5
Control of the works

5.1 The previous chapter focused on the programming of the works, and on monitoring progress in relation to the planned programme. This chapter examines the quality of the works: how it is achieved, who is responsible for it and what steps can and may need to be taken if problems are experienced.

5.2 Achieving the contractual standard is entirely the responsibility of the contractor, but the contract administrator also has a role to play, by providing information on the required standard and monitoring whether it is achieved. The RIBA Building Contracts also confer various powers on the contract administrator that can be used if the contract administrator feels it is necessary to step in.

Control of day-to-day activities

5.3 The day-to-day control of the works, i.e. the management of operations on site, coordination of orders and supplies, procurement of labour and subcontractors, and all issues relating to quality control, is entirely the responsibility of the contractor.

‘Person-in-charge’

5.4 In order that its responsibility is carried out properly, the contractor is required to ensure that ‘a suitably qualified representative is on Site during the Works to answer queries and receive instructions on its behalf’ (cl 1.3). What constitutes ‘suitably qualified’ would depend on the nature and scale of the project, i.e. the representative should be sufficiently qualified to fulfil their role competently and in accordance with the contract. The contracts do not require that the person is present ‘at all times’ (as in the JCT’s SBC11), and it may be that something less than full-time presence would be acceptable, provided that they are present at all material times, and that they make arrangements for dealing with queries or receiving instructions during short absences. There is no requirement in the Contract Conditions to have the person named, but it would be good practice to establish the identity of the person at the pre-start meeting, and to make sure this is recorded in writing.

Responsibility for subcontractors

5.5 The contractor is also fully responsible for the quality of work of all subcontractors (cl 1.7), whether these are its own domestic subcontractors or those selected by the client under the required specialists optional clauses (cl A7.1.3 CBC; or A5.1.3 DBC). As there are no provisions in the RIBA Building Contracts for the client to directly engage other firms, any persons on the site during the works would be under the direct supervision and responsibly of the contractor. If the client made any special arrangements with the contractor, outside of the contract, to allow its directly engaged persons on site, then this would cause confusion as to who is responsible for their performance, including in relation to quality of work, progress and health and safety, unless a detailed agreement regarding these matters is drawn up.

Principal designer

5.6 The RIBA Building Contracts require that both parties comply with all health and safety regulations (cl 4.3). The key relevant regulations are the Construction (Design and Management) Regulations 2015, which came into force on 6 April 2015 and apply to all construction projects.

5.7 For almost all projects, the Regulations require the client to appoint (in writing) a principal designer and a principal contractor (Regulation 5). The principal designer manages and co-ordinates health and safety aspects during the pre-construction phase, and then liaises with the principal contractor and co-ordinates ongoing design work during the construction phase. The principal designer could be the architect and/or the contractor administrator, but this is not necessarily the case; the role of principal designer is a distinct one and should normally be covered by a separate appointment. The principal contractor, which will almost always be the contractor under the contract, manages the construction phase of a project. This involves liaising with the client and principal designer throughout the project, including during the pre-construction phase, and producing a plan of how it will manage health and safety on site during the construction phase. If a domestic client fails to make the required appointments, the Regulations state that the designer in control of the pre-construction phase of the project is the principal designer, and that the contractor in control of the construction phase is the principal contractor (Regulation 7(2)).

5.8 If either party breaches its obligations under clause 4.3, it will be contractually liable to the other party, as well as liable under the Regulations. For a detailed understanding of their roles, the parties should consult the Regulations and related guidance.1

Flow of information

5.9 The most important function of the contract administrator is to ensure that the contractor is supplied with detailed and accurate information, either at tender stage or during the project, which makes clear precisely what standards and quality are required. In projects where the contractor is undertaking design, it will be required to submit its design to the contract administrator before or during the construction phase. The overall responsibility for integrating that design with the rest of the project rests with the contract administrator.

Information to be provided by the contract administrator

5.10 In most projects the information in the contract documents is not sufficient to construct the works; a certain amount of detailed information (e.g. schedules of finishes) is often outstanding, and it is usual for the contractor to be provided with this information during the course of the work. The RIBA Building Contracts – unlike, for example, the JCT’s MW11 (cl 2·4) – do not contain an express obligation to provide further information. However, they do place a general duty on the contract administrator to issue instructions (cl 5.1), which would include instructions regarding detailed aspects of the works. In any case, such an obligation is likely to be implied with respect to all work that is not listed as a part to be designed by the contractor. It is difficult to see how a contractor could successfully achieve completion in the absence of a duty requiring that instructions, information, plans, drawings etc. are issued in good time, so the obligation is likely to arise under an implied duty to co-operate. The contract administrator should therefore assume that it should provide the contractor will all key information, the only exceptions being in relation to contractor-designed items and, possibly, very small items, where it may be that the contractor could be expected to determine these for itself (see Wells v Army & Navy Cooperative Society Ltd, also para. 3.13, and National Museums and Galleries on Merseyside (Trustees of) v AEW Architects and Designers Ltd).

Wells v Army & Navy Co-operative Society Ltd (1902) 86 LT 764

The Court of Appeal refused to allow the deduction of liquidated damages where late completion was partly caused by late provision of information by the architect (as well as by variations and a delay by the employer in giving possession). These were considered acts of prevention that were not catered for in the extension of time clause in the contract, and it was held that the liquidated damages provisions were ineffective and could not be applied to the delay period.

5.11 The time by which information should be supplied is whenever the contractor needs it, given the overall progress on site and the date for completion. The contractor’s programme might have been required to set out dates for information to be provided, in which case this would be a guide, but it would not be conclusive. As with other issues concerning timing, it would be sensible to have this as an ongoing agenda item at progress meetings.

Information to be provided by the contractor

5.12 If optional clause A2 is selected, the contractor is required to provide information regarding its developing design, as set out in the Contract Details (item U in CBC, item R in DBC). The clause states:

This is a very useful provision to include, as it is essential that the contract administrator is able to monitor that the design meets the client’s requirements, as set out in the contract documents, and to co-ordinate it with the rest of the project.

5.13 The RIBA Building Contracts do not include a detailed procedure for submissions (e.g. format, response, comments or resubmission), such as that set out in Schedule 1 to SBC11. The administrator could, however, use the power under clause 5.4.7 to instruct that further or revised documents are provided. More importantly, the contracts do not include an equivalent clause to SBC11 Schedule 1:8·3, which states that:

5.14 If an RIBA Building Contract is to be used for a project where there are significant contractor design elements, then it may be wise to consider including some provisions regarding submission. Failing that, when making comments it might be sensible to remind the contractor of its obligation to ensure that the design is in accordance with the client’s specification (cl A2.1.3).

Inspection and tests

5.15 In addition to providing information, the contract administrator will also inspect the works at regular intervals to monitor whether the required standard is being met. The contract administrator may also, if necessary, issue instructions to have work opened up and tested, although this may have implications for the contract price and programme.

Inspection

5.16 On most projects the contract administrator will inspect the works at regular intervals. The RIBA Building Contracts do not place a duty on the contract administrator to do this, although they do give the contract administrator the power to visit the site and inspect the works (cl 5.3.1 and 5.3.2). Note that the reference in the guidance notes to the contract administrator’s ‘duty’ to visit and inspect is incorrect. However the contract administrator’s obligations to the client will, almost always, include a duty to inspect. Normally this would be an express duty under the terms of appointment, but in some circumstances it could also be implied: clearly, when the contract administrator is required under the contract to form an opinion on various matters – including being satisfied with the standard of work and materials prior to issuing a payment certificate – then it is essential that some form of inspection takes place. However, it is important to note that the duty is owed to the client, and not to the contractor. For example, a contractor cannot blame a contract administrator for failing to draw its attention to defective work.

5.17 Furthermore, a contract administrator will not necessarily be liable to the client for negligent inspection if a defect in a contractor’s work is not identified. The question in every case is whether the contract administrator exhibited the degree of skill that an ordinary competent professional would exhibit in the same circumstances. Generally, the extent and frequency of inspections must enable the contract administrator to be in a position to properly certify that the construction work has been carried out in accordance with the contract (Jameson v Simon). The case of McGlinn v Waltham Contractors Ltd sets out some useful advice on the appropriate standard of inspection.

McGlinn v Waltham Contractors Ltd [2007] 111 Con LR 1

This case concerned a house in Jersey called ‘Maison d’Or’ that was designed and built for the claimant, Mr McGlinn. The house took three years to build, but after it was substantially complete, it sat empty for the next three years while defects were investigated. It was completely demolished in 2005 having never been lived in, and was not rebuilt. Mr McGlinn brought an action against the various consultants, including the architect, and the contractor, claiming that Maison d’Or was so badly designed, and so badly built, that he was entitled to demolish it and start again. The contractor however had gone into administration and played no part in the hearing. The architect was engaged on RIBA Standard Form of Appointment 1982, which referred to ‘periodic inspections’. HH Judge Peter Coulson QC usefully summarised the principles relating to inspection (at paras 215 and 218), which included the following:

  • The change from ‘supervision’ to ‘inspection’ represented ‘a potentially important reduction in the scope of an architect’s services’.
  • ‘The frequency and duration of inspections should be tailored to the nature of the works going on at site from time to time’.
  • ‘If the element of the work is important because it is going to be repeated throughout one significant part of the building, then the inspecting professional should ensure that he has seen that element of the work in the early course of construction/assembly so as to form a view as to the contractor’s ability to carry out that particular task’.

Testing and defective work

5.18 As noted at the beginning of this chapter, it is entirely the contractor’s responsibility to ensure that the work is completed in accordance with the contract. The contract administrator is, however, given various discretionary powers that may be useful if it is concerned that the contractor does not appear to be fulfilling this primary obligation.

5.19 First, the contract administrator may issue instructions requiring any work to be uncovered, inspected and/or tested for compliance (cl 5.3.3, 5.4.3, and cl 5.7 in CBC or clause 5.5 in DBC). If the work proves to be defective, the contractor will bear the cost of the complying with the instruction and the correction of the defects (cl 5.7.1 or cl 5.5.1). If the work complies with the contract, the client will bear the cost of the complying with the instruction (cl 5.7.2 or cl 5.5.2). Generally, therefore, the contract administrator would only issue such an instruction if there was a serious concern, or if the failure of the element in question would be crucial to the project or extremely difficult to correct later. Failure to issue any instructions would not in any circumstances lessen the contractor’s responsibility, no matter how difficult or expensive it might be to correct the problem later.

5.20 Second, whether or not the defective work has been tested, the contract administrator has power to instruct that it is removed (cl 5.4.3). Alternatively, the contract administrator may accept work that does not accord with the contract ‘and adjust the Contract Price accordingly’ (cl 5.8 in CBC, or cl 5.5.3 in DBC). Care should be taken when doing this. The contract administrator should obtain the client’s agreement, and a value should be proposed and agreed (see para. 6.12). Although an instruction is not required (unlike in JCT contracts), it would be advisable for the contract administrator to confirm the acceptance and deduction in writing.

Contractor administrator’s instructions

5.21 The RIBA Building Contracts give the contract administrator wide-ranging powers to issue instructions. In some cases these are expressed as being a duty, and generally if the contract administrator fails to issue instructions necessary for the progress of the works, this may constitute a breach by the client. The full list is set out in Table 5.1.

Table 5.1 Matters about which the contract administrator may issue an instruction
table5_1.jpg

5.22 There is some overlap between clause 5.4.8 and the other clauses in Table 5.1. However, it serves as a ‘catch-all’ and gives the contract administrator a wide discretionary power.

5.23 Note that a ‘Change to Works Instruction’ is one that alters the ‘design, quality and/or quantity’ of the works. This is a narrower definition than in JCT contracts, in that it appears not to cover the manner of carrying out the works, working hours, access to the site and general management matters. However, the clause 5.4.8 provision for ‘Instructions on any clause of the Contract to enable good administration’ may well cover most of these matters.

Delivery of instructions

5.24 All instructions are required to be in writing, and the contractor is required to comply with them immediately (cl 5.5 in CBC, or cl 5.6 in DBC). If the contract administrator gives an instruction orally, the contract requires that it is confirmed in writing ‘promptly’ (cl 5.6.1/cl 5.7.1). If the contract administrator does not confirm the instruction, the contractor ‘shall issue a written record of the oral instruction to the Architect/Contract Administrator’ (cl 5.6.2/cl 5.7.2). Clause 5.6.3/5.7.3 then states ‘Except where clause 5.6.4/5.7.4 applies, a written record under clause 5.6.2/5.7.2 shall be the record of the Architect/Contract Administrator’s instruction unless the Architect/Contract Administrator amends it in writing within 5 days of receiving it’.

5.25 Ideally, contract administrators should avoid giving oral instructions, except in cases of emergency. If they cannot be avoided, it should not be difficult to confirm an instruction promptly using electronic communications. Remember that a simple email would constitute an instruction in writing; there is no need (although it may be good practice) to issue it in any special format.

5.26 The contracts (cl 5.6.2 in CBC and cl 5.7.2 in DBC) refer to the common practice whereby the contractor issues a ‘written record of the oral instruction’ (often termed a ‘confirmation of verbal instruction’ or ‘CVI’). Many contract administrators are comfortable with having the contractor confirm what they have said, but if this system is used, the contract administrator must be very vigilant and check that a contractor’s confirmation exactly reflects what was intended. In a busy office with a constant stream of emails, it is easy to misread one, and an inaccurate confirmation will become the contractual record after five days.

5.27 If the contract administrator would prefer to avoid this situation, it can instruct that oral instructions do not take effect until confirmed by the contract administrator in writing (cl 5.6.4 in CBC, cl 5.7.4 in DBC). The contractor is still required to send the written record under clause 5.6.2/6.7.2.

5.28 In the first system for dealing with oral instructions, it appears that the instruction is intended to take effect immediately; although the contracts do not say this, clauses 5.6.2 and 5.6.3 of CBC and clauses 5.7.2 and 5.7.3 of DBC refer to a record of an instruction, as if it is already effective – it simply needs to be recorded. However, under the second system, an oral instruction would be of no effect until confirmed by the contract administrator. Although this system would prevent inaccurate CVIs slipping through the net, there is a danger that an instruction could get overlooked entirely. The choice of which system to use is a matter of personal preference for the contract administrator. It can be decided after the contract is entered into, but the decision should be made early on in the project, ideally at the pre-contract meeting, as otherwise there could be confusion if an emergency unexpectedly arises.

Procedure following an instruction

5.29 In CBC, the contractor is given the power to notify the contract administrator, within seven days of receiving an instruction, if it believes the instruction is not in accordance with the contract or that implementing it would have adverse health and safety implications or would adversely affect any part of the works designed by the contractor (cl 5.9). (It is suggested that, in order to discharge its duty of care, the contractor should notify the contract administrator if any of these situations arise; this duty would apply to both contracts.) The contract administrator may then, on receipt of the notification, modify, amend, withdraw or confirm the instruction, and the contractor shall comply accordingly (cl 5.10).

5.30 In both contracts, if the contractor fails to comply with an instruction, the contract administrator may issue the contractor with a seven-day notice to comply (cl 5.11 in CBC, cl 5.8 in DBC), and if the contractor fails to comply with the notice, the client may engage others to undertake the instruction (cl 5.11.1/cl 5.8.1); this works in a very similar way to the notice to comply provisions in JCT contracts. As with the JCT notice, if the contract administrator has serious concerns that the contractor may refuse to comply (e.g. because it has already expressed that intention at a meeting) then it would be possible for it to issue the instruction and the compliance notice together. In addition to giving the client this right, the contracts require the contractor to co-operate with the new contractors (cl 5.11.2/cl 5.8.2) and to allow them access to the site (cl 5.11.3/cl 5.8.3), and the contractor is to be responsible for all costs and expenses incurred by the client (cl 5.11.4/cl 5.8.4).

5.31 Where a change to works instruction is issued, the contractor is required to calculate and submit details to the contract administrator of its effect on the contract price and date for completion (cl 5.12 CBC, 5.9 DBC). This must be done within 10 days of receiving the instruction. The contract administrator and contractor should aim to agree the appropriate revision of time and/or additional payment promptly, otherwise the contract administrator determines the appropriate amount (cl 5.13 CBC, 5.10 DBC).

Practical completion

5.32 The decision to certify practical completion is one of the most important that the contract administrator makes during the whole project as it triggers many contractual consequences that are important to both the client and the contractor. The period leading up to practical completion can be difficult and stressful. Sometimes this may be due to an (erroneous) belief by the contractor that the word ‘practical’ indicates that something that is 90 per cent finished, or could be occupied, has reached practical completion. At other times there may be pressure from a client who is very anxious to occupy the building, and who may not appreciate how much work is still needed to correct what might appear to minor matters. However, in the RIBA Building Contracts (unlike many other contracts), a clear definition of practical completion is given. Clause 9.15 states:

5.33 In addition, if optional clause A8 of CBC is selected, the contractor must have provided copies of all collateral warranties/third party rights agreements required before practical completion can be certified (cl A8.2).

5.34 It is suggested that ‘no aspect of the Works or a Section of the Works shall be outstanding’ includes aspects of quality, as well as quantity, therefore if the quality of work is unsatisfactory, practical completion as defined has not been reached. This interpretation has been supported by the courts, for example in the well-known case of H W Nevill (Sunblest) Ltd v William Press & Son Ltd. If the client nevertheless wishes to occupy the building with minor work outstanding, then a special arrangement will need to be made, as discussed below (see para. 5.40).

H W Nevill (Sunblest) Ltd v William Press & Son Ltd (1981) 20 BLR 78

Here William Press entered into a contract with Sunblest to carry out foundations, groundworks and drainage for a new bakery on a JCT63 contract. A practical completion certificate was issued, and new contractors commenced a separate contract to construct the bakery. A certificate of making good defects and a final certificate were then issued for the first contract, following which it was discovered that the drains and the hard standing were defective. William Press returned to the site and remedied the defects, but the second contract was delayed by four weeks and Sunblest suffered losses as a result. It commenced proceedings, claiming that William Press was in breach of contract and in its defence William Press argued that the plaintiff was precluded from bringing the claim by the conclusive effect of the final certificate. Judge Newey decided that the final certificate did not act as a bar to claims for consequential loss. In reaching this decision he considered the meaning and effect of the certificate of practical completion and stated (at page 87): ‘I think that the word “practically” in clause 15(1) gave the architect a discretion to certify that William Press had fulfilled its obligation under clause 21(1) where very minor de-minimis work had not been carried out, but that if there were any patent defects in what William Press had done then the architect could not have issued a certificate of practical completion.’

5.35 It is open to the parties to set out their own particular requirements for practical completion, including the standard expected and the means for establishing if it has been reached (cl 9.15.3). The parties might consider, for example, requiring that mechanical services are properly commissioned, that any performance in use criteria are tested and checked (e.g. airtightness and acoustic requirements), that an operations manual is handed over and the client trained in operation of the building. Any of these would, of course, have to have been made clear in the tender documents.

5.36 The contractor is required to notify the contract administrator when it thinks that practical completion of the works, or a section, has been achieved (cl 9.16). If the contract administrator agrees, it will issue a certificate of practical completion of the works or section as appropriate (cl 9.16.1).

5.37 If the contract administrator does not agree, it must inform the contractor of this (cl 9.16.2). It is important to note that the contract administrator is not required to give reasons for this decision, and there is certainly no obligation to produce ‘snagging lists’. It is common practice for the contract administrator to issue such a list, but, unless it has entered into special terms of appointment with the client, there is no need for it to do so. Not only is it very time consuming and resource hungry, it is effectively taking on the contractor’s quality assurance duties, which could ultimately lead to a confusion as to roles and responsibilities. If the contract administrator is concerned about particular defects, there is no harm in informing the contractor, provided it is made clear that these are just examples of some of the shortfalls on the project and that they are not intended to be a comprehensive list.

Consequences of practical completion

5.38 The consequences of practical completion are as follows:

  • liquidated damages will cease (cl 10.1);
  • half the withheld retention is released (cl 7.4 CBC, cl 7.2 DBC);
  • the defects fixing period commences (cl 10.2);
  • the contractor remedies defects identified during the defects fixing period (cl 10.3.1;
  • there is no requirement for the contract administrator to give notification of defects);
  • the client allows the contractor reasonable access to remedy defects (cl 2.1.3);
  • due dates change from monthly to two-monthly (cl 7.1, CBC only).

5.39 These consequences are important and therefore the contract administrator should take great care to ensure the defined level of completeness has been reached before certifying practical completion. Issuing the certificate with work outstanding places considerable additional risk on the client: the key areas being that there is no longer the sanction of liquidated damages to encourage the contractor to finish promptly, and the client holds only half the retention sum as security against any hidden defects. In addition, matters such as insurance of the works and health and safety will need to be resolved, and there are practical issues to do with managing the programming and payment for the outstanding work. The contracts have no provisions to cover these aspects as it assumes that the work will be finished, with the exception of defects that appear during the defects fixing period (see para. 5.46).

Use/occupation before practical completion

5.40 If the works have not reached practical completion, but the client wishes to use them, the contracts contain two provisions that may be of help to the client. The first is clause 9.17, which states that the client may request to use part of the works or a section of the works for ‘storage or other purposes’. In theory at least, the clause places no limits on what form the use might take. The contractor must grant permission, but only if the use does not interfere with the carrying out of the works. If the contractor agrees, it would be wise for the contract administrator to confirm this in writing, so that later this use cannot be raised as a reason for claiming a revision of time or additional payment. Practical completion is not certified and therefore none of the above consequences apply, although the contracts state that the client becomes responsible for the insurance implications of such use (cl 9.17).

5.41 The second provision allows the client to request to ‘take over’ (as opposed to ‘use’) any part or parts of the works or a section of the works before the contract administrator certifies practical completion (cl 9.18). As above, the contractor must grant permission, but only if the use does not interfere with the carrying out of the works. If the contractor agrees, the contract administrator must issue a notice clearly identifying the areas to be taken over and the date of takeover (cl 9.18.1). The contracts then state (cl 9.18.2):

5.42 Although it is not entirely clear, the reference to the part or section being ‘viewed as having achieved Practical Completion’ suggests that (a) the works to that part or section should be complete before takeover and (b) all the consequences of practical completion are intended to be triggered by the taking over, not just the defects fixing period. For example, although there is no specific reference to any reduction in liquidated damages, it would seem reasonable for some reduction to be made; this could be calculated on the basis of the proportion of the value of the completed works to the contract price. A similar reduction could be applied to the withheld retention. In order to avoid any doubt, the parties would be wise to agree the consequences in advance of the takeover, and the contract administrator to confirm them in the takeover notice.

5.43 There can be situations where the client is anxious to occupy part or possibly the whole of the works before any parts are sufficiently complete to be taken over under clause 9.18. Rather than viewing the work as having reached practical completion when it has not, it would be better if the parties make an ad hoc agreement as to what the arrangement will be. A suggestion was put forward in the ‘Practice’ section of the RIBA Journal (February 1992) which has frequently proved useful in practice: in return for being allowed to occupy the premises, the client agrees not to claim liquidated damages during the period of occupation. Practical completion obviously cannot be certified, and the defects fixing period will not commence, nor will there be any release of retention money, until the work is complete. Health and safety will need to be given careful consideration, and matters of insuring the works will need to be settled with the insurers.

5.44 Because such an arrangement would be outside the terms of the contract, it should be covered by a properly drafted agreement that is signed by both parties. (The cases of Skanska v Anglo-Amsterdam Corporation and Impresa Castelli SpA v Cola Holdings Ltd illustrate the importance of drafting a clear agreement.) It may also be sensible to agree that, in the event that the contractor still fails to achieve practical completion by the end of an agreed period, liquidated damages would begin to run again, possibly at a reduced rate. In most circumstances this arrangement would be of benefit to both parties, and is certainly preferable to issuing a heavily qualified takeover notice, or a certificate of practical completion, listing numerous incomplete items of work.

Skanska Construction (Regions) Ltd v Anglo-Amsterdam Corporation Ltd (2002) 84 Con LR 100

Anglo-Amsterdam Corporation (AA) engaged Skanksa Construction (Skanska) to construct a purpose-built office facility under a JCT81 With Contractor’s Design form of contract. Clause 16 had been amended to state that practical completion would not be certified unless the certifier was satisfied that any unfinished works were ‘very minimal and of a minor nature and not fundamental to the beneficial occupation of the building’. Clause 17 of the form stated that practical completion would be deemed to have occurred on the date that the employer took possession of ‘any part or parts of the Works’. AA wrote to Skanska confirming that the proposed tenant for the building would commence fitting-out works on the completion date. However, the air-conditioning system was not functioning and Skanska had failed to produce operating and maintenance manuals. Following this date the tenant took over responsibility for security and insurance, and Skanska was allowed access to complete outstanding work. AA alleged that Skanska was late in the completion of the works and applied liquidated damages at the rate of £20,000 per week for a period of approximately nine weeks. Skanska argued that the building had achieved practical completion on time or that, alternatively, partial possession of the works had taken place and that, consequently, its liability to pay liquidated damages had ceased under clause 17.

The case went to arbitration and Skanska appealed. The court was unhappy with the decision and found that clause 17·1 could also operate when possession had been taken of all parts of the works and was not limited to possession of only part or some parts of the works. Accordingly, it found that partial possession of the entirety of the works had, in fact, been taken some two months earlier than the date of practical completion, when AA agreed to the tenant commencing fit-out works. Consequently, even though significant works remained outstanding, Skanska was entitled to repayment of the liquidated damages that had already been deducted by AA.

Impresa Castelli SpA v Cola Holdings Ltd (2002) CLJ 45

Impresa agreed to build a large four-star hotel for Cola Holdings Ltd (Cola), using the JCT Standard Form of Building Contract with Contractor’s Design, 1981 edition. The contract provided that the works would be completed within 19 months from the date of possession. As the work progressed, it became clear that the completion date of February 1999 was not going to be met, and the parties agreed a new date for completion in May 1999 (with the bedrooms being made available to Cola in March) and a new liquidated damages provision of £10,000 per day, as opposed to the original rate of £5,000. Once the agreement was in place, further difficulties with progress were encountered, which meant that the May 1999 completion date was also unachievable. The parties entered into a second variation agreement, which recorded that access for Cola would be allowed to parts of the hotel to enable it to be fully operational by September 1999, despite certain works not being complete (including the air conditioning). In September 1999, parts of the hotel were handed over, but Cola claimed that such parts were not properly completed. A third variation agreement was put in place with a new date for practical completion and for the imposition of liquidated damages. Disputes arose and, among other matters, Cola claimed for an entitlement for liquidated damages. Impresa argued that it had achieved partial possession of the greater part of the works, therefore a reduced rate of liquidated damages per day was due. The court found that, although each variation agreement could have used the words ‘partial possession’, they had in fact instead used the word ‘access’. The court had to consider whether partial possession had occurred under clause 17·1 of the contract, which provides for deemed practical completion when partial possession is taken, or whether Cola’s presence was merely ‘use or occupation’ under clause 23·3·2 of the contract. The court could find nothing in the variation agreements to suggest that partial possession had occurred. It therefore ruled that what had occurred related to use and occupation, as referred to in clause 23·3·2 of the contract, and that the agreed liquidated damages provision was therefore enforceable.

Non-completion

5.45 If the contractor fails to achieve practical completion of the works by the date for completion, the client may deduct liquidated damages at the agreed rate (cl 10.1). There is no need for the contract administrator to have issued any certificate, although it would normally write to the client advising it of the position.

The defects fixing period

5.46 The contractor is required to remedy defects identified during the ‘Defects Fixing Period’ (cl 10.3.1). The period begins at practical completion and lasts for the length of time entered in the Contract Details (cl 10.2, Item K CBC and J DBC), the default period being 12 months (12 months is commonly used so that any mechanical services such as heating systems can be run through four seasons). A shorter period might be acceptable for very small projects.

5.47 The contracts do not state who should identify the defects. As part of its general duty to complete the works satisfactorily, the contractor would be obliged to ascertain whether any defects have appeared. There is no requirement for the contract administrator to prepare a schedule of defects at the end of the defects fixing period, as there is in some of the other standard contracts (e.g. IC11, cl 2·30), and the contractor’s obligation to correct work does not depend on it having been notified by the contract administrator. However, the contract administrator is required to issue a notice to the contractor requiring it to remedy any defect which it fails to fix (cl 10.3.3). If the contractor does not comply with the notice promptly, the client may engage others to rectify the problem, and all costs are the responsibility of the contractor (cl 10.3.4). This right would only arise if the correct procedures are followed; if the client, for example, refuses to allow the contractor reasonable access for inspecting and undertaking work, this might result in the client being unable to claim the costs of remedying the defects by others (Pearce and High Ltd v John P Baxter and Mrs A S Baxter).

5.48 In practice, correction of defects is normally left until the end of the defects fixing period, as it is usually more convenient for both parties if all the work is done together. However, sometimes a defect can cause considerable problems to the client, in which case the contractor should take steps as soon as it is aware of the matter. In either case, if the contractor fails to deal with any defect satisfactorily, the contract administrator should issue a clause 10.3.3 notice, in order to trigger the client’s right to engage others if necessary. After the end of the defects fixing period, when the contract administrator is satisfied that all defects are remedied, the contract administrator is required to notify the parties accordingly (cl 10.3.2).

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset