Chapter 4
Project Design and Contract and Bid Documents for a Project

4.1 Introduction

The discussion in Chapter 1 included a definition and description of “the people involved in a construction project.” This chapter will focus on the evolution and development of the design for a project, and the contract and bid documents that are used by the architect-engineer to communicate the design. As those topics are developed, the roles of some of the people involved—owner, architect-engineer, construction manager, prime contractor, subcontractor, and vendor—will be further discussed in the context of the evolution of the design of a construction project and in terms of the development and use of the contract and bid documents for the project.

4.2 The Architect-Engineer

As was noted in Chapter 1, construction projects are designed by licensed professional designers, architects, and/or engineers. The nature of the project and the preference of the owner determine the division of responsibilities between these two design professionals. As a general rule, building projects are designed by architects or have an architect as the primary designer, and civil, structural, electrical, and mechanical engineering services are provided to the architect by consulting engineers as needed.

Highways, bridges, and heavy construction projects, as well as utility and industrial projects, are typically designed with an engineer as the primary designer, and architectural services are included as may be needed. Such projects are typically referred to as engineered projects or engineered construction.

Additionally, there are a number of firms that designate themselves as architect-engineers that perform planning and design work in both classifications of construction work. In this text, the term architect-engineer is used to designate the organization, person, firm, or team that performs the project design, whether it be architectural, engineering, or a combination of both, in composition.

The architect-engineer can occupy a variety of positions contractually relative to the owner and contractor on a project. Typical among these are the following.

4.2.1 Owner-Client

In the traditional project delivery method, the architect-engineer is a private professional design firm that enters a contract with the owner to perform professional design services, as depicted in Figure 4.1.

c04f001

Figure 4.1 Contractual Connections and Hierarchy of Contracts on a Typical Building Construction Project

Most often, the construction is performed by a single prime contractor or by a number of separate prime contractors who also have a contract with the owner. In this project delivery method, there is no privity of contract between the prime contractor and the architect-engineer.

4.2.2 In-House Capability

Owners sometimes have their own in-house design capability. For example, some large industrial firms and petrochemical firms, as well as many public agencies that have ongoing construction needs, maintain their own design departments. In these firms, the architect-engineer is an integral part of the owner's organization. Construction is usually accomplished by an independent construction firm or firms, who enter a contract with the owner in the single-contract system or the separate-contracts system. However, some large firms and agencies also maintain in-house construction capability for the construction of their projects.

4.2.3 Design-Build

In this project delivery method, the owner contracts with a single entity for both the design and construction of the project. This project delivery method is very popular today and is being employed by an increasing number of owners. Although the architect-engineer and the contractor may be related in a variety of ways on design-build projects, four of the most commonplace arrangements are:

  1. An architect-engineer design firm may maintain in-house construction capability alongside its design staff.
  2. A contractor may have in-house design capability with architects and/or engineers on its staff.
  3. The contractor and architect-engineer, both functioning as separate and independent firms, may form a joint venture design-build firm for the performance of a given project or contract.

4.2.4 Construction Management

The owner may enter a contract with a construction management (CM) firm separate from the contracts that the owner has with the architect-engineer and with the prime contractor, in an arrangement referred to as construction manager as agent, construction management agency, or construction management at risk (CMAR).

In the construction management agency arrangement, the owner is generally seeking the input and advice of the construction manager and is looking to the construction manager to represent the owner's best interests throughout the evolution of the design, as well as after the design is complete and when a contract has been awarded to a contractor. The contract between the owner and the construction manager, as well as the contract between the owner and the architect-engineer, will call for extensive collaboration and cooperation between the architect-engineer and the construction manager in the evolution of the design and the production of the contract and bid documents, as the owner seeks to ensure that his best interests are maximized throughout the process. During the construction process, and often extending through the warranty period following completion of the project, the owner's contract with the construction manager calls for the construction manager to continue to provide guidance, advice, and counsel to the owner.

The owner may also enter a contract with a construction manager, which is a CMAR arrangement. In this form of CM contract, the construction manager takes contractual responsibility for completion of the contract in accord with the provisions of the contract documents for the project, and is further bound to complete the project not later than a specified date, and for not more than a specified sum. In this arrangement, the construction manager typically will provide input during project design as well. The separate-contracts method of contracting is commonly used in this arrangement.

Both construction manager as agent and construction manager at risk, as well as single-contract and separate-contract delivery methods, are more fully discussed and are illustrated in Chapter 1.

4.2.5 Design-Manage

In this arrangement, the owner enters a single contract for both design and CM services. A design-manage firm may perform both the design and CM functions, or the architect-engineer can be a corporate affiliate or subsidiary of the construction manager, or there can be a joint venture between the architect-engineer and the construction manager.

4.3 Designers' Professional Associations

Several associations of designers of construction projects provide a variety of very valuable services for architect-engineer professionals. These associations provide ethical, professional, and business guidance to the individual architect-engineer. Among these professional organizations are the American Institute of Architects (AIA), National Society of Professional Engineers (NSPE), Construction Management Association of America (CMAA), and the American Council of Engineering Companies (ACEC). These professional associations serve in a number of ways to promote and protect the image and reputation of the design profession and to assist their members in achieving higher professional, ethical, business, and economic standards. Additionally, these professional associations produce and publish a variety of “standard form documents” that are very widely utilized in professional practice.

4.4 Selection of the Architect-Engineer

When the owner has in-house design capability, there is no need for a selection process to choose an architect-engineer to design a project for the owner. Otherwise, and for most construction projects, some form of selection process must be followed. Four options that the owner may exercise when selecting a design firm are:

  1. The owner seeking out a firm, or a number of firms, and negotiating a contract with the firm of choice.
  2. A design competition wherein interested firms present designs and qualifications to the owner, who then selects a designer with whom he will enter a contract.
  3. Call for submissions from interested designers with selection based on professional qualifications alone.
  4. Call for submissions, which include designation of fees that become a part of the evaluation criteria.
  5. Call for bids for professional services and selection on the basis of price alone.

Traditionally, professional societies of architects and engineers have opposed competitive bidding and price competition as a basis for selecting firms to perform professional design services. A number of professional associations have included in their codes of ethics prohibitions against such competitive bidding by their members. These organizations advocate that design professionals should be selected by the owner, based on their qualifications and competence, with the professional fee to be determined through negotiation. Objection to competitive bidding for planning and design services is voiced on the grounds that it is not in the best interest of the client or the public.

However, in 1978, the U.S. Supreme Court ruled that the National Society of Professional Engineers' ethical ban on competitive bidding for engineering services was not permissible under the Sherman Antitrust Act. As a result of this decision, the professional societies for designers, to which almost all designers belong, may not prohibit competitive bidding procedures if those in practice wish to engage in such methods. Consequently, it is not now considered unethical to submit or to invite such bids. Professional societies, however, may encourage owners to continue using the traditional selection and fee-setting procedures. Professional designers are not required to submit bids, and owners may, if they wish, shun competitive procedures in their procurement of professional design services.

Most agencies of the federal government are prohibited from using competitive bidding in the procurement of design services by the Brooks Act (1972). This act mandates the negotiation of design contracts at fair and reasonable prices on the basis of demonstrated competence and qualifications for the type of professional service required. Many states have passed legislation with provisions similar to those in the Brooks Act, that set forth professional selection and negotiation procedures for state-financed projects.

Nevertheless, recent years have witnessed a pronounced shift away from the traditional selection of design professionals exclusively on the basis of qualifications. Following the 1978 Supreme Court decision on competitive bidding by design professionals, there has been a substantial movement by public owners, other than the federal and some state governments, toward the use of price as one of the criteria to be utilized in the selection of architect-engineer firms. The procurement codes of many state and local governments now make the design fee an integral and important component of the selection process. Certain public agencies presently issue fee schedules that apply to their selection of design professionals. In the private sector, the amount of the designer's professional fee usually plays an important role in the procedure for the owner's selection of a designer.

Additionally, there are now requirements that certain designated construction design contracts be set aside for small businesses. Such “set-aside projects” frequently require a specified maximum estimated professional fee or a specified maximum estimated project cost. Small design businesses are identified by the U.S. Small Business Administration as those with annual gross billings of less than a specified maximum average value.

4.5 Services Provided by the Architect-Engineer

The scope of services to be provided by the architect-engineer is subject to considerable variation, depending on the needs and wishes of the owner, and as formalized in the owner-designer contract. Basic to such services, however, are the following:

  • Analyzing and ascertaining the needs of the owner.
  • Developing a design that will meet the needs of the owner within the owner's budget.
  • Preparing the contract and bid documents for the project.
  • Assisting the owner in the selection of a contractor.
  • Usually, representing the interests of the owner during the construction process.
  • Sometimes the architect-engineer firm is also called upon in its contract with the owner to assist the owner with warranty matters following the conclusion of the construction contract.

The function of analyzing the needs of the owner is usually referred to as programming. The architect-engineer assists the owner in the development of a complete and detailed itemization of the owner's needs and wishes. The design produced by the architect-engineer will then address those items that have been listed in the program.

The design produced by the architect-engineer will need to be constructed within the budget the owner has established. In this regard, an early action in the initiation of a proposed construction project is the architect-owner's assisting the owner with the establishment of his budget, as well as the formulation of an estimate of the probable final cost of the project. Such conceptual and feasibility cost estimates (discussed more fully in Chapter 5) are standard procedure for most construction projects and provide the owner with invaluable information concerning necessary project financing. A conceptual cost estimate is the usual starting point for a construction project and is often made using the standards manual issued by the American Society of Professional Estimators. In this ease, the estimating guidelines are based on the standardized system developed by the Construction Specifications Institute (CSI) and called “Construction Specifications Institute MasterFormat 2014,” as shown in Appendix C of this text.

Additionally, the architect-engineer firm may utilize other construction cost summaries such as those produced by the RSMeans Company, the Frank Walker Company, or others. In addition, architect-engineers sometimes engage the services of contractors on a paid consulting basis to provide conceptual and preliminary estimates for use by the owner and the design team as the design is produced.

Whether the project delivery method is competitive bid or negotiated, the architect-engineer's contract with the owner will typically include a requirement that he assist the owner in receiving contractors' proposals, analyzing the proposals and other submittal data, evaluating contractors' credentials and references, and selecting the contractor.

The scope of services provided to the owner by the architect-engineer during construction of the project depends on the needs and preferences of the owner. While the responsibility of the architect-engineer to the owner may cease when the contract documents are finalized and delivered, the owner may require full construction-phase services, including project inspection or observation during construction, the checking of shop drawings, the approval of periodic payments to the contractor, the issuance of a certificate of completion, the processing of change orders, and project closeout. Additionally, owners frequently include provisions in the designer's contract whereby the architect-engineer will assist the owner with administration of warranty issues during the contractor's warranty period for the project.

Although the architect-engineer is not usually a party to the construction contract between the owner and contractor, the contract between the owner and the architect-engineer often conveys certain powers to the architect-engineer such as the authority to act on behalf of the owner, to decide contract interpretation questions, judge performance, condemn defective work, and stop field operations under certain circumstances.

A standard form of design contract between the architect and owner, published by the American Institute of Architects, AIA Document B101–2007 “Standard Form of Agreement between Owner and Architect,” which is widely used for building construction, is reproduced in Appendix B. It should be noted that this and other standard forms and documents reproduced in this text are for illustrative purposes only. Because AIA documents are revised from time to time, users should obtain from the AIA the current editions of the documents reproduced herein.

4.6 Fee for Design Services

When an architect-engineer, acting as a private practitioner, performs a design service for a client, the professional fee may be determined in a number of different ways. The most commonly used are the following:

  1. Percentage of construction cost.
  2. Multiple of salary cost.
  3. Multiple of salary cost plus nonsalary expense.
  4. Fixed lump-sum fee.
  5. Total expense plus professional fee.
  6. Hourly or per diem charge plus expenses.

The basic elements of the agreement as previously described in the clauses, are typically supplemented with additional language relating to compensation for the architect-engineer's expenses such as travel, document reproduction, and so on.

Fees for the design professional on publicly financed projects are often subject to statutory or administrative conditions and limitations. There are instances where the design contract between the owner and architect-engineer provides that payment of the fee is contingent in some way on the project cost being within the budget established by the owner. For example, such contracts may provide that the architect-engineer shall not be entitled to any increase in fee when project redesign is required to keep construction costs within an agreed-upon budget amount. It is common for design contracts to provide that the architect-engineer's fee be paid in installments, as designated phases of the designer's services are completed. It should be noted that contracts between the owner and the architect-engineer in private construction projects often contain provisions similar to these as well.

4.7 Responsibility to the Owner

Although the owner and architect-engineer are usually joined together by contract, their exact relationship depends on the duties being performed by the architect-engineer as defined in the contract. In the preparation of bid documents and contract documents, the architect-engineer firm functions primarily as an independent contractor; however, during construction of the project, its role is that of being an agent of the owner, acting to ensure that the contractor fulfills all of the requirements set forth in the contract documents. Throughout, the architect-engineer has a fiduciary obligation to its client requiring fairness, trust, and loyalty to the owner. Additionally, the design professional must avoid any conflict of interest that could work to the disadvantage of the owner.

The common-law standard of care applicable to architect-engineers is the same as that for other licensed professionals such as doctors and lawyers. The services of experts are sought by the public because of the special skills which they possess. These professionals have a duty to exercise ordinary skill and competence in carrying out their function, and a failure to discharge this duty will subject them to liability for negligence.

As a professional, the architect-engineer is required to exercise care and diligence in carrying out its responsibilities. Learning, skill, and experience are expected to the degree customarily regarded as being necessary and sufficient for the usual practice of that profession. By the contract of employment, the architect-engineer implies that it possesses the ordinary skill and ability for a person acting in this capacity, and that it will carry out the design with promptness and a reasonable exactness of performance.

The designer is responsible for the adequacy of the materials, components, and systems that are selected and specified. The architect-engineer also bears the responsibility for preparing design documents that are in conformance with applicable building codes, setback requirements, zoning regulations, and environmental regulations. It is not expected that the architect-engineer produce a perfect design, or even satisfactory end results. However, the law expects the design professional to carry out the tasks it has undertaken with reasonable standards of care, skill, and performance. If the owner suffers loss or injury because this standard is not met, the architect-engineer is liable for damage or injury that may result.

Architect-engineer liability to the owner may arise through breach of contract or through tort responsibility. More specifically, the designer can be held liable to its client for violation of a specific contract provision, from an express or implied warranty in the design contract, or from negligence in the performance of the architect-engineer's duties under the contract. If the design professional is found to have given an express or implied warranty regarding the sufficiency of the design, or indicating that the structure would be reasonably suitable for the purpose intended, then the architect-engineer is strictly liable for damages caused by a breach of the warranty, and it is not necessary that the owner prove any specific negligence. Although legal interpretations vary somewhat, most jurisdictions hold that there is no implied warranty by design professionals that their plans and specifications are adequate for a specific purpose, except as previously noted. According to most courts, an architect-engineer warrants its work only to the extent that it has used the customary skill of the profession.

Although the architect-engineer firm can be held responsible for lack of care, diligence, or skill, it is not normally considered to be negligent because of errors in judgment. However, there is a definite trend in the courts toward expecting a greater degree of perfection and foresight on the part of architect-engineers and holding these parties responsible for their negligence. In addition, if the architect-engineer represents itself to be a specialist in a certain type of work, it will likely be held to a greater degree of competence and care than would a general practitioner.

If the architect-engineer selects and employs consultants such as electrical engineers, mechanical engineers, acoustical engineers, or landscape architects to design or advise concerning specialized portions of the project, as he almost always does, the architect-engineer remains responsible to the owner for the overall adequacy of the completed design. In this regard, the design professional has a nondelegable duty to the owner and promises by implication that all services will be properly performed. If a consultant's work should prove to be faulty, the architect-engineer is liable to the owner for any resulting damages. The consultant is, in turn, accountable to the architect-engineer for whom the special work was done.

If the architect-engineer's contract with the owner includes provision for inspecting or observing the work of the contractor during construction, it has the duty to ensure that the contractor materially complies with the drawings and specifications and fulfills the requirements of the contract documents. It has the responsibility to see that the owner receives substantially the structure called for by the construction contract.

Design professionals sometimes include exculpatory clauses, which are also known as “hold harmless” clauses, in their design contracts in an attempt to limit their professional liability. Some of these clauses provide that the architect-engineer will not be liable to the owner for damages resulting from negligence of the designer. Other clauses limit the potential liability of the architect-engineer to a specific amount. However, such agreements generally apply only to parties who sign them and cannot limit the architect-engineer's liability to third parties.

Additionally, with regard to exculpatory language in design contracts, certain contractual exemptions from liability have been declared invalid by state statutes, and the general enforceability of such contract clauses is uncertain at best. Courts favor strict interpretation of such exculpatory clauses and seek to avoid contract provisions that excuse parties from their own fault or negligence.

A relatively new approach called a contingency reserve provides that the owner agrees to establish a fund of some specific percentage (perhaps 5 percent) of the construction cost of the project. This reserve is to be used by the owner as necessary to pay the contractor for expenses arising from minor design errors or omissions. The owner agrees not to bring any action against the architect-engineer for additional construction costs within the limits of the contingency reserve, even though they may be the fault of the architect-engineer.

4.8 Liability to Third Persons

Legislative law now generally recognizes that an architect-engineer can be held liable to a third party if bodily injury or property damage is caused to that party by reason of negligence or failure in duty of the designer. Common laws have long held architect-engineers to a similar standard. The law of negligence requires a professional to exercise reasonable care to protect third parties during the performance of the professional's work. In addition, the architect-engineer may in some instances be held liable to third parties for economic loss suffered as a result of its negligence. In this context, third party refers to any party who does not have privity to the design contract between the architect-engineer and the owner.

Third-party liability can arise from a project either during its construction or after its acceptance and occupancy by the owner. Under this concept of liability, architect-engineers now find themselves subject to damage claims by contractors, subcontractors, construction workers, sureties, suppliers, lenders, and outsiders lawfully on the project premises, where the negligent performance of duty by the architect-engineer allegedly caused or contributed to harm or injury.

Recent years have seen the design professional increasingly held liable to general contractors and subcontractors for economic loss caused by the architect-engineer's negligence. Architect-engineers have been held liable for a variety of injuries suffered by workers during construction and by members of the general public after project completion. There have been several cases in which an architect-engineer firm, being responsible in its contract with the owner for job inspection, has been judged responsible for the safety of the work and has been made liable for damages when it failed to take corrective measures, if it knew or should have known of a dangerous job condition. Negligence suits stemming from injuries suffered on completed projects have been filed by parties whose injuries were caused by alleged improper or inadequate design. An architect-engineer's continuing liability for completed projects is often limited by special statutes of limitations, a subject discussed in the following section.

In any discussion of tort liability arising out of negligence, the matter of strict liability arises. There is an increasing trend in this country toward imposing strict liability, on the basis of implied warranty, for injuries caused to the user or consumer of mass-produced products. Product liability, or strict liability, refers to liability without proof of fault; that is, liability for damages is not based on a demonstration of negligence on the part of the producer of the goods. Under this theory, the person suffering injury or damages can receive compensation if it can be proved the product was defective and this defect caused the injury or other loss. The courts have not yet applied product liability to architect-engineers or construction managers, although strict liability has been applied to the manufacturers of prefabricated buildings and to builder-vendors who produced and sold homes that were shown to be defective. These findings were based on implied warranties of workmanship and habitability.

4.9 Statutes of Limitations

Most states now have special statutes of limitations that apply to the accountability for damages that arise out of a defective and unsafe condition created as the result of an improvement to real property. These statutes apply to architect-engineers and construction contractors and establish a time beyond which these parties are no longer liable for damages arising out of completed construction projects. Such statutes provide that the time during which the architect-engineer and contractor remain liable begins with the substantial completion of the work or acceptance of the work by the owner. These statutory periods vary from 4 to 20 years in the various states, with the average being about 7 years.

In those states without such statutes, the architect-engineer and contractor must rely on the states' general statutes of limitations. The time period within which a given action must be brought under these statutes varies. However, a typical statute provides for a three-year period for torts (negligence) and a six-year period for breach of contract. A serious question concerning these general statutes of limitations arises with regard to when the statutory time begins. The usual provision for negligence suits against architect-engineers and contractors is that time starts when the cause of action accrues. The right of the owner to sue for breach of contract ordinarily begins when the work is accepted. However, there can be exceptions when the construction defect is concealed. Such defects are commonly referred to as concealed defects or latent defects.

The result of these conditions is that in those states without special statutes of limitations, the architect-engineer and contractor are indefinitely vulnerable to suits charging negligence or breach of contract. In this regard, it must be noted that some of these special statutes of limitations have been declared unconstitutional in recent years.

In general, it can be said that architect-engineers must be aware of the liability that they assume in the performance of their design work. As a matter of fact, most architect-engineer firms carry professional liability insurance, which is commonly referred to as errors and omissions insurance to assist them in managing this risk.

4.10 Contractor Input into Design

Although construction contracting firms do not typically think of themselves as participants in the design process, increasingly the experience and expertise of constructors are being sought for use by owners and designers. It has repeatedly been shown that construction contractors are a valuable addition to the design team.

In the traditional and still predominant linear construction process, there is usually no input from the contractor into the design process. There are occasional instances where the owner or architect-engineer obtains the consultation services of a contractor during the planning and design phases, but this is much more the exception than the rule. However, extensive contractor input into design is a normal part of design-construct, construction management, and design-manage contracts, where the team concept prevails.

Where the input of experienced construction people into the planning and design of the project is a part of the procedure, the contractor typically enters the process at an early date. The constructor does not perform the design but provides continuing advice concerning general site planning, local work practices, labor availability and costs, material availability, delivery times, and alternative work methods and procedures. The contractor prepares cost estimates and construction and procurement schedules and participates in the value-engineering program. The contractor's knowledge of prices and the availability of materials and services is an invaluable source of information to those making design decisions. As one who is familiar with performance, maintenance, and installation costs, the contractor can help assess life-cycle costs and benefits. Additionally, as one who is familiar with construction procedures and details, the contractor can provide input regarding constructability, and/or the most effective use of various materials, methods, and details to best advantage. Under the right circumstances, contractor input into the design process can result in substantial benefits of all kinds to the owner.

4.11 Project Description—Communicating the Design

The nature and extent of the construction to be performed, the materials to be provided, and the quality of workmanship required for the project are described by the drawings and specifications. Complementing each other very closely, the drawings and specifications present a complete description of the project and the work to be done. The drawings portray pictorially the extent and arrangement of all of the components of the structure. The specifications describe in writing the quality of the materials and the standards of workmanship required. These documents serve four important functions. First, they are the communication tools with which the design of the project is articulated to the owner, to the contractor, and to all other parties associated with the project. Second, they define the entire project and all that is to be built, and thereby serve as a basis for competitive bidding or contract negotiation. Thus, they become the basis for formation of the construction contract. Third, they serve as contract administration documents during the construction phase, describing the work to be accomplished and defining the rights and duties of the participants. Fourth, they are component elements of the contract documents for the project (as discussed in the paragraphs that follow), that define and describe the materials to be used (concrete, brick, steel, wood, gypsum products, etc.) in terms of comprehensive reference standards that have been developed, which define their key properties. The drawings and specifications will be further discussed in sections to follow, in the context of being components of the complete set of contract documents for a project.

4.12 Announcing the Project to Contractors

When the architect-engineer has completed the design and the owner has approved, the project will be announced to construction contractors, meaning that the bid documents and contract documents (to be more fully discussed in sections that follow) will be made available to contractors, and contractors will be invited to prepare and submit proposals for negotiation or competitive bidding. Generally speaking, there are two methods by which the project may be announced to contractors: advertisement for bids and an invitation to bid.

4.12.1 Advertisement for Bids

The advertisement for bids serves as public notice to all contractors that those who are interested and can qualify are being sought to submit proposals for the construction of the project. This method of making contractors aware of the project may be used at the election of the owner on private projects. On public projects, statutory requirements typically indicate that this method must be employed.

Advertisements for bid are typically placed in newspapers, magazines, and in design and construction professional journals. They are listed with contractor news services such as the Dodge Reports, and are furnished to contractor professional associations such as the Associated General Contractors (AGC), Associated Builders and Contractors (ABC), and others. The intent is to place the advertisements for bids wherever the owner and architect-engineer believe contractors may see them and to attain broad distribution so that any contractors who are interested can learn of the project and determine whether they wish to prepare and submit a proposal.

The advertisement for bids typically is included in the bid documents that the architect-engineer makes available to the contractors. The bid documents and the other elements that comprise the set of bid documents are further discussed in the sections that follow.

The advertisement for bids may also be referred to as a notice to bidders or as public notice. Additionally, in a semantic twist, the advertisement for bids may also sometimes be referred to as an invitation to bid. Even when this term is used, this method of making contractors aware of the project is distinguished from the invitation to bid, as it will be discussed in a following section, by the fact that it is public notice to any and all interested contractors.

The advertisement for bids usually contains basic information regarding the name of the owner and architect-engineer, the location of the project, approximate size of the project, and a general description of the scope of work.

Also included is information regarding the procedure for contractors' obtaining the bid documents and contract documents, and reference to deposits that may be required, along with a notation indicating whether deposits are refundable. The expected start date for the project, along with its duration, which is the amount of time that has been allocated for the contractor's completion of all contract requirements, will typically be included. The contract system or project delivery method is described, along with the date, time, and place when proposals are due. Additionally, requirements for bonds, and any prequalifications that the owner and architect-engineer may have established, will be set forth. Instructions and procedures for contractors' obtaining bid documents and contract documents are included. The advertisement will also typically include a statement reserving the owner's right to reject any and all bids.

In addition, the advertisement for bids will usually contain a general description of materials and construction trades to be included in the project. This may take the form of a listing, or this information may be conveyed in terms of divisions of the Construction Specifications Institute (CSI) divisions and/or division numbers that are applicable.

Figure 4.2 illustrates an advertisement for bids for a building construction project, and Figure 4.3 provides an example of an advertisement for bids for an engineered construction project.

c04f002

Figure 4.2 Advertisement for Bids for a Building Construction Project

c04f003

Figure 4.3 Advertisement for Bids for an Engineered Construction Project

4.12.2 Invitation to Bid

The invitation to bid is utilized by the owner and architect-engineer when they wish to notify contractors, whom they have preselected, of the existence of the project and of the fact that they and selected others are being invited to submit proposals. Invitations to bid, as defined here, are typically prohibited by statutory stipulations that regulate contract formation in public construction work. However, they are legal for use on private construction projects and are utilized when the owner and architect-engineer have preselected or have prequalified certain contractors that they wish to invite to submit proposals. When this method is employed, there is typically a stipulation in the invitation and/or in the instructions to bidders, that only those contractors who have been invited may submit proposals to be considered for the project. The invitation to bid typically also contains the same kind of basic information about the project, and the contracting method, etc. as described above for the advertisement for bids.

4.13 Project Manual

The architect-engineer commonly assembles the bid documents and the contract documents into a book or binding, which is referred to as the project manual. This manual, along with the drawings for the project, is what the contractor will receive when he contacts the architect-engineer and requests a copy of the bid documents and contract documents for the project.

This document is sometimes referred to as the specifications, and contractors frequently say they are requesting the “drawings and specifications” from the designer. When this vernacular is employed, it should be remembered that the specifications are a component of the contract documents that are bound into the project manual. To facilitate the distinction, the term technical specifications is sometimes utilized for the specifications as a component of the contract documents.

4.14 Bid Documents

On a competitive bid project, the architect-engineer will typically produce and publish a set of documents referred to as the bid documents for the project. These documents usually include the advertisement for bids or the invitation to bid, along with the instructions to bidders and the proposal form. These documents are graphically depicted in Figure 4.4.

c04f004

Figure 4.4 Bid Documents and Contract Documents for a Construction Project

The advertisement for bids and the invitation to bid were discussed in preceding sections. The sections that follow will discuss the instructions to bidders and the proposal form.

4.15 Instructions to Bidders

For competitive bidding to be a valid procedure, all competitors must bid under exactly the same conditions for an identical package of work. This requires that a set bidding procedure be established and all bidders be required to conform.

Consequently, when competitive proposals are requested, a considerable amount of information concerning the technicalities of the bidding process must be communicated to the contractors involved. This information usually comprises one of the first divisions of the project manual and is designated as instructions to bidders. These instructions review the requirements that the owner or contracting authority has established for the form and content of the bids, and also prescribe certain procedures with which the bidding contractors are required to conform. This document, for example, states conditions pertaining to the form of the bid, where and when it must be delivered, bid security required (see Chapter 5), and information concerning late bids and bids submitted by mail, telegram, or e-mail. A contractor's failure to comply with any stipulation of the instructions to bidders can result in a contractor's bid not being accepted.

Clauses are commonly included that give the owner the right to reject any or all bids, to postpone the date of bid opening, and to exercise many prerogatives in the selection of the successful bidder. An example of instructions to bidders is contained in Appendix A. Standard forms of instructions to bidders are used by many public agencies, many of whom have developed their own form of these documents. The American Institute of Architects has developed a standard form of instructions to bidders. However, standard sets of instructions are designed for general use and do not normally provide all of the information peculiar to a specific project that would be required by prospective bidders. Consequently, supplementary instructions or modifications are customary, or reference is made to certain specific information of interest to bidders already contained elsewhere, such as in the advertisement or invitation to bid. Appendix E is a set of supplementary conditions, which demonstrates this fact.

4.16 Contract Documents

The contract documents for a project are the set of documents that together comprise the contract for construction. These documents are typically prepared by the architect-engineer under the terms of the designer's contract with the owner. Included in the set of contract documents as defined by the architect-engineer are the following: conditions of the contract, drawings, specifications, addenda, alternates, agreement, and modifications to the contract. No one of these comprises the contract for construction; rather, the set of all of these documents defines the contract for construction of the project. Figure 4.4 graphically depicts these documents.

4.16.1 Conditions of the Contract

The conditions of the contract define and describe the administrative and operational elements of the contract. From the definitions of the parties involved and their roles and responsibilities, to the closeout and termination of the contract, all operational and administrative aspects of the project are set forth.

The conditions of the contract typically exist in several elements: the general conditions of the contract for construction, followed by some combination of modifications to the general conditions, supplementary conditions, and special conditions. The general conditions are frequently in the form of a standard form document, as produced by one of the professional associations for architect-engineers.

For building construction projects, documents published by the AIA are frequently utilized by the architect as contract documents. For example, AIA Document A201–2007, “General Conditions of the Contract for Construction,” is frequently utilized as the general conditions, or this document may be modified or amended to structure the general conditions as the architect wishes. This document is reproduced in Appendix D in this text.

It should be noted that this and other standard forms and documents reproduced in this text are for illustrative purposes only. Because AIA documents are revised from time to time, and because the documents included in this book are samples and included for illustrative purposes only, users should obtain from the AIA the current editions of the documents reproduced herein.

4.16.2 Drawings

The drawings, also referred to as the working drawings, portray in graphic form all of the elements of the design. The drawings are considered to be a working pair with the specifications, and these two documents communicate and convey the design of the architect-engineer.

The drawings depict, with line drawings and dimensions, each component element of the design. The drawings contain a variety of views such as perspective, plan, elevation, and section views of the building and all of its component parts. They are typically divided into sections such as plot plan, foundation, architectural, structural, electrical, mechanical, and plumbing. Additionally, the drawings typically include sheets of details, sections, and schedules (for items such as windows and doors), and commonly include written “notes” as well.

The drawings may be produced on paper or on mylar, and are reproduced as blueline or blackline prints on paper. Alternately, the drawings may be produced and conveyed electronically in the form of computer-aided design and drafting (CADD) or building information model (BIM) files. They may be made available to contractors in the form of “hard-copy” paper drawings or electronic files, or they may be filed on a secure web site for reference and use by contractors.

4.16.3 Specifications

Closely complementing the drawings, the specifications written by the architect-engineer for a project provide a written description of the work. They define the quality of all materials to be used in the project, and the standards of workmanship to be provided in the construction of the project.

On building construction projects, the specifications are frequently organized in accord with the divisions and subdivisions of the CSI format. The CSI MasterFormat, with its standard named and numbered sections, is included as Appendix C in this book.

Specification language, the manner in which the architect-engineer goes about calling out and establishing quality standards for the materials and products for use in the structure being designed, is described as being “open” or “closed.” Open specification language is used in both private and public projects, while closed specifications, also referred to as proprietary specifications, are often prohibited by statute for use on public projects and therefore are used primarily on private projects.

4.16.3.1 Open Specifications

Open specifications for materials are those that describe the characteristics and attributes of materials and equipment to be incorporated in the project in generic terms, which establish the quality required in the material by the designer in terms of standardized industry generic language, compliance with industry standards, and criteria that can be verified by standardized testing, which will fit or apply to a number of brand names or manufacturers. Commonplace examples include such entries as, “all portland cement used for concrete on the project shall comply with ASTM Standard C150,” or “softwood plywood to be used for roof sheathing shall bear the recognizable grade stamp of the American Plywood Association and its Product Standard 1, and shall be 3/4 thick, and in a grade of C-D with exterior adhesive.” Designers establish the structural, appearance, or performance attributes of the material or product and/or require its compliance with recognized industry standards, and the contractor takes price quotations from, and eventually purchases the product from, distributors or vendors who can supply a product that fits the descriptive requirements.

4.16.3.2 Closed Specifications

A second method that designers may employ to establish a desired level of material quality is the use of a closed specification, also known as a proprietary specification. In this type of specification entry, the quality requirement established by the designer is established by listing a specific brand-identified product, sometimes including model name and/or model number. In addition, sometimes designers will write the specification language in such a way that only the product made by the supplier whom they have chosen can satisfy the specification language.

Many public bodies do not allow the use of closed specification entries on the specifications relating to the design of projects they will construct. Open specifications are required, in the interest of avoiding favoritism and promotion of fair trade and open competition.

Sometimes, especially in public construction, the designer will name a proprietary product in the specification, and then will convert the specification entry into an open specification with suitable wording in the project specifications. One way to achieve an open specification is to follow a specification for a manufacturer or brand name, a proprietary specification, with the words “or approved equal.”

The purpose of an “or-equal” provision is to enable an alternative material or product to be used without adversely affecting quality. This, then, allows an owner to realize the full economic benefit of competitive bidding and contractor expertise. The primary problem with the use of the or-equal provision is the determination of what constitutes an equal, as well as the timing of the making of that determination. It is unusual for comparable products of different manufacturers to be identical in every respect. Different brand-name items, equally suitable for some particular application, will usually differ in certain respects.

Usually, in the context of an or-equal provision, a substitute need not be identical in every respect to the product specified as a standard of quality. A substitute may be equal but be different in appearance, size, configuration, or design. The equality of an alternative product is established on the basis of the quality and performance of the substitute, as compared to the brand-name product specified. The equality of substitutes proposed by the general contractor or a subcontractor is decided by the architect-engineer or owner. For each proposed substitution, samples, descriptive and technical data, test reports, and other information typically must be submitted by the contractor as a means of demonstrating equality. Even though the or-equal clause is useful in allowing substitutions when cost savings are possible, or when the availability of materials specified is uncertain, this provision has been and continues to be troublesome for both the architect-engineer and the contractor.

Because it is often not possible to obtain approval for a material substitution before proposals are submitted on a competitively bid project when this specification language is employed, contractors are frequently faced with difficult decisions as to what material prices they should use in their proposals. It is not uncommon that the lowest price received by the contractor for a certain item applies to a brand or model not listed in the closed specifications. The contractor is then faced with the dilemma of whether or not to use this lower price, and thus taking the risk with regard to whether the architect-engineer will subsequently approve the substitution. Alternatively, if the bidding firm states in its proposal that the bid amount is based on the stipulated substitutions, the contractor takes the risk that its proposal may be rejected by the bidding authority as being irregular or nonresponsive.

Although the contractor has the obligation of providing proof that a substitution meets the standards originally specified, the architect-engineer must bear the responsibility for its decisions regarding material equality. Architect-engineers must exercise care in this regard because they can be held liable for the inadequacy of approved substitutions. In spite of the troubles frequently encountered with closed specifications and or-equal clauses however, the or-equal approach to specification writing continues to be commonly used.

Additionally, there are several cases on record where a court has ruled that when the specifications provide for or-equal substitutions, the contractor is entitled to make a substitution that it can show is, in reasonable terms, equivalent to or equal to the product specified. If the owner or architect-engineer rejects the substitution of a product that is less expensive but equal, and directs the contractor to install the more expensive product specified, this has been ruled to constitute a constructive change to the contract. This entitles the contractor to recover the cost difference between the less expensive substitute and the product that it was originally directed to install, plus a reasonable profit.

Another common way to convert a proprietary specification to an open specification is to include a paragraph defining the usage of trade names, and describing the applicable substitutions policy. On public projects, there is often a “standard of quality” clause that permits substitution of equal products. In such cases, the term or approved equal is not used.

4.16.3.3 Other Material Specification Types

As discussed in the preceding sections, a closed specification has the advantage of ensuring the desired quality of material, but the disadvantage of eliminating competition among manufacturers and suppliers. An open specification will provide competition but, by permitting substitutions, introduces the possibility of materials being used that are inferior to those desired by the architect-engineer. Several specification writing methods have been developed, whose purpose is to attain the advantages and minimize the disadvantages of the open specification and closed specification concepts. Unfortunately, a completely satisfactory procedure has yet to be devised.

One of these combination-type specifications referred to in the last paragraph is called a base-bid material specification or substitute-bid specification. When this procedure is followed, materials are identified in the technical specifications of the contract documents by reference to a manufacturer's name, model number, catalog number, or other specific data. The words or equal do not appear. The intent is that only those items listed are to be used by the contractors in preparing their base bids. However, the bidding contractors may offer alternate items, either on the proposal form or as an attachment to the proposal. These alternate proposals are accompanied by full descriptions and technical data, along with a statement indicating the cost additional to, or deductive from, the base bid, if the substitution is approved.

In this method, the architect-engineer or owner does not approve or disapprove such alternates before the bid opening, and the submission of material or equipment alternatives is voluntary with the contractor. The low bidder is determined on the basis of the base bid price submitted on the proposal. After the bids have been submitted, decisions regarding whether to accept or reject any or all of the alternate proposals suggested by the bidding contractors are made by the owner. If decisions concerning approved substitutions are made prior to execution of the contract, they can readily be incorporated into the contract documents through the use of addenda (see addendum section 4.16.4). After the signing of the contract, approved substitutions can be incorporated into the contract by change order.

Another method sometimes used is for a closed specification to be written, but with a provision that proposals for substitutions can be submitted by a bidder up to a stipulated number of days prior to bid opening. Notice of any approved product substitution is circulated to all bidding contractors by addendum. After the deadline for substitute requests has passed, no further substitutions are permitted.

4.16.3.4 Standard Specifications

Standardized specifications, including both the technical and nontechnical provisions of the specifications, are used by some segments of the construction industry. These have found considerable application in highway, bridge, and utility construction projects. They are also frequently used in federal projects for both civilian and military work. These preprinted standard specifications are issued by the contracting agency and may be readily obtained by any interested party. Although they may not form a physical part of the specification booklet or project manual that is prepared by the architect-engineer for a specific project, these specifications are made a part thereof by reference.

When standardized specifications are included by reference in a project, the project manual that is produced for the individual projects consists merely of the conditions of the contract, the proposal, bond forms, and the agreement, together with any necessary modifications and special provisions regarding the standard specifications. This practice can save considerable time and effort in the preparation of project specifications, and is conducive to bidding and construction uniformity.

Similar standard specifications, sometimes used in other fields of construction, have been prepared to cover the work of the various trades, such as electricians, plumbers, and drywall applicators. A number of government, state, and city agencies utilize these standard trade specifications, augmenting them with modifications in order to make them conform to the unique aspects of a particular project under consideration. However, to date, the use of standard specifications by the construction industry has met with only limited acceptance, with the notable exceptions of highway, bridge, and utility construction, where their use is commonplace. Architect-engineers who design building construction projects, continue generally to favor the customized specification approach.

4.16.4 Addenda

Addenda (singular: addendum) are defined as any modifications to the bid documents or to the contract documents, issued by the architect-engineer during the bidding period. The bidding period is the time between the announcement of the project to contractors by means of the advertisement to bid or the invitation to bid, and the time when proposals are due to the architect-engineer and owner from the contractor. On public projects, an addendum is sometimes referred to as an amendment.

Addenda may take the form of interpretations or explanations of elements of the contract or bid documents, additions to or deletions from these documents, changes in the date when bids are due, or modifications of any other kind. Addenda can be issued only by the architect-engineer. Each addendum is defined to be a part of the contract documents, and must receive the full attention of all parties who are preparing bids for any or all portions of the project.

When addenda are issued for a project, they are typically issued in consecutively numbered series to help contractors ensure that they have received all of the addenda that have been issued. The architect-engineer, when he decides to issue an addendum, will typically distribute the addendum to all of the contractors and trade associations and others who have requested contract and bid documents from the architect-engineer.

When addenda are utilized, the architect-engineer will typically require each contractor to include a signed affirmation on his proposal that he has received and considered in his proposal all of the addenda that have been issued, by number. This provides assurance to the owner and the architect-engineer that all of the proposals from all of the bidding contractors are based on exactly the same information and that all of the bids are therefore comparable. Typically, absent this signed affirmation on the proposal on projects where addenda have been issued, the contractor's proposal will be rejected.

4.16.5 Alternates

Classically, alternates are defined as alternative materials or methods, or alternative elements of the design, which are included within the original contract documents as prepared by the architect-engineer, and sent to contractors. Alternates of this kind are referred to as owner-designated alternates, in order to distinguish them from contractor-designated alternates, which will be addressed in the next section. Alternates provide a means for the architect-engineer and owner to consider different alternatives to the original design, and then to include them in the construction contract or not, as they choose, after proposals have been received from contractors. They are a method of allowing the architect-engineer and owner to structure the contract for construction so as to attain maximum value or, perhaps, to get the contract price within the owner's budget.

Each alternate will describe a design alternative as a specific body of information and scope of work that completely defines, describes, and specifies all of the elements that are the content of the alternate. This will typically include drawings, details, and specification language, so as to set forth a definition, and to provide a clear understanding of the content of the alternate, and to clearly define all of the requirements that must be met.

When alternates are included on a project, the architect-engineer will typically note in the instructions to bidders and/or in the special conditions that contractors are required, when they submit their proposals, to submit a “base bid” for a basic, well-defined scope of work that is defined as the “base bid items.” In addition, the contractor is required to determine and submit a separate price for each alternate included in the contract documents, as an addition to or a deduction from the base bid.

Whether or not to submit a price for each alternate, is not an option for the contractor. Additionally, the architect-engineer and owner will typically note that they reserve the right to accept or reject any or all of the alternates in any combination.

Alternates are used for many different elements of work, but common examples of alternates might include to delete (or to add) a well-defined package of exterior lighting on the façade of the building and/or to portions of the site; to provide window units described and defined as “X,” rather than the window units as drawn and specified in the basic contract documents and defined to be base bid items; or to add an exterior patio area or outdoor gathering space as drawn, specified, and described and defined in this alternate, to the base bid items, which do not include these elements.

When more than one alternate is used on a project, then each alternate, whether additive to or deductive from the base bid, will be clearly delineated as a body or work. Additionally, when more than one alternate is included on a project, each alternate will be consecutively numbered.

When alternates are used on a project, when the proposals are received from contractors, the architect-engineer and owner will consider each contractor's base bid price, as well as his price for each alternate. The construction contract (as defined in the agreement, to be discussed in the following section) will then designate that the construction contract is for the base bid items and those alternates that have been accepted as listed. The contract amount will be then be the contractor's base bid amount as proposed, adjusted upward or downward by the “add” or “deduct” alternates the architect-engineer and owner have chosen to accept. The agreement form in Appendix G illustrates the incorporation of alternate proposals in the formalization of the contract.

In another variation of owner-designated alternates, public owners in bridge construction projects have sometimes provided a base design, and also alternate designs for a bridge. They have then structured the conditions of the contract and the instructions to bidders in such a way as to indicate that the contractor is required to bid only the alternative design that the contractor believes will result in the least total construction cost to the owner.

It is clear that alternates provide the architect-engineer and the owner with a considerable degree of flexibility with regard to what will be included in and what the final price will be for the contract for construction. Alternates can be of special importance to owners as a means of ensuring that they receive a bid within their limited financing or providing them with an opportunity to make the most judicious selection of a material, process, or scope of work. However, it can also be clearly seen that the use of alternates by the owner and architect-engineer complicates the bidding process, and the more alternates there are on a project, the more difficult the contractor's bidding becomes.

The award of a lump-sum contract with alternates is made to a single contractor. Normally, the low bid is determined from the algebraic sum of the base bid and any alternates accepted by the owner. Especially when there are several alternates, it has been argued that it may be possible for the owner to manipulate the alternates that are to be selected for inclusion in the contract in such a way that a preferred contractor receives the contract. To combat this possibility, it is usual for the bidding documents to state the order of acceptance of the alternates. Occasionally, the low bidder on a project with alternates is identified on the basis of the low base bid only. This then leaves the owner free to accept or reject any combination of alternates. Additionally, sometimes the conditions of the contract will indicate the order in which the owner will select alternates.

4.16.6 Contractor-Designated Alternates

Another variation in the use of alternates has sometimes been used, whereby the owner and the architect-engineer make provision for the contractor to include alternates in his proposal when none were incorporated in the original design by the owner and architect-engineer. On private projects, provision is sometimes made in the bid documents and/or the contract documents, whereby a bidding contractor is allowed to include with its proposal alternate materials or systems, and their prices, that it considers potentially attractive to the owner, in terms of price, or quality, or value. Unsolicited alternates of this kind are ordinarily not accepted by a public owner or on a private project where specific provision has not been made.

In recent years, some public owners have developed contract documents and bid documents structures wherein the owner produces a base bid design. The owner and architect-engineer state that contractor-originated design alternates are permitted; that is, a contractor is allowed to submit its own design and the corresponding price for construction, if it believes the cost will be less, and/or the value will be greater for the owner than the base design proposed by the owner. The contractor normally engages a professional consulting firm to make the design and pays the resulting cost. The contractor then submits its bid on the basis of its design alternate, the owner's base design, or both. The successful contractor is selected on the basis of project cost, owner evaluation of the alternate design, and a study of life-cycle costs.

The entire objective of the inclusion of alternates in contract documents is to produce a quality structure at the lowest cost to the owner by allowing evaluation of different design options and their prices. The use of contractor-originated design alternates is still relatively new, and questions remain concerning design quality, design liability, economy to the owner, procurement procedures, and selection of the successful bidder.

4.16.7 Agreement

The agreement is the document that is signed by the owner and the contractor that formalizes the contract between the two for the construction of the project. The agreement will list all of the elements of the contract documents as they have been defined by the architect-engineer, incorporate them by reference, and indicate that by their signatures on the agreement, both parties are binding themselves to all of the elements of content of all of the contract documents.

Additionally, the agreement will typically include the number of days allotted for completion of all of the contract requirements (which is called the duration of the project), and will often make reference to the liquidated damages amount that the contractor will be required to pay to the owner for each day past the completion date stipulated by the duration, which the contractor requires to complete all requirements of the contract documents. Reference to addenda will also frequently be included. If alternates have been included as part of the proposal process, a listing will be made on the agreement of the alternates that have been accepted, along with a designation regarding the final dollar amount of the contract.

Often, the agreement takes the form of a standard form document provided by one of the designer professional associations. Appendix G includes the agreement form authored by the AIA, Document A101–2007, “Standard Form of Agreement between Owner and Contractor Where the Basis of Payment Is a Stipulated Sum,” which is very widely used as the agreement form on building construction projects. It is noted that this example contains project duration and liquidated damage stipulations as noted earlier, as well as reference to addenda and indication of the alternates that have been accepted, along with the contract price.

4.16.8 Modifications to the Contract

The architect-engineer and owner almost always reserve for themselves the right to make changes in the contract requirements, after the agreement for the contract for construction has been signed. Usually, the conditions of the contract will state that the architect-engineer and owner reserve this right, that the contractor is required to implement such changes as may be properly requested, and that the contract sum and/or the contract time will be adjusted accordingly.

The standard form AIA General Conditions of the Contract for Construction, AIA Document A201, which is very commonly used on building construction projects, provide that such changes can be by a modification to the contract. AIA Document A201–2007 is included in Appendix D.

In AIA Document A201–2007, modifications to the contract are defined as:

  1. A written amendment signed by both parties.
  2. A change order.
  3. A construction change directive.
  4. A written order for a minor change in the work issued by the architect.

The written amendment signed by both parties is self-explanatory. A change to the contract is proposed by one party or the other in written form, and then is agreed to, and then is signed by both parties to the contract. The change order, construction change directive, and written order for a minor change are fully defined and described in the general conditions and/or in the modifications to the general conditions. A basic definition and summary of each will be provided here.

A change order is a written instrument prepared by the architect and signed by the owner, architect, and contractor, directing a specific change in the work and stating their agreement regarding the exact nature of the change, and the change, if any, in contract sum and/or contract time. Change orders on a project are usually issued in consecutively numbered series.

A construction change directive is a written order prepared by the architect, and signed by the owner and the architect, directing the contractor to effect a change in the work prior to agreement with the contractor regarding adjustment, if any, in contract sum or contract time, or both. The general conditions contain additional language that describes the manner of determining the change in contract sum and/or contract time, and noting that the contractor is obligated to proceed immediately with the change in the work as directed, and noting the contract sum and/or time will be adjusted at a later time. When the contractor subsequently signs the construction change directive, his signature indicates his agreement, including the adjusted contract sum and/or contract time. Additionally, when the contractor signs the construction change directive indicating his agreement, the document is immediately recorded as a change order. There is additional language in the general conditions regarding how resolution will be achieved, and describing the rights of the parties if the contractor and the architect and owner should disagree on the manner of determining compensation or credit for the change and/or the amount of the change in contract sum and/or contract time.

With regard to minor changes, the general conditions stipulate that the architect has the authority to order minor changes in the work that do not involve changes in the contract sum or extension of the contract time and are not inconsistent with the contract documents. The general conditions provide that such changes will be effected by means of a written order signed by the architect, which is binding upon the owner and the contractor.

4.17 Summary and Conclusions

While the terms contract and contractor are commonly used in the singular form to describe the basis on which construction projects are performed and the person who performs construction contracts, as has been discussed here, there are a number of documents that together define the construction contract. Additionally, there are a number of people involved in the process of designing and constructing a project, and each has a role, a specific set of duties, and a defined series of responsibilities that are likewise defined by a variety of contracts.

Chapter 4 Review Questions

  1. Define a closed specification, and provide a synonym for the term.
  2. Define the term alternate, and state two different forms of alternates.
  3. Discuss the objection that has been held by professional associations of architects and engineers against the use of competitive bids as the basis of selection of architects-engineers to design construction projects.
  4. State the full name of the standard form of the general conditions that is frequently used in building construction contracts.
  5. Define the project manual, and list its contents.
  6. Describe the basic services provided to an owner by an architect-engineer firm.
  7. Define MasterFormat, describe its source, and discuss its use in construction contracting.
  8. List and define the four forms of modifications to the contract typically provided for in the conditions of contract for a building construction project.
  9. Define the term contingency reserve, and describe its use.
  10. Which component of the contract documents actually formalizes the contract and is signed by the owner and by the contractor?
  11. Define the term addendum, and contrast an addendum with a change order.
  12. Define the term base bid, and discuss its usage.
  13. Describe the difficulties that may be caused by the use of an “or–equal” clause in a set of specifications.
  14. Discuss the significance of the Brooks Act.
  15. State the name of the method that must, by law, be used on most public construction projects to inform contractors that a project has been designed and to let contractors know that the owner and architect-engineer are soliciting bids from contractors.
..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset