl. 1.3). The other consultants have no defined role under the building contract, and all communication should be with the contract administrator, but it is sometimes useful for the contractor to be aware of who else is advising the client.

Regulatory consents, fees and charges (item I, both contracts)

2.18 This item asks the parties to indicate who will be responsible for obtaining and paying for ‘regulatory and statutory consents, fees and charges’. It will almost always be the case that the client takes responsibility for planning permission because, unless the project is to be entirely designed by the contractor, which is unlikely, the contractor will not be engaged at the time planning permission is usually sought. The application and any permission issues are normally resolved before going out to tender (the RIBA Plan of Work 2013 notes that ‘Planning applications are typically made using the Stage 3 output’). It is possible, however, that the contractor may be required to deal with Building Regulations approval on small projects (by means of a building notice), but for more complex schemes the client will take responsibility. In the case of party wall consents, under the Party Wall etc. Act 1996 the building owner is required to serve notices on all adjoining owners of intended work on or near the site boundaries, and in many cases to appoint surveyors to act on its behalf. It is not possible to require the contractor to take on these roles under the building contract; a separate appointment would be needed (with either the contractor or another consultant).

Contract price (item K, both contracts)

2.19 Both contracts give two options for setting the contract price: ‘Contract Price’ or ‘Contract Price calculated in accordance with the Pricing Document listed under item D’. It is not entirely clear what this distinction means. Even if the ‘Contract Price’ option is selected, which the guidance notes describe as the ‘lump sum’ option, the contractor would still be entitled to additional amounts in the event of changes to the works, etc. (see para. 6.6). A pricing document would be very useful to assess these changes, for example the pricing document could be a fully priced bill of quantities, or a schedule of works or a contractor-prepared price breakdown; therefore, selecting ‘Contract Price’ does not preclude the need for a pricing document.

2.20 The second option has no space for entering a total Contract Price, so the effect of selecting this option would to create a measurement, rather than a lump sum contract. What is probably intended is that for this option the pricing document will be in the form of a schedule of rates. This will give rates for all types of work envisaged, but not quantities, and will have been prepared by one of the client’s consultants. Alternatively, if preferred, the contractor can be asked to prepare the document. The schedule of rates option is useful for projects where it is difficult to assess the likely quantity of work in advance, such as in refurbishment work, where the extent of repair work cannot be ascertained until demolition work is complete. However, there will be no overall contract sum, and it may be difficult to control the overall budget.

Liquidated damages (item L, both contracts)

2.21 The Contract Details require the parties to insert an agreed amount of liquidated damages per day, and the contractor should be informed of the rate at the tender stage. This is an amount to be allowed by the contractor in the event of failure to complete by the date for completion (cl. 10.1; note that if the works are divided into sections under optional clause 17, several different rates may be applied).

2.22 As a result of two decisions in the Supreme Court, it is no longer considered essential that the amount is calculated on the basis of a genuine pre-estimate of the loss likely to be suffered (Cavendish Square Holdings v El Makdessi and ParkingEye Limited v Beavis). Provided that the amount is not ‘out of all proportion’ to the likely losses, the damages will be recoverable without the need to prove the actual loss suffered, irrespective of whether the actual loss is significantly less or more than the recoverable sum (BFI Group of Companies v DCB Integration Systems). In other words, once the rate has been agreed, both parties are bound by it. Of course, for practical reasons, the rate should always be discussed with the client before inclusion in the tender documents, and an amount that will provide adequate compensation included, to cover among other things any additional professional fees that may be charged during this period. If ‘nil’ were to be inserted into the contract particulars then this would preclude the client from claiming any damages at all (see Temloc v Errill). If no sum were entered, the client may be able to claim general damages, but if this were the intention it would be better to set this out clearly rather than simply to leave the section blank.

2.23 If completion in sections is selected in item R, rates of liquidated damages are required for each section. Note that in this case, the rate should reflect the realistic losses to the client of not getting access to that section, which may not necessarily relate to the floor area of that part. In addition, the professional fees element may not be proportionally reduced.

Cavendish Square Holdings v El Makdessi and ParkingEye Limited v Beavis, Supreme Court [2015] UKSA 67

In this landmark case the Supreme Court restated the law regarding whether a liquidated damages clause may be considered a penalty. Key criteria for whether a provision will be penal are: if ‘the sum stipulated for is extravagant and unconscionable in amount in comparison with the greatest loss that could conceivably be proved to have followed from the breach’; and whether the sum imposes a detriment on the contract breaker which is ‘out of all proportion to any legitimate interest of the innocent party’. In determining these, the court must consider the wider commercial context.

BFI Group of Companies Ltd v DCB Integration Systems Ltd [1987] ClLL 348

BFI employed DCB on the JCT Agreement for Minor Building Works to refurbish and alter offices and workshops at its transport depot. BFI was given possession of the building on the extended date for completion, but two of the six vehicle bays could not be used for another six weeks as the roller shutters had not yet been installed. Disputes arose which were taken to arbitration. The arbitrator found that the delay in completing the two bays did not cause BFI any loss of revenue, and that BFI was therefore not entitled to any of the liquidated damages. BFI was given leave to appeal to the High Court. HH Judge John Davies QC found that BFI was entitled to liquidated damages. It was quite irrelevant to consider whether in fact there was any loss. Liquidated damages do not run until possession is given to the employer but until practical completion is achieved, which may not be at the same time. Therefore, the fact that the employer had use of the building was also not relevant.

Temloc Ltd v Errill Properties Ltd (1987) 39 BLR 30 (CA)

Temloc entered into a contract with Errill Properties to construct a development near Plymouth. The contract was on JCT80 and was in the value of £840,000. ‘£ nil’ was entered in the contract particulars against clause 24.2, liquidated and ascertained damages. Practical completion was certified around six weeks later than the revised date for completion. Temloc brought a claim against Errill Properties for non-payment of some certified amounts, and Errill counterclaimed for damages for late completion. It was held by the court that the effect of ‘£ nil’ was not that the clause should be disregarded (because, for example, it indicated that it had not been possible to assess a rate in advance), but that it had been agreed that no damages would be payable in the event of late completion. Clause 24 is an exhaustive remedy and covers all losses normally attributable to a failure to complete on time. The defendant could not, therefore, fall back on the common law remedy of general damages for breach of contract.

Dispute resolution (item N, both contracts)

2.24 Three forms of dispute resolution are listed in the RIBA Building Contracts: adjudication, mediation and arbitration. In DBC, all three can be selected, or none, or any combination. In CBC, the adjudication option is preselected to ensure that the contract complies with the Housing Grants, Construction and Regeneration Act 1996 (as amended), which requires that all contracts covered by the Act include the right to adjudication. Otherwise, the same applies as for DBC, i.e. the parties may choose any combination.

2.25 It is important to give careful consideration to the choice of dispute resolution options. The differences between them are significant, and it might not be possible for one party to persuade the other to use a different system after a dispute has arisen; this therefore is the only opportunity to determine how matters will be resolved. In particular it should be noted that whereas adjudication is preselected in CBC, it is optional in DBC. This is because adjudication could be seen as favouring the contractor, given the short response times that may be difficult for a lay client to deal with. If selected, the provisions will nevertheless be binding (the courts have held that consumer clients are bound by an adjudication agreement in a standard form contract, as it does not significantly affect the balance of power between the parties) (Lovell Projects v Legg & Carver). The different options and their implications, including for the completion of item N, are discussed in Chapter 10.

Lovell Projects v Legg & Carver [2003] BLR 452

The employers were residential occupiers and consumers who engaged a contractor to refurbish their house using the JCT MW98. This edition included the JCT’s own adjudication procedure (instead of relying on the Scheme for Construction Contracts, as it now does). The employers were advised by an architect, and during the tender negotiations they insisted that MW98 was used. Following an adjudication, the employers resisted enforcement of the decision on the basis that the adjudication provisions were unfair and had not been brought to their attention before they signed the contract. The court decided that contractual adjudication provisions in the consumer’s contract were not unfair under the Unfair Terms in Consumer Contracts Regulations 1999 because they did not cause a significant imbalance in the parties’ rights and obligations. The court bore in mind that it was the employers, not the contractor, who had proposed the term, and that the employers had access to advice from their contract administrator.

Contractor design (item P, both contracts)

2.26 If this item is selected it requires the client to indicate which aspects of the works are to be designed by the contractor. It is important that any aspect, whether a component, element or system (such as services), is delineated with care, as otherwise there may later be disagreements as to who is responsible for interfaces between these and any consultant-designed areas. It is very important that this entry is completed carefully and the consultant and client must give careful consideration to the issue of liability before sending out the tender documents.

2.27 As well as indicating which parts are to be designed by the contractor, the client is likely to want to stipulate requirements that the designed parts should meet. It would be sensible for the contract administrator to indicate in item P exactly where these requirements are set out (quite often this will be in the form of a performance specification). In addition, if the contractor is to be required to submit design proposals at tender stage, then this should be made clear in the tender documents, including the nature and extent of the submission required. Similarly, it may be sensible to set out details of any information to be submitted during the works, and the dates by which it will be required (cl. 15.2).

Insurance-backed guarantee and new building warranty (items U and V, both contracts)

2.28 These items require the client to set out details of any insurance-backed guarantee and/or new building warranty that will be required. These are similar products; the term ‘new building warranty’ is used mainly in the context of new homes, whereas ‘insurance backed guarantee’ can be applied to any type of building work. The National House Building Council’s (NHBC) Buildmark scheme is a well-known example of a new building warranty, which covers homes built by NHBC-registered builders. The scheme protects the homeowner against defects for ten years; for the first two years the builder is responsible for putting right any defects, and during the third to tenth years any damage to a home resulting from building defects is covered by an insurance policy. It will also protect the homeowner if the builder goes bankrupt during the course of the work but before completion. Various trade associations offer a range of insurance-backed guarantees for domestic and commercial work, for example the Federation of Master Builders’ Build Assure scheme, which offers a variety of packages, from simple liquidation cover to ten years’ protection against structural damage. If selected, the insurance-backed guarantee is to be provided before the start date (cl. 20.1).

Collateral warranty/third-party rights (item X, CBC only)

2.29 A collateral warranty is a separate contract entered into by the contractor and a third party, typically a purchaser or tenant of the completed building or a project funder. They are particularly important if the contractor is undertaking design, as without one the purchaser, tenant or funder will not be able to recover its losses should the building later develop defects.

2.30 If the client wishes the contractor to provide such a warranty, this should be made clear in the tender documents (if not the contractor may later agree to provide one, but the client would not be able to insist that it does). The details of to whom the warranty is to be provided and the form of warranty to be used should also be given. Standard forms of warranty are published by the JCT, although these may require some modification for use with the RIBA Building Contracts. The contractor must execute the warranties as set out within 14 days of being requested to do so by the client (cl. 23.1).

2.31 As an alternative to the use of a collateral warranty, the contract refers to the use of a third-party rights agreement. This facility was introduced by the Contracts (Rights of Third Parties) Act 1999. Until this Act came into force, it was a rule of English law that only the two parties to a contract had the right to bring an action to enforce its terms (termed ‘privity of contract’). Now, the Act entitles third parties to enforce a right under a contract, where the term in question was intended to provide a benefit to that third party. The third party could be specifically named or it could be an identified class of people. The Act, however, allows for parties to agree that their contract will not be subject to its provisions, and many standard forms adopt this course in order to limit the parties’ liabilities. Both RIBA Building Contracts state: ‘Third parties have no rights under the Contract’ (cl. 11.4). The concise contract, however, states that this is ‘unless item X of the Contract Details has been selected’ and provides for the client to require the contractor to enter into a ‘Third Party Rights Agreement’ (cl. 23.1), details of which must be set out in the Contract Details. It should be noted that there are no standard forms of agreement available for use with the RIBA Building Contracts, therefore the parties would need to draft their own.

Pre-contract negotiations

2.32 Once the tenders have been returned, the next stage is to finalise the agreement with the selected contractor. Ensuring that a contract is in place before construction work begins is a key task of the contract administrator, and to neglect to do so may constitute negligence.

2.33 A contract is formed when an unconditional offer is unconditionally accepted. In the context of a building project, where contractors have been invited to submit competitive tenders, the tenders constitute ‘offers’ to carry out the work shown in the tender documents for the price tendered. If a tender is accepted unconditionally then a contract will have been formed, and the terms of the contract will be those set out or referred to in the tender documents.

2.34 ‘Letters of intent’ can cloud the picture and should be avoided. If it is possible to accept the tender without qualification then it is better simply to write a letter to that effect, and the contract comes into existence from the moment the letter has been received by the contractor.2 The effect of a letter expressing an intention to enter into a contract at some point in the future will depend on the wording and circumstances in each case, but it is likely to be of no legal effect. Starting work on such a basis could have disastrous consequences for both parties.

2.35 If there is a period of negotiation before the formal contract is drawn up, careful records should be kept of all matters agreed in order that they can be accurately incorporated into the formal contract documents. These documents should always be prepared as soon as an agreement is reached, and before work commences on site. Failure to execute the documents does not necessarily mean that no contract is in existence, but it might give rise to sufficient doubt to require spending on legal fees in an effort to establish the true position (Goldsworthy v Harrison). In addition, it can often lead to avoidable arguments about what was agreed.

2.36 The formal contract, once executed, will supersede any conflicting provisions in the accepted tender and will apply retrospectively (Tameside Metropolitan BC v Barlow Securities).

Goldsworthy and others v Harrison and another [2016] EWHC 1589 (TCC)

The case concerned the enforcement of an adjudicator’s decision. The defendant employers were residential occupiers and the key matter in dispute was whether the parties had agreed contract terms that contained an adjudication clause. If they had not, the adjudicator had no jurisdiction. At the time of tender, there had been no mention of the use of JCT MW. However, an email around the time work began stated: ‘As discussed previously the contract will be a JCT Minor Work’, which was followed shortly after by another stating: ‘If you are successful in the quotation for the garage and summer house, and main works please note at that time there will be retentions applied and the JCT Minor Works Contract’. However the documents were never executed, and there was no evidence that key matters such as liquidated damages had been agreed. The court refused to give summary judgment, stating that without fuller evidence from both sides, in particular of the discussions lying behind the emails, it was impossible to say that there was not a triable issue on the question of whether the parties had agreed on the JCT Minor Works terms, in particular the gaps where particular options had not been filled in or agreed. The matter would therefore have to proceed to a full trial.

Tameside Metropolitan Borough Council v Barlow Securities Group Services Limited [2001] BLR 113

Under JCT63 Local Authorities, Barlow Securities was contracted to build 106 houses for Tameside. A revised tender was submitted in September 1982 and work started in October 1982. By the time the contract was executed, 80 per cent of building work had been completed, and two certificates of practical completion were issued relating to seven of the houses in December 1983 and January 1994. Practical completion of the last houses was certified in October 1984. The retention was released under an interim certificate in October 1987. Barlow Securities did not submit any final account, although at a meeting in 1988 the final account was discussed. Defects appeared in 1995, and Tameside issued a writ on 9 February 1996. It was agreed between the parties that a binding agreement had been reached before work had started, and the only difference between the agreement and the executed contract was that the contract was under seal. It was found that there was no clear and unequivocal representation by Tameside that it would not rely on its rights in respect of defects. Time began to run in respect of the defects from the dates of practical completion; the first seven houses were therefore time barred. Tameside was not prevented from bringing the claim by failure to issue a final certificate.

Preparing and executing the contract package

2.37 The RIBA Building Contracts have an ‘Agreement’ section at the start of the document that is to be signed by both parties. The contracts can be executed as a simple contract (sometimes termed ‘under hand’ in other contracts) or as a deed; if neither option is selected, the default is a simple contract. It is good practice to sign not only the form itself, but also a copy of all other contract documents, to avoid any arguments about exactly which contract or revisions are included in the contract. In CBC the client is given the option of signing as an individual or as a registered company; obviously, if it signs as an individual, the client will be personally liable to the contractor, whereas as a company its liability will be limited (see Hamid v Francis Bradshaw Partnership). The option of signing as a company is not offered in DBC, because a company would not fall under the residential occupier exception discussed at para. A1.7 of Appendix 1. Therefore, DBC cannot be used by, for example, a homeowner who wishes to engage a contractor through a company they own.

2.38 Once the tender process is complete and the contract has been signed, the contract administrator is required to give the contractor ‘up to two copies of the Contract Documents’ (cl. 5.2.1). This could be in any format the parties agree; there is no need to sign multiple sets – one set should be signed and then copies made. It may be that the contractor would prefer to have one of these as a secure PDF. The original is usually retained by the client, with the contract administrator holding a copy (or the other way around). Any changes are to be issued to the parties (cl. 5.2.2); this might happen, for example, if the parties agree an amendment. Any amendment should be in writing and signed by both parties (cl. 11.7).

Interpreting the contract and resolving inconsistencies

2.39 The RIBA Building Contracts are clearly laid out and generally easy to understand. However, it should be remembered that the contract between the parties comprises not only the signed contract form, but all the contract documents as well. Even if great care has been taken in preparing the contract documents, there can be unintended conflicts or inconsistencies between them. As a result, it may be difficult to anticipate their combined effect. This section looks at how the contract itself and the package of contract documents are to be interpreted, and how any errors or problems are corrected.

Definitions

2.40 A ‘Definition of Terms’ is set out on pages 17 and 18 of both versions of the contract. These should be used to interpret the meanings of clauses (they would be used, for example, by a court). For example, a Payment Notice is defined as ‘a notice that the Contractor issues to the Client, in accordance with clause 7, showing the payment that the Contractor considers is due and how it was calculated’. The contract also includes ‘defined terms’ that are not included in the Definition of Terms but are defined within the Contract Details. These terms are all capitalised throughout the contract and include, for example, ‘Contractor’, ‘Client’ and ‘Start Date’.

2.41 Note that no definition of ‘a day’ is given. It is suggested that in calculating periods of days, parties should adopt the normal procedure that all days including weekends should be counted, except for public holidays. To avoid any passible disputes, it may be sensible to set this definition in the specification preliminaries.

Priority of contract documents

2.42 Clause 11.1 states that:

This means that conflicting provisions in other documents, for example in the preamble to a bill of quantities, will not override the printed conditions. This gives clarity and avoids unintended clashes occurring. However, if the parties wish to agree special terms that differ in any way from the printed conditions, then it will not be sufficient to simply append them in a separate document: amendments must be made to the actual printed contract (note: this is easier to do in the online version). This could be done by amending the individual clauses in the printed contract; alternatively, clause 11.1 could be amended by adding a qualification that the revisions set out in another document will take precedence over the printed contract. Amending standard contracts is unwise without expert advice, as the consequential effects are difficult to predict. Deleting clause 11.1 would be particularly unwise as it may have unintended effects on the contract as a whole.

2.43 Subject to clause 11.1 (i.e. that the printed conditions take precedence), the parties would be able to set out a priority between the other contract documents. If no priority is set out and a conflict exists that gives rise to a dispute, the adjudicator or court would need to decide, on a balance of probabilities, what the parties’ intentions were when they made the contract. This is done objectively, i.e. the adjudicator or court is not interested in the subjective intention, but in what a disinterested bystander would conclude the parties had meant. A contract administrator trying to resolve conflicts in this situation would need to be equally objective, i.e. when looking at the documents as a whole, what, on balance, do they appear to mean?

Inconsistencies, errors or omissions

2.44 Clause 5.9 states:

The equivalent clause in the 2014 editions also required the contractor to notify the contract administrator of inconsistencies ‘between the documents and the law’. It is not clear why this was removed, but it would normally be implied that a competent contractor ought to notify any such discrepancies it finds, especially if the shortfall is a serious matter.

2.45 The contract administrator is given the power under clause 5.4.3 to issue instructions to correct any inconsistency in the contract documents, which would cover issues that have not been notified. Although expressed as a power, and not a duty (as in JCT forms), it is suggested that the contract administrator should normally take steps to resolve any problems that emerge. Any such instruction that results in a change to works is to be dealt with in the same way as a clause 5.4.1 change to works instruction (cl. 5.11, see paragraph 6.12).

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset