3
Roles and management systems

3.1 Contracts perform many functions: they assign risk, they set out obligations and rights, and they can also act as a management tool.

3.2 Generally speaking, where a contract states that an action ‘shall’ be performed, this indicates an obligation, also referred to as a ‘duty’; where it says it ‘may’ be performed, this is an optional action, referred to as a ‘right’ or a ‘power’. Some of the obligations and rights could be described as core; for example, the contractor’s duty to complete the works, the client’s duty to pay the contractor, and the contract administrator’s right to instruct a change to the works. Some are procedural, for example the obligation to submit a document within a particular time frame. The RIBA Building Contracts additionally have a group of clauses, under the heading ‘Collaborative Working’, which are aimed at assisting the smooth management of the contract.

3.3 This chapter describes the roles of the contract administrator, the contractor and the client, outlining their duties and rights. It then looks at some of the provisions in the RIBA Building Contracts that aim to ensure best practice management procedures are applied to projects.

Role of the contract administrator

3.4 The contract administrator is appointed by the client, and its duties and liabilities are owed to the client as set out in its terms of appointment. The contract administrator is not a party to the contract, but is named in the contract (cl 11.5), and the extent of its authority to administer the contract derives from the wording of the contract.

3.5 The RIBA Building Contracts place various duties on the contract administrator, particularly with regard to issuing certificates or statements, as well as a wide variety of powers, such as the power to issue instructions. For a full list of these duties and powers, along with references as to where they are discussed in this Guide, see Tables 3.1 and 3.2.

3.6 In some matters the contract administrator will act as an agent of the client, for example when issuing instructions that will vary the works. In other instances it acts as an independent decision-maker, e.g. when deciding on claims for additional payment. When acting in the latter capacity, it would be implied that the contract administrator must act fairly at all times. It would be sensible for the contract administrator to use one of the RIBA standard forms of appointment to ensure that the obligations under its appointment align with those in the RIBA Building Contracts.

3.7 Failure by the contract administrator to comply with any obligation, either express or implied, may result in the contractor suffering losses. As the contract administrator is not a party to the contract, if the contractor wishes to bring a claim, this would, in the first instance, have to be against the client. It is likely, however, that any failure to administer the building contract according to its terms would be a breach of the contract administrator’s duties to the client and, therefore, the client may seek, in turn, to recover its losses from the contract administrator.

Table 3.1 Contract administrator’s duties
table3_1 table3_1
Table 3.2 Contract administrator’s powers
table3_2

Role of the contractor

3.8 The contractor has the most extensive lists of duties and rights, which is unsurprising as it is the contractor which is primarily responsible for delivering the project on time and to the client’s requirements. Full lists of these duties and rights are provided in Tables 3.3 and 3.4, and the key duties are outlined below.

Completing the works

3.9 The main obligation of the contractor is to complete the works as set out in the contract documents. In both CBC and DBC, this obligation is set out in clause 1.1, which states:

3.10 The above clause does not refer expressly to ‘materials, goods and workmanship’, as would be usual in JCT contracts, and it is therefore suggested that ‘in a good and workmanlike manner’ refers to the method of carrying out the work, not what work is to be done. Therefore, it is essential that the standards for materials, goods and workmanship are set out clearly in the specification and other contract documents. Clause 1.2 states that:

This is also intended to refer primarily to workmanship, but may also act as a useful catch-all to cover matters that have not been specified in detail. However, it is doubtful whether the obligation would override, for example, any express specification that had set out methods or materials that were unsafe.

Contractor’s design obligation

3.11 Like most traditional contracts these days, the RIBA Building Contracts make provision for some design to be carried out by the contractor. It is an optional provision, but it is likely that on most projects it will be required to some extent. Any decision that affects the final form of the building (as opposed to the method of construction) is a design decision, even if it relates only to small levels of detail, such as the exact size of joist hangers or of central heating pipes. If in any doubt as to whether something is effectively ‘design’, the contract administrator should consider whether it is intending to make all the necessary decisions, and, if not, what would happen if the particular detail were to fail: would it be prepared to accept responsibility? If not, it should take steps to ensure that liability for design of that detail is expressly placed with the contractor.

