Chapter 15

Keeping Everyone Informed

IN THIS CHAPTER

Bullet Highlighting some important elements of communication

Bullet Deciding whether to share the news through writing or a meeting

Bullet Writing your project progress report

Bullet Getting familiar with different meeting styles

Bullet Creating a project communications plan

Imagine standing at one end of a large room filled with assorted sofas, chairs, and tables. You’ve accepted a challenge to walk to the other end without bumping into any of the furniture. But as you set off on your excursion, the lights go off and you have to complete your trip in total darkness, with only your memory of the room’s layout to guide you.

Sounds like a pretty tough assignment, doesn’t it? How much easier it would be if the lights went on every few seconds — you could see exactly where you were, where you had to go, and where the furniture would get in the way. The walk would still be challenging, but it would be much more successful than in total darkness.

Surprisingly, many projects are just like that walk across the room. People plan how they’ll perform the project — who will do what, by when, and for how much — and they share this information with the team members and other people who will support the project. But as soon as the project work begins, people receive no information about their progress, the work remaining, or any obstacles that may lie ahead.

Effective communication — sharing the right messages with the right people in a timely manner — is a key to successful projects. Informative communications support the following:

  • Continued buy-in and support from key stakeholders and team members
  • Prompt problem identification and decision-making
  • A clear project focus
  • Ongoing recognition of project achievements
  • Productive working relationships among team members

Planning your project communications upfront enables you to choose the appropriate media for sharing different messages. This chapter can help you keep everyone in the loop so no one’s left wondering whether or not your project’s on track.

I Meant What I Said and I Said What I Meant: Successful Communication Basics

Have you ever played the game of telephone with a group of people sitting around a table? The first person at the table has a written message, and the object of the game is for the group to transmit that message accurately to the last person at the table by having each person in turn whisper the contents of the message to the next person in line. The rules are simple: No one other than the first person can see the original written message, and each person must ensure that only the next in line hears the message they whisper. Invariably, the message received by the last person bears little, if any, resemblance to the original message because, even in this controlled setting, a myriad of factors influence how well people send and receive messages.

Sadly, sometimes this type of miscommunication can occur in a project management environment. But don’t worry! This section is here to help. It explores important parts of the communication process, distinguishes different types of communication, and offers suggestions to improve the chances that the message a receiver gets is the one the sender intended to give.

Tip The game of telephone makes for an outstanding, lighthearted icebreaker for a new team or even one that’s already familiar with each other. Try to come up with a message that is somehow related to your project, team, organization, or customer and have fun with it!

Breaking down the communication process

Communication is the transmitting of information from a sender to a receiver. Whenever you communicate, during the life of a project or at any other time, your goal is to ensure that the right person correctly receives your intended message in a timely manner.

Remember The process of transmitting information includes the following components:

  • Message: The thoughts or ideas being transmitted.
  • Sender: The person transmitting the message.
  • Encoded message: The message translated into a language understandable to others (this language may consist of words, pictures, or actions).
  • Medium: The method used to convey the message (we discuss different mediums in detail in the later section “Choosing the Appropriate Medium for Project Communication”).
  • Noise: Anything that hinders successfully transmitting the message (noise may include preconceived notions, biases, difficulty with the language used, personal feelings, nonverbal cues, and emotions).
  • Receiver: The person getting the message.
  • Decoded message: The message translated back into thoughts or ideas.

Depending on the nature of a particular communication, any or all of these elements can affect the chances that the receiver receives the message as intended.

Distinguishing one-way and two-way communication

Certain types of communication are more effective for transmitting particular types of information. The two main types are:

  • One-way communication: Going from the sender to the receiver with no opportunity for clarification or confirmation that the receiver got and correctly understood the intended message. This type of communication can be effective for presenting facts, confirming actions, and sharing messages that have little chance of being misinterpreted.
  • One-way communications are either push or pull:
    • Push: Proactively distributed to particular people; examples include memos, reports, and emails.
    • Pull: Available to people who must access the communications themselves; examples include Internet and intranet sites, knowledge repositories, and message boards.
  • Two-way communication: Going from the sender to the receiver and from the receiver back to the sender to help ensure that the intended audience received and correctly interpreted the message. Examples include face-to-face discussions, phone calls, in-person group meetings, videoconferences, and online instant messaging. Two-way communication is effective for ensuring that more complex content is correctly received and for conveying the sender’s beliefs and feelings about the message.

Can you hear me now? Listening actively

The one skill that most strongly influences the quality of your communications is your ability to listen actively. Although you can assume that the information contained in a message and the format in which it’s presented affect how well that message is received, you can find out whether the recipient actually received the message as you intended by listening carefully to the recipient’s reactions.

Active listening is exploring and discussing a message that’s being sent to help ensure that the message is understood as intended. If you’re sending a message, you should encourage your intended recipient to use active listening techniques to help ensure that they correctly understand your message. If you’re receiving a message, you should use these techniques to verify to yourself that you have correctly received the intended message.

Because listening to and observing your recipient’s response to a message you sent involves information flowing first from you to the recipient and then from the recipient back to you, active listening is, by definition, a form of two-way communication.

Active listening techniques include the following:

  • Visualizing: Forming a mental picture of the content of a message. Forming this picture gives the receiver the opportunity to identify pieces of the message that may be missing or misunderstood, as well as to seek additional information that may improve the overall understanding of the original message.

    Consider that your manager asked you to redesign the layout of your group’s offices in order to create a more open environment that will encourage people to feel more relaxed and to engage in more informal working group discussions. To help clarify what’s expected, you may try to visualize how the office environment will look and how people will behave after the changes in the layout are made. In particular, you may think about the following:

    • Whether you’ll have to use the existing furnishings or you’ll be able to buy new ones
    • Where people might hold informal meetings
    • How much soundproofing partitions of differing heights will provide

    When you try to visualize these different parts of the new office layout, you realize that the following aspects aren’t quite clear to you:

    • Will window offices have couches or just chairs?
    • How many people should be able to sit comfortably in an office?
    • Should you install “white noise” machines?

    As you talk with your supervisor to find answers to your questions, you get a better idea of what they do and don’t want.

  • Paraphrasing: Explaining the message and its implications, as the receiver understands them, back to the sender in words different from the original message. To be most effective, the receiver should repeat the message in their own words to give the sender the best chance of identifying any misinterpretations.

    Consider that your manager asks you to prepare a report of your company’s recent sales activity by the end of the week. Many aspects of this request are unclear, such as the time period the report should cover, the specific time by when the report must be finished, the format in which you should prepare the report, and so forth. To clarify these items, you can paraphrase the request back to your manager as follows:

    “I’d like to confirm that you’re asking me to prepare for you a PowerPoint presentation on the company’s total gross and net sales of Products A, B, and C for the period from January 1 to March 31 of this year and that you’d like me to have it for you by this coming Friday at 5 p.m. Does my understanding align with your expectations?”

  • Checking inferences: Clarifying assumptions and interpretations that the receiver makes about the message received.

    Consider the previous example in which your manager asks you to redesign the layout of your group’s offices. As you start to calculate the number of desks and chairs you’ll need in the new arrangement, you realize you’re assuming that the group will have the same number of people after the move that it has now, before the move. However, instead of making this assumption, you can check with your manager to find out how many people they would like you to consider as you design the new layout.

Remember Active listening is particularly useful in emotionally charged situations, situations in which understanding is critical, situations in which consensus and clarity are desired in resolving conflict, and situations in which trust is sought.

Choosing the Appropriate Medium for Project Communication

When deciding how to communicate with your team and your project’s stakeholders, choosing the right medium is as important as deciding what information to share (check out Chapter 4 for a detailed discussion of project stakeholders). Your choice of medium helps ensure that people get the information they need when they need it.

Project communications come in two forms:

  • Formal: Formal communications are preplanned and conducted in a standard format in accordance with an established schedule. Examples include weekly team meetings and monthly progress reports.
  • Informal: Informal communications occur as people think of information they want to share. These communications occur continuously in the normal course of business. Examples include brief conversations via text message or online chat and spur-of-the-moment emails you fire off during the day.

    Warning Take care not to rely on informal communications to share important information about your project, because these interchanges often involve only a small number of the people who should hear what you have to say. To minimize the chances for misunderstandings among your project’s team members and other stakeholders, follow these guidelines:

    • Confirm in writing any important information you share in informal discussions.
    • Avoid having an informal discussion with only some of the people who are involved in the topic.

Formal and informal communications can be written or oral. The following sections suggest when to use each format and how to make it most effective.

Just the facts: Written reports

Unlike informal oral communication, written reports enable you to present factual data efficiently, choose your words carefully to minimize misunderstandings, provide a historical record of the information you share, and share the same message with a wide audience.

Warning Although written reports have quite a few benefits, they also have some drawbacks that you need to consider:

  • They don’t allow your audience to ask questions to clarify the content, meaning, or implication of your message.
  • With written reports, you can’t verify that your audience received and interpreted your message as you intended.
  • They don’t enable you to pick up nonverbal cues that suggest your audience’s reactions to the message.
  • They don’t support interactive discussion and brainstorming about your message.
  • You may never know whether your audience actually reads the report!

Tip Keep the following pointers in mind to improve the chances that people read and understand your written reports (see the later section “Preparing a Written Project Progress Report” for specifics on writing this special type of communication):

  • Prepare regularly scheduled reports in a standard format. This consistency helps your audience find specific types of information quickly.
  • Stay focused. Preparing several short reports to address different topics is better than combining several topics into one long report. People are more likely to pick up the important information about each topic.
  • Minimize the use of technical jargon and acronyms. If a person is unfamiliar with the language in your report, they’ll miss at least some of your messages.
  • Use written reports to share facts and be sure to identify a person or people the recipient may contact for clarification or further discussion of any information in the reports. Written reports present hard data with minimal subjective interpretation, and they provide a useful, permanent reference. A contact person can address any questions a recipient has about the information or the reasons for sharing it.
  • Clearly describe any actions you want people to take based on information in the report. The more specifically you explain what you want people to do, the more likely they are to do it.
  • Use different approaches to emphasize key information. For example, print key sections in a different color or on colored paper, or mention particularly relevant or important sections in a cover memo. This additional effort increases the chances that your audience will see the report and read it.
  • After you send your report, discuss one or two key points that you addressed in it with people who received it. These follow-up conversations can quickly tell you whether your recipients have read your report.

    When you come across people who clearly haven’t read your report, in addition to following the other suggestions in this section, explain to them the specific parts of the document that are most important for them to review and why. Then tell them that you’d like to set up a follow-up meeting with them to discuss any questions or issues they may have regarding the information contained in those parts of the document.

  • Keep your reports to one page, if possible. If you can’t fit your report on one page, include a short summary (one page or less) at the beginning of the report (check out the nearby sidebar “Keep it short — and that means you!”).

Moving it along: Meetings that work

Few words elicit the same reactions of futility and frustration that the word meeting can provoke. People consider meetings to be everything from the last vestige of interpersonal contact in an increasingly technical society to the biggest time waster in business today.

You’ve probably been in meetings where you wanted to bang your head against the wall. Ever been to a meeting that didn’t start on time? How about a meeting that didn’t have an agenda or didn’t stick to the agenda it did have? Or how about a meeting at which people discussed issues you thought were resolved at a previous meeting? Finally, have you been in a meeting where the same one or two people dominated the entire meeting without regard for anyone else’s desire to contribute?

Remember Meetings don’t have to be painful experiences. If you plan and manage them well, meetings can be effective forms of communication. They can help you find out about other team members’ backgrounds, experiences, and styles; stimulate brainstorming, problem-solving, and decision-making; and provide a forum to explore the reasons for and interpretations of a message.

You can improve your meetings by using the suggestions in the following sections (in addition, check out the later section “Holding Key Project Meetings” for tips on planning different types of meetings).

Planning for a successful meeting

Tip To have a good meeting, you need to do some planning. Keep these pointers in mind as you plan:

  • Clarify the purpose of the meeting. This step helps you ensure that you invite the right people and allows attendees to prepare for the meeting.
  • Decide who needs to attend and why. If you need information, decide who has it, and make sure they attend the meeting. If you want to make decisions at the meeting, decide who has the necessary authority and who needs to be part of the decision-making, and make sure they attend.
  • Decide who doesn’t need to attend and inform them their attendance is optional. It is very frustrating to sit through a meeting when you have nothing valuable to contribute and no good reason for being there. People have plenty of other things to do during their day, so let them know if their attendance is mandatory or optional and let the optional attendees decide for themselves to attend.
  • Give plenty of advance notice of the meeting. This step increases the chances that the people you want to attend will be able to do so.
  • Let the people who should attend the meeting know its purpose. People are more likely to attend a meeting when they understand why their attendance is important.
  • Prepare a written agenda that includes topics and their allotted discussion times. This document helps people see why attending the meeting is worth their time. The agenda is also your guideline for running the meeting.
  • Circulate the written agenda and any background material in advance. Doing so gives everyone time to suggest changes to the agenda and to prepare for the meeting.
  • Keep meetings to one hour or less. You can force people to sit in a room for hours, but you can’t force them to keep their minds on the activities and information at hand for that long. If necessary, schedule several meetings of one hour or less to discuss complex issues or multiple topics. If you absolutely must conduct a meeting for longer than one hour, be sure to plan for breaks to stretch, use the restroom, and refill coffee!

Conducting an efficient meeting

Remember How you conduct the meeting can make or break it. The following tasks are essential for conducting a productive meeting:

  • Start on time, even if people are absent. After people see that you wait for latecomers, everyone will come late!
  • Assign a timekeeper. This person reminds the group when a topic has exceeded its allotted time for discussion.
  • Assign a person to take written minutes of who attended, which items you discussed, and what decisions and assignments the group made. This procedure allows people to review and clarify the information and serves as a reminder of actions to be taken after the meeting.

Tip Aim to assign someone other than yourself to take meeting notes, whenever possible, since it can be difficult for you to effectively facilitate the meeting and also write down notes. You aren’t able to focus all of your attention on either of these tasks.

  • Keep a list of action items that need further exploration, and assign one person to be responsible for each item. This step helps ensure that when you meet to discuss these issues again, you have the right information and people present to resolve them.
  • If you don’t have the right information or the right people to resolve an issue, stop your discussion and put it on the list of action items. Discussing an issue without having the necessary information or the right people present is just wasting everyone’s time.
  • Stick to your agenda. Follow the meeting agenda and be wary of hijackers who can derail your meeting and shift the conversation away from your established topics.
  • End on time. Your meeting attendees may have other commitments that begin when your meeting is supposed to end. Not ending on time causes these people to be late for their next commitments or to leave your meeting before it’s over.

Following up with the last details

Your meeting may be over, but your work isn’t done. Make sure you complete the following post-meeting tasks to get the greatest benefit from the session:

  • Promptly distribute meeting minutes to all attendees. These minutes allow people to reaffirm the information discussed at the meeting when it’s still fresh in their minds, and minutes quickly remind people of their follow-up tasks. Try to distribute the minutes within 24 hours of the meeting, and ask recipients to let you know if they have any corrections or additions.
  • Monitor the status of all action items that are performed after the meeting. Because each action item is itself a mini-project, monitoring its progress increases the chances that people will successfully complete it.

Remember Don’t just talk about the suggestions from the preceding sections for making your meetings more effective. Simply talking about them won’t improve your meetings. Act on them!

Preparing a Written Project Progress Report

The project progress report is a project’s most common written communication. The report reviews activities performed during a performance period and describes the identified risks, the problems encountered, and the corrective actions planned and taken. This report also previews plans for the next period (refer to Chapter 14 for tips on how to choose the length of your project’s performance period — the length of time between performance assessments).

This section helps you identify the audience for your project progress report, provides pointers on what to include in your report, and suggests how to keep that content interesting so it doesn’t put your team to sleep.

Making a list (of names) and checking it twice

A project progress report is a convenient way to keep key stakeholders involved in your project and informed of their responsibilities. Decide who should get regularly scheduled project progress reports by answering the following questions:

  • Who needs to know about your project?
  • Who wants to know about your project?
  • Whom do you want to know about your project?

Remember At a minimum, consider providing project progress reports to your project’s sponsor (your project’s client or customer), project stakeholders, your project champion, others who are helping you on the project, and people who are interested in or will be affected by the project’s results, including your supervisor, executive leadership, and project team members (see Chapter 4 for people who should typically be included in this group).

Knowing what’s hot (and what’s not) in your report

Preparing the project progress report gives you an opportunity to step back and review all aspects of your project so you can recognize accomplishments and identify situations that may require your early intervention. Be sure to include some or all of the following information in your project progress report for each performance period:

  • Activities that were planned to be performed and milestones that were planned to be accomplished: Comparison of actual accomplishments for the reporting period with this information will reveal where performance equaled, exceeded, or failed to meet that planned.
  • Performance highlights: Always begin your report with a summary of project highlights, such as “The planned executive leadership review was successfully conducted on schedule” or “Our client Mary Fisher approved our training outline according to schedule” (just remember to keep it to one page!).
  • Performance details: Describe the activities performed, outcomes achieved, milestones reached, labor hours charged, and non-personnel resource expenditures incurred in detail. For consistency, identify each activity by its work breakdown structure (WBS) code (see Chapter 6 for more on WBS).
  • Problems and issues: Highlight special issues or problems that you encountered during the period and propose any necessary corrective actions.
  • Approved changes to the plan: Report all approved changes to the existing project plan.
  • Risk management status: Update your project risk assessment by reporting on changes in project assumptions, the likelihood of these updated assumptions occurring, and the effect of those updated assumptions on existing project plans (Chapter 10 covers the basics of dealing with risk and uncertainty).
  • Plans for the next period: Summarize major work and accomplishments that you have planned for the next performance period.

Figure 15-1 contains an example of a project progress report format. Although you can expand each section of information, depending on the nature of your project, note that the longer the report is, the less likely your intended audience is to read and understand it.

Table represents an example of a project progress report.

© John Wiley & Sons, Inc.

FIGURE 15-1: An example of a project progress report.

Earning a Pulitzer, or at least writing an interesting report

When you write your project progress report, make sure it’s interesting, relevant, and tells the appropriate people what they need to know. After all, you don’t want your report to end up as a birdcage liner. Use the following tips to improve the quality of your project progress reports:

  • Tailor your reports to the interests and needs of your stakeholders. Provide only the information that your stakeholders want and need. If necessary, prepare separate reports for different stakeholder groups (see Chapter 4 for more on defining your project’s stakeholders).
  • If you’re preparing different progress reports for different stakeholders, prepare the most detailed one first and extract information from that report to produce the others. This approach ensures consistency among the reports and reduces the likelihood that you’ll perform the same work more than once.
  • Produce a project progress report at least once a month, no matter what your stakeholders request. Monitoring and sharing information about project progress less often than once per month significantly increases the chances of major fallout resulting from an unidentified problem. Depending on the size and duration of your project, weekly progress reports may be warranted or expected.
  • Make sure that all product, schedule, and resource information in your report is for the same time period. Accomplishing this may not be easy if you depend on different organization systems for your raw performance data.

    If you track project schedule performance on a system that you maintain yourself, you may be able to produce a status report by the end of the first week after the performance period. However, your organization’s financial system, which you use to track project expenditures, may not generate performance reports for the same period until a month later.

    Address this issue in your project’s start-up phase (see Chapter 13 for suggested start-up activities). Determine your sources for status data, the dates your updated data are available from each source, and the time periods that the data apply to. Then schedule your combined analysis and reporting so that all data describe the same time period.

  • Always compare actual performance with respect to the performance planned for the period. Presenting the information in this format highlights issues that you need to address.
  • Include no surprises. If an element requires prompt action during the performance period (if, say, a key person unexpectedly leaves the project team), immediately tell all the people involved and work to address the problem. A routine project progress report is not the place to introduce impactful news. However, be sure to mention the occurrence and any corrective actions in the progress report to provide a written record.
  • Use your regularly scheduled team meetings to discuss issues and problems that you raise in the project progress report. Discuss any questions people have about the information in the project progress report (however, don’t read verbatim to people from the written report they’ve already received — and hopefully read on their own)!
  • Make your report easy to digest and keep your audience engaged. Settle on a consistent, informative format (bulleted lists are almost always a good touch), don’t ramble, and conclude with a “Next Steps” section.

Holding Key Project Meetings

Active, ongoing support from all major project stakeholders gives you the greatest chance for achieving project success. To gain that support, continually reinforce your project’s vision and your progress toward it, and help your project’s stakeholders understand when and how they can most effectively support your efforts. This section looks more closely at the three types of meetings you might conduct during your project.

Regularly scheduled team meetings

Regularly scheduled team meetings give members an opportunity to share progress and issues and to sustain productive and trusting interpersonal relationships. These meetings also provide an opportunity to reaffirm the project’s focus and to keep team members abreast of activities within and outside the project that affect their work and the project’s ultimate success. Recognizing that most people work on several projects at the same time, these meetings can reinforce the team’s identity and working relationships.

Tip Consult with team members to develop a meeting schedule that’s convenient for as many people as possible. If some people can’t attend in person, try to have them participate in a conference call (see Chapter 18 for more about how you can use technology to support your project).

In addition to following the suggestions for productive meetings in the section “Moving it along: Meetings that work,” observe the following guidelines when planning and conducting regular team meetings:

  • Even though your team meetings are held regularly, before each meeting, prepare a specific agenda, distribute it beforehand, and solicit comments and suggestions.
  • Before the meeting, distribute the project progress report for the most recent performance period (take a look at the earlier section “Preparing a Written Project Progress Report” for details on this report).
  • Distribute any other background information related to topics on the agenda before the meeting.
  • Limit discussions that require more in-depth consideration; deal with them in other forums.
  • Start on time and end on time (yes, we mentioned this earlier in the chapter, but it is important and worth mentioning again!).
  • Prepare and distribute brief minutes of the meeting within 24 hours after its end.

Ad hoc team meetings

Hold ad hoc team meetings to address specific issues that arise during your project. An ad hoc meeting may involve some or all of your team’s members, depending on the topic. Because issues often arise unexpectedly, do the following as you plan an ad hoc meeting:

  • Clarify the issue and what you hope to achieve at your meeting.
  • Identify and invite all people who may be interested in, affected by, or working on the issue.
  • Clearly explain the meeting’s purpose to all meeting invitees.
  • Carefully document all action items that the attendees develop at the meeting, and assign responsibility for their completion.
  • Share the results of an ad hoc meeting with all team members who may be affected by the results, who have an interest in them, and/or whose support you need to implement them.
  • As appropriate, share any information discussed at the meeting with people to whom the information related but who did not attend the meeting, including team members’ functional managers, executive leadership, and others.

Executive leadership progress reviews

An executive leadership progress review is a meeting over which a senior-level manager usually presides, a project manager typically runs, and team members and representatives of all functional areas customarily attend. This review gives you the chance to tell executive leadership about your project’s status, its major accomplishments, and any issues that require their help. The review is also an opportunity for you to note ways to keep the project in line with major organization initiatives.

Remember Take every opportunity to help executive leadership remember why your project is important to them. They may have approved your project only months ago, but chances are your project’s now just one of many activities in your busy organization.

Tip Get the most out of your executive leadership progress review by observing the following tips:

  • Distribute an agenda in advance of your meeting.
  • Identify the interests of your audience and explain how your project is meeting those interests.
  • Keep your presentation short — choose a few key messages and emphasize them.
  • Highlight your key information but be prepared to go into more detail on issues if anyone asks you to do so.
  • Use both text and graphics to convey important information.
  • Start and end on schedule and allow time for questions.
  • Present updated information on project risks and explain how you’re addressing them.
  • Limit the number of presenters to only the key team members, when multiple presenters are required.
  • After the meeting, distribute notes that highlight issues raised and actions that you agreed on during the review.

Preparing a Project Communications Management Plan

With the diversity of stakeholders who will be looking for information about your project and the array of data you’ll be collecting, it’s essential that you prepare a project communications management plan to avoid duplication of effort and to ensure that nothing falls through the cracks.

A project communications management plan is a document that specifies all project communications generated throughout the project, their target audiences, their information content, and their frequency. Prepare an initial version of your project communications management plan in the starting-the-project stage of your project, and update it as needed in the carrying-out-the-work stage (flip to Chapter 1 for details on the distinct stages of a project).

At a minimum, your plan should specify the following for all project communications:

  • Target audience: The people whose information needs are addressed through the project communication (check out Chapter 4 for a discussion of how to identify and classify project stakeholders).
  • Information needs: The information that the target audience wants and/or needs.
  • Information-sharing activity: The specific type of information-sharing activity to be used to transmit information to the target audience (written reports, presentations, and meetings, for example). (Check out the earlier section “Choosing the Appropriate Medium for Project Communication” for more on when to use different types of information-sharing activities.)
  • Content: The specific data to be shared in the project communication.
  • Frequency: When the information-sharing activity occurs (can be regularly scheduled or ad hoc).
  • Data collection: How and when the data for the report are collected.

Relating This Chapter to the PMP Exam and PMBOK 7

Pay special attention to Table 15-1, which notes topics in this chapter that may be addressed on the Project Management Professional (PMP) certification exam and that are included in A Guide to the Project Management Body of Knowledge, 7th Edition (PMBOK 7).

TABLE 15-1 Chapter 15 Topics in Relation to the PMP Exam and PMBOK 7

Topic

Location in This Chapter

Location in PMBOK 7

Comments

Components of the communication process and different types of communication

I Meant What I Said and I Said What I Meant: Successful Communication Basics

2.1.1.4. Engage

4.2.2. Communication Models

Both books identify similar components of the communication process. PMBOK 7 mentions a number of techniques, while this book gives more descriptive information and illustrations.

Selecting the appropriate medium

Choosing the Appropriate Medium for Project Communication,” “Preparing a Written Project Progress Report,” and “Holding Key Project Meetings

4.2.2.2. Effectiveness of Communication Channels

4.4.3. Meetings and Events

4.6.7. Reports

This book identifies the benefits and drawbacks of different types of reporting mechanisms and offers suggestions for improving their effectiveness. PMBOK 7 notes different types of communication approaches and media and emphasizes the importance of preparing a communications strategy.

Form and content of written project reports

Preparing a Written Project Progress Report

4.6.7. Reports

2.7.3. Presenting Information

PMBOK 7 identifies issues to consider when preparing reports, while this book goes into more depth describing different techniques and explaining how to apply them.

What to include in a plan to meet audience information needs

Preparing a Project Communications Management Plan

2.4,.4. Communication

2.7. Measurement Performance Domain

4.6.3. Plans

PMBOK 7 provides an extensive list of information concerning the preparation of reports that can be included in a communications management plan. This book focuses more on the types of information required to guide the preparation and distribution of reports.