3.12 The provisions are set out in optional clause A2, and the parts to be designed by the contractor are be described in item U (CBC) or item R (DBC) of the Contract Details. A ‘Contractor’s design proposal’ is referred to in item F (both contracts), therefore the contract anticipates that the contractor may have provided a design prior to the contract being executed, which may be for some or all of the parts, depending on what was requested at tender stage (see paras. 2.15, 2.16 and 2.27). It appears that the contractor is responsible for designing only the parts that are listed. The contract makes it clear that the contractor is not liable for design provided by the client or the client’s agents (A2.4). However, it must notify the contract administrator of any discrepancy it finds in those designs.

3.13 What happens if the contractor makes a design decision relating to a part that has not been stipulated in the Contract Details, but for which the contract administrator has provided no design information? It is possible that the contractor would not be held responsible for that design decision. A relevant case concerns the Museum of Liverpool (National Museums and Galleries on Merseyside v AEW Architects and Designers), where the judge said the contractor was not responsible for designing anything not identified as part of the contractor’s designed portion (CDP), in this case deciding the tolerance gaps between steps. Courts might a take less strict view in a smaller project, but to be safe it is best to use the ‘Contractor Design’ optional clause and to make sure the extent of the contractor’s design responsibility is clear.

3.14 It is therefore very important that the delineation between the parts to be designed by the contractor and the rest of the project is described accurately.1 This can be quite difficult in practice, especially where several parts or elements are listed, or the list includes a system (e.g. services) that is integral to many parts of the building.

3.15 The RIBA Building Contracts are clear that the contract administrator remains responsible for any integration. This could extend to the physical junctions between the contractor designed parts and other parts, but could also cover the combined performance of several systems or of systems and elements. If it is intended that the contractor is to be responsible for resolving any interface (physical or performance), the interface would have to be identified clearly within the parts to be designed by the contractor. The contractor retains the copyright in any design it provides, but grants the client a license to use it for the Works and related purposes (cl A2.5).

Contractor’s design liability

3.16 Under clause A2 the level of liability of the contractor for design is to use the skill and care of a competent designer. The contractor is also required to ensure that its design meets the client’s requirements. Taken together, this would not be interpreted as an absolute obligation to meet the specification, but a duty to use reasonable skill and care so that it does.

3.17 There are essentially two levels of liability used in construction. Professionals normally undertake to use reasonable skill and care, rather than promise to achieve a particular result. To understand this distinction, consider the case of a medical professional: a doctor would never promise to cure a patient, but simply to use their medical skills competently to achieve the best outcome possible. The fact that the patient does not get better is not of itself sufficient to show the doctor made a mistake. Similarly, with professional designers such as architects, the fact that there is a defect in the design is not sufficient to show they were negligent. Any client bringing a claim must also prove that the architect failed to use the reasonable skill and care of a competent architect. This is sometimes referred to as a ‘negligence-based liability’ and is the normal level of liability that would be set out in an architect’s appointment or would be implied by the courts if no level has been set.

3.18 The alternative, more onerous, level of liability is to promise to achieve a result. This is often referred to as a ‘strict liability’, as there is no need for the claimant to show that there was any negligence on the part of the designer; it would be enough to show that the result did not meet the stated requirements in some respect. A commonly used shorthand descriptor is that the designer has taken on a ‘fit for purpose’ liability. Contractors who undertake design work often take on an express ‘fit for purpose’ liability. Where no level of liability had been set out, the courts may imply that there is a strict liability, provided it can be shown the client was relying on the contractor’s skill and judgment.

3.19 The RIBA Building Contracts contain an option to set a strict liability obligation, in place of reasonable skill and care. This appears in the Contract Details under ‘Contractor Design’ (item U in CBC, or item R in DBC), which states ‘Contractor’s design to be fit for purpose’. No default is given: the parties are required to indicate ‘yes’ or ‘no’. However, the effect of clause A2.3 is that the default would be ‘no’, as it states:

3.20 Clients would usually prefer a ‘fit for purpose’ level of liability. After all, if they have taken the trouble, with their consultant, to set out detailed requirements for the design, including specific performance targets (e.g. in relation to energy use), they are likely to want to be able to bring a claim should the building not perform, without having to also prove a lack of care. However, as the ‘fit for purpose’ level of liability is more onerous on the contractor, some contractors may be unwilling to tender on this basis or might submit higher tender prices. The JCT contracts do not generally contain this option (except in the case of the Major Project Construction and Constructing Excellence contracts). However, it is an optional provision in NEC3 contracts (and standard in the FIDIC and IChemE contracts), and is often asked for in bespoke contracts, therefore its use is increasing.

3.21 Under clause A2.7 the contractor is required to ‘ensure there is adequate professional indemnity insurance for its design responsibilities, as set out in … the Contract Details’ (if no requirement is set out the obligation would fall away). The contractor might not be able to obtain insurance to cover a ‘fit for purpose’ risk, but that would not, of course, affect its liability.

3.22 Note that the contractor is also required to ‘compensate the [client] for all claims in respect of the Contractor’s designs’ (cl A2.6). This is a wide liability – it would cover, for example, claims by tenants for repair work or claims for breach of copyright – wider than a normal professional liability for design errors. There is no requirement to insure to cover this liability, and if the contractor’s design is extensive the client should consider whether to add this requirement at tender stage.

Contractor’s obligations in respect of subcontracted work

3.23 The contractor’s duties with respect to subcontracting the work are set out briefly in the following two clauses:

  • 1.6 The Contractor shall inform the Architect/Contract Administrator of any parts of the Works that it has subcontracted.
  • 1.7 The Contractor is solely responsible for carrying out the Works and for the performance of all subcontractors and suppliers.

3.24 The contractor may subcontract to anyone it chooses; there is no requirement to inform the contract administrator beforehand, or to obtain permission from the contract administrator or the client, and neither has the power to bar a contractor from using a particular firm. The contractor is, of course, entirely responsible for all its subcontractors (cl 1.7), so in theory there is no risk to the client, even if the contractor selects firms that are not capable of achieving the desired standard of work. However, in practice it can be frustrating to stand by without intervening, as work has inevitably to be redone and delays are caused.

3.25 If the client wishes to take a more proactive stance, there are two possible courses: one is to add a clause requiring the client’s or contract administrator’s permission for any sub-contracting (or perhaps only for subcontracting certain work), with such permission not to be unreasonably withheld. The second is to use the ‘Required Specialists’ provisions for critical areas of work.

Required specialists

3.26 Under an optional clause (A7 in CBC and A5 in DBC) the client may specify that the contractor uses particular specialists to carry out described parts of the works in the contracts. If used, the contractor is fully responsible for the performance of those specialists (cl 1.7 and A7.1.3, CBC; cl 1.7 and A5.1.3, DBC), in the same way that it would be for its own domestic subcontractors.

3.27 The details of the specialists, and the work they are to carry out, are entered in the Contract Details (item Z in CBC, or item U in DBC). Clause A7.1.1 (CBC) and clause A5.1.1 (DBC) require that the contractor should be given ‘reasonable advance notice of the Required Specialists and is deemed to be satisfied with their suitability’. What is ‘reasonable notice’ will depend on the circumstances. Normally a reasonable tender period should be sufficient; however, if possible, it may be prudent to alert contractors at an earlier date, i.e. before the formal tender invitations are sent out.

3.28 The notice period is included to allow the contractor to make enquiries as to the suitability of the firm, and its price and terms for carrying out the work. The requirement to enter into a subcontract with the required specialist (cl A7.1.2, CBC; cl A5.1.2, DBC) is said to be ‘subject to clause A7.1.1 [CBC; A5.1.1, DBC]’; therefore, if inadequate notice is given (e.g. the requirement is a late addition to the tender information or is introduced after the tenders have been returned), the contractor can refuse to engage the specified firm.

3.29 It is also possible that if the contractor is not given adequate notice, it may engage the specialist, but then attempt to claim for additional time and money should the firm later default on its subcontract (there is old case law that may support such a claim, for example see Gloucestershire County Council v Richardson). It is suggested that in the context of the RIBA Building Contracts the argument is unlikely to succeed: clause 1.7 and clause A7.1.3 (CBC) or A5.1.3 (DBC) are unqualified, and it is the requirement to engage the specialist, not the responsibility once engaged, that is subject to reasonable notice.

Gloucestershire County Council v Richardson [1969] 1 AC 480 HL

In this case the House of Lords considered whether a main contractor might be liable to the employer in respect of latent defects in materials delivered by a nominated supplier. It held that the main contractor’s liability to the employer was limited to the extent of the nominated supplier’s liability to the main contractor by operation of the terms of the nominated subcontract.

3.30 If the contractor terminates the required specialist’s employment, it must notify the contract administrator, who is required to ‘issue appropriate instructions regarding a replacement’. The contract then states that the contractor ‘shall be entirely responsible for any delay or additional costs arising from the termination’.

3.31 This juxtaposition is not particularly comfortable. If the contractor is responsible for the specialist firm, and the losses, then it would be more straightforward if it was given the responsibility of finding a replacement, subject to the contract administrator’s approval, and confirming instruction. However, there is nothing to prevent the contractor from making proposals, which would be sensible, as they may minimise the losses it will suffer. Nevertheless, the contract administrator is responsible for taking action and resolving the situation.

3.32 The contracts do not distinguish between the possible different reasons for the termination, so it appears that the liability would apply whatever the reason; whether a simple falling out or a disagreement about money, or because the firm seriously failed to perform. Furthermore, they do not discuss what would happen if the required specialist refused to undertake the project, or became insolvent, and yet no termination was issued. The contractor is only made liable for consequences of any termination, not of complete non-performance, and a contractor might argue that in these circumstances the client should carry the risk. It would therefore be sensible for the contract administrator to take action promptly, whatever the cause of the termination.

Compliance with statute/health and safety legislation

3.33 The contractor is required to comply with all statutory requirements (cl 1.1.2). In addition, clause 4.3 states that ‘the Parties shall comply with all health and safety regulations, including making any appointments or submissions required under such regulations’. CBC also requires the contractor to notify the contract administrator if, in its opinion, an instruction may have adverse health and safety implications (cl 5.9.2). It is not clear why this useful provision was not also included in DBC, nevertheless it is suggested that the contractor would normally be under a duty to warn of any instruction that would have an adverse effect.

3.34 Clause 1.1.3 states the contractor shall: ‘be responsible for all statutory fees, notices and charges not covered in item L [CBC; item K, DBC] of the Contract Details’. However, it is important to note that it is not just the statutory fees, notices and charges that are referred to in item L or K, as this states: ‘Responsibility for obtaining and paying for all planning permissions, Building Regulations approvals and party wall consents shall be taken by: [select Employer/Customer (default) or Contractor]’.

Table 3.3 Contractor's duties
table3_3 table3_3a table3_3b
Table 3.4 Contractor’s rights
table3_4 table3_4a

3.35 This is, of course, a far greater responsibility than is set out in clause 1.1.3. If the client wishes the contractor to obtain permissions, it would be important to make this clear in the tender documents, and to ensure that ‘Contractor’ is selected in item L (CBC) or item K (DBC), as otherwise this would not be covered by the lesser obligation in clause 1.1.3.

Role of the client

3.36 The client has a significant role in any construction project. Its key duties, outlined in Table 3.5, are ones of collaboration. For example, not to take any action that would interfere with the carrying out of the works, and to pay the contractor on time in accordance with the contract. The client is also given various rights, as listed in Table 3.6. Generally, though, the client should discuss both its duties and its rights with the contract administrator, and should seek the contract administrator’s advice before taking any action; the contract administrator has the overall responsibility for administering the project, and if actions are co-ordinated there is less likelihood of clashes or unexpected consequences.

Table 3.5 Client’s duties
table3_5
Table 3.6 Client’s rights
table3_6 table3_6

Customer acting as contract administrator

3.37 DBC is unusual in that it offers the facility for the customer to name themself as contract administrator (optional cl A6). Although it is sometimes frowned upon, there is no reason why the customer can’t name themself in this way, with the very important proviso that it must have been made completely clear to the contractor at tender stage that this was going to be the arrangement. The customer must also ask themself whether they have the skills and resources (particularly time) necessary to perform the role, and whether they are capable of being truly impartial. Any incorrect or biased decisions are liable to be challenged by the contractor and, if a reasonable solution is not agreed, may result in the contractor being successful in subsequent litigation (as the tribunal is likely to examine the decision very closely). It is unwise for a customer to hope that it may secure a ‘better deal’ by taking on the role of contract administrator.

Management systems

3.38 The RIBA Building Contracts place more emphasis on management, and have more provisions concerning meetings, co-ordination and communication, than do other equivalent contracts.

3.39 These provisions are aimed at ensuring the smooth running of the project. They include requirements to:

  • provide and update a programme;
  • give early warning of matters that may cause a delay or affect the contract price (see paras. 4.224.23);
  • suggest improvements (see para. 6.9);
  • hold a pre-start meeting;
  • hold progress meetings;
  • maintain a risks register.

Some of these mechanisms are discussed in other parts of this Guide, but the last three are of more general application.

Pre-start meeting

3.40 The requirement to hold a pre-start meeting, at least ten days before the work is due to start on site, is contained in clause 3.1. Both parties must attend, as well as the contract administrator. Clause 3.1 states that the parties must:

  • 3.1.1 set out expectations for each Party
  • 3.1.2 set out communication procedures, including any specific rules on electronic communications
  • 3.1.3 identify risks and set out the risk mitigation procedure
  • 3.1.4 set out any administrative procedures.

3.41 The pre-start meeting is often the point at which the contract documents are signed. None of the discussions ought to result in any changes to the contract terms or the obligations of the parties. However, it would be wise to bear in mind that there is nevertheless a close link between the above and various contractual issues. For example, the ‘expectations’ cannot be more than those that are already set out. The client, for example, cannot demand a higher standard of work than the level specified in the contract documents or that the contractor finishes earlier than the contractual date. If it becomes apparent at the meeting that expectations are at odds with those in the contract, then the documents should be amended before signature.

3.42 The meeting will be used to flesh out and fine-tune some of the procedural matters. Key among these would be whether the client is to remain in occupation, and what the exact arrangements will be with regard to security, safety, access, use of facilities, storage and disposal of rubbish. If any additional or new arrangements are made, these should be recorded and annexed to the contract documents. The same applies to communications and other administrative procedures; the meeting will also be used to agree communication procedures (cl 11.11.1); and if the parties fail to do this the contract administrator is required to issue instructions regarding these (cl 11.11.2). Generally all communication is to be in writing and issued to the parties and the contract administrator (cl 11.10), unless the contract states otherwise. Special procedures are set out in the case of termination (cl 11.12, see para. 8.26).

Progress meetings (CBC)

3.43 CBC requires that progress meetings are held monthly (or other period as agreed) and attended by the contractor, the contract administrator and any other party invited by the contract administrator (cl 3.6). The meetings should cover all operational issues relating to the project. It is common practice to hold such meetings, but including them in the contract means that it becomes an obligation on the contractor to attend, and a breach if it does not. The meeting will normally cover matters such as progress, technical issues and information needed, and is an opportunity to discuss advance warning notices. In particular, the contractor is required to provide an update to its programme five days before the meeting, which is a useful way for the administrator to monitor and record how the job is progressing. Parties using DBC may wish to consider adding in this provision.

Risks register

3.44 This is an optional provision that, if selected, requires the contract administrator to establish and maintain a risks register (cl A10 in CBC, or A8 in DBC). Initially, the register will list the risks and mitigation procedures identified and agreed at the pre-start meeting, but these are likely to be adjusted as the project progresses and new risks are identified. The register could be in the form of a simple list (or more likely a spreadsheet), and it is common practice to place a priority on the risks (e.g. highly likely, not likely), as well as to set out the measures or actions to be taken should a risk materialise and who will take them. Strictly speaking there is no contractual obligation to comply with any actions set out (unless, of course, the register includes obligations already covered in other contractual provisions). Nevertheless, it may be a useful point of reference in day-to-day communications and a good discussion item at progress and other meetings.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset