Subject Index by paragraph

acceleration, 5.17, 8.10

access to site, 5.35.7, 6.4, 6.33

adjudication, 11.811.19, 11.29

advance payment bond, 2.4, 3.21, 8.5, 8.28

advance payments, 3.21, 8.58.6, 8.28

antiquities, 5.24

arbitration, 11.2011.36

architect

authority, 1.25

consultant switch, 1.171.18

as employer’s agent, 1.14, 1.24, 1.25, 2.13

liability, 1.16, 1.17, 1.18, 1.30

novation, 1.16, 1.23

provision of information, 1.23

relations with contractor, 1.141.17, 1.25

relations with employer, 1.141.15, 1.191.21, 1.241.25

role, 1.141.15

terms of engagement, 1.211.24

as-built information, 3.12, 5.43, 6.10

assignment of contractual rights, 3.473.49

bills of quantities, 3.8

bonds, 2.4, 3.21

advance payment, 2.4, 3.21, 8.5, 8.28

performance, 3.21, 3.46

retention, 2.4, 3.21, 8.26

building information modelling (BIM), 3.17

Building Regulations, 4.20

CDM Regulations, 2.22, 3.18, 4.284.32, 10.12

changes, 6.306.36

affecting completion date, 5.16

affecting construction phase plan, 4.31

to comply with planning requirements, 3.9

contractor’s obligations, 4.3

to contractor’s proposals, 4.26, 6.196.20

discrepancy from requirements, 3.363.37

to employer’s requirements, 3.6, 3.33, 6.306.34

omission of work, 5.265.27, 5.28, 7.14

relevant events, 6.36

site boundary, 3.32

in statutory requirements, 4.26, 5.24

valuation, 3.15, 5.16, 7.67.16, 7.23 (see also contract sum analysis)

charges and fees, 4.22

‘chose in action’, 3.48

client see employer

collaborative working, 2.17, 4.2

collateral warranties, 3.51, 3.583.63, 6.47

commencement date, 5.15.7

communication methods, 3.25, 6.236.24

completion contracts, 10.20, 10.22

completion date, 5.15.2, 5.125.15

acceleration, 5.17

affect of delays, 5.32

affect of omission of work, 5.265.27, 5.28

changes affecting, 5.16

failure to meet, 5.505.51

confidential information, 3.45

consequential losses, 4.8

Construction (Design and Management) (CDM) Regulations, 2.22, 3.18, 4.284.32, 10.12

Construction Industry Council (CIC), 1.23, 3.17

construction phase plan, 3.19, 4.31, 6.5

Construction Supply Chain Payment Charter 2014, 2.18

consultant switch, 1.171.18

consumer contracts, 2.20

Consumer Rights Act 2015, 5.2

contract administration, 2.12, 6.1

contract documents, 3.13.63

copies of, 3.44

custody and control, 3.433.45

discrepancies and errors, 3.313.38

interpretations and definitions, 3.243.27

priority, 3.283.30

sub-contracts, 3.223.23

contract execution, 1.12, 3.2, 3.4

contract sum, 7.1

adjustments, 2.14, 6.41, 7.27.5, 8.25, 8.31, 8.40

fluctuations provision, 5.8, 5.51, 7.387.41, 8.10

two-stage tendering, 1.10, 1.12

contract sum analysis, 2.14, 3.15, 7.147.16

contractor

access to site, 5.35.7, 6.33

‘best endeavours’ to prevent delay, 5.31

compliance with employer’s instructions, 6.266.28

directly engaged by employer, 6.556.56

duty to proceed ‘regularly and diligently’, 5.8, 10.1310.14

estimates for changes, 5.16, 7.77.11, 7.23

information to be provided by, 6.96.11

insolvency, 10.1510.19

interim payment applications, 7.24, 8.7, 8.30

liability, 1.281.29, 1.31, 2.10, 3.563.57, 4.44.8

losses and/or expenses, 7.177.37, 8.24

notice of delay, 5.215.22

obligations, 4.14.32

relations with architect, 1.141.17, 1.25

right of suspension, 8.37

sequencing of work, 5.8

contractor’s design documents, 3.12

contractor’s obligations, 4.3

copies for employer, 3.44, 6.13

discrepancies, 3.35

submission procedure, 6.126.20

contractor’s programme, 3.12, 5.95.11, 5.30 (see also construction phase plan)

contractor’s proposals, 2.82.9, 3.133.14

changes, 4.26, 6.196.20

custody and control of documents, 3.433.45

discrepancies, 2.11, 3.35

divergence from employer’s requirements, 3.393.41

divergence from statutory requirements, 3.42, 4.234.25

form of submission, 3.11, 3.13

Contracts (Rights of Third Parties) Act 1999, 3.26, 3.51, 3.523.54

contractual rights, 3.473.49

cost-saving measures, 7.12

covenants, 3.10

custody of documents, 3.43

date for commencement, 5.15.7

date for completion see completion date

date of possession by the contractor, 5.15.7

daywork, valuation, 7.157.16

Defective Premises Act 1972, 1.32, 4.7

defective work, 6.386.44

acceptance of, 6.41, 6.60, 8.31

appearing after rectification period, 6.586.59, 6.62

exclusion from interim payments, 8.148.15, 8.348.35

making good, 6.576.63

removal of, 6.396.40

schedule, 5.48, 6.586.59

defects liability period see rectification period

definitions in documentation, 3.243.25

delays (see also extensions of time; relevant events)

caused by employer, 5.13, 5.185.19, 5.24, 7.29

concurrent events, 5.335.34

mixed responsibility, 5.34

notice of delay, 5.215.22

permissions and approvals, 4.25, 5.24

possession by contractor, 5.55.7

design

contractor’s see contractor’s design documents

employer’s outline, 3.7, 3.33, 4.3

Design and Build Contract (DB16)

changes from previous edition, 2.222.23

comparison with SBC16, 2.21

key features, 2.62.18

when to use, 2.19

design defects, 1.29, 1.31, 4.44.5, 4.8

design liability, 1.261.32, 2.10

design submission procedure, 6.126.20

development permissions, 3.9, 4.20, 4.25, 5.24

discrepancies (documentation), 2.11, 3.313.38

dispute notice, 8.448.45

dispute resolution, 11.111.36

disruption of work, 7.30, 7.36 (see also suspension of work)

domestic clients, 2.20, 4.7

drawings see contractor’s design documents

dwellings, 1.32, 2.20, 4.7

easements, 3.10

Emden formula, 7.35

employer

acceptance of contractor’s proposals, 4.4

delays caused by, 5.13, 5.185.19, 5.24, 7.29

indemnity, 9.29.3

information to be provided by, 6.76.8

insolvency, 10.29

instructions, 6.216.29

non-payment by, 8.368.38, 10.2710.28

obligations, 6.76.8

outline design, 3.7, 3.33, 4.3

payment notices, 8.29

relations with architect, 1.141.15, 1.191.21, 1.241.25

response to design documents, 6.166.17

use of site during works, 5.4

employer’s agent, 2.13, 6.2

access to site, 6.4

architect as, 1.14, 1.24, 1.25, 2.13

Employer’s Liability (Compulsory Insurance) Act 1969, 9.6

employer’s requirements, 2.82.9 (see also named sub-contractors)

architect’s role, 1.14

changes, 3.6, 3.33, 6.306.34

custody and control, 3.433.45

discrepancies, 2.11, 3.14, 3.313.38

divergence from statutory requirements, 4.234.25, 4.27

documentation, 3.53.12

environmental performance measures, 7.13

estimates for changes see valuation of changes

extensions of time, 5.185.34

assessment, 5.295.34

following non-completion notice, 5.57

for neutral events, 5.19

procedure, 5.205.28

resulting from changes, 5.16

fair payment provisions, 2.18

fees and charges, 4.22

final payment, 8.408.46

final statement, 8.408.46, 10.24

fire safety, 9.289.29

‘fitness for purpose’, 1.291.30, 4.64.7, 4.9

‘fixed’ price, 7.38

fluctuations provision, 5.8, 5.51, 7.387.41, 8.10

framework agreements, 1.9, 2.3

Freedom of Information Act 2000, 2.18

‘guaranteed’ price, 7.38

guarantees, 3.46

handover meeting, 5.49

health and safety documents, 3.183.20

health and safety file, 3.20, 5.43, 6.9

health and safety legislation, 4.284.32

Housing Grants, Construction and Regeneration Act (HGCRA) 1996, 2.15, 2.18, 8.29

contractor’s right of suspension, 8.37

dispute resolution, 11.8, 11.1611.17

payment provisions, 8.1

Hudson formula, 7.35

indemnity, employer’s, 9.29.3

industrial action, 5.24

insolvency

contractor, 10.1510.19

employer, 10.29

inspections, 6.37, 6.38

instructions, employer’s, 6.216.29

insurance, 9.19.31

contractors engaged by employer, 6.56

insurance of the works, 9.149.24

partial possession, 5.37

third parties, 9.19.31

interest on overdue payments, 8.36

interim payments, 8.38.4 (see also payments to the contractor)

applications, 7.24, 8.7, 8.30

ascertainment of amounts due, 8.88.15, 8.258.27

due date, 8.29

interpretation of contract, 3.243.27

Joint Contracts Tribunal (JCT)

collateral warranties, 2.4

Design and Build Guide, DB/G, 2.5

Design and Build Sub-Contract, 6.46

forms of contract, 1.7, 2.19

Pre-Construction Services Agreement (General Contractor) (PCSA), 1.11

SBC16, 2.19, 2.21

Joint Fire Code, 9.289.29

Late Payment of Commercial Debts (Interest) Act 1998, 8.36

Late Payment of Commercial Debts Regulations 2013, 2.18

LDEDCA see Local Democracy, Economic Development and Construction Act (LDEDCA) 2009

liquidated damages, 5.12, 5.525.58

in case of partial possession, 5.37

deduction from payments, 5.505.51, 5.56

employer’s notice to claim, 5.545.55

repaid to contractor, 5.575.58

‘listed items’, 8.228.23

litigation, 11.3011.36

local authorities, 2.22

as employer, 2.2, 3.21

termination of contractor’s employment, 10.7, 10.32

work in pursuance of statutory duties, 5.24

Local Democracy, Economic Development and Construction Act (LDEDCA) 2009

dispute resolution, 11.8

payment provisions, 2.15, 8.1, 8.14, 8.24

losses and expenses

reimbursement, 7.177.37, 8.24

relevant matters, 7.18, 7.297.30

valuation, 7.237.28, 7.317.32

making good defects, 6.576.63

materials and goods

‘listed items’, 8.228.23

ownership, 6.46, 8.19

payments to the contractor, 2.4, 3.21, 8.168.21

price adjustment, 5.8, 5.51, 7.387.41, 8.10

removal from site, 6.46, 8.19

removal of defective work, 6.396.40

samples, 6.11

shortages, 5.24

standards and quality, 1.281.29, 4.64.7, 4.114.16, 6.37

substitution, 4.124.16

mediation, 11.511.7

named sub-contractors, 6.496.54

contract documents, 3.23

contractor’s responsibility, 2.16

delays caused by, 5.24

itemised in contract sum analysis, 3.16

termination of employment, 10.3410.36

neutral events, 5.19, 5.24, 10.6

non-completion notice, 5.50, 5.57

non-standard terms, 3.29

novation, 1.16, 1.18, 1.23

occupation by employer, 5.355.41

omission of work, 5.265.27, 5.28, 7.14

opening up completed work, 6.38, 6.42

operation and maintenance manual, 6.10

outline design, 3.7, 3.33, 4.3

partial possession, 5.355.38

partnering provisions, 1.9, 2.17

pay less notice, 5.55, 8.30, 8.31, 8.35

payment applications, 7.24, 8.7

payment notices, 8.29

payments to the contractor, 2.14, 8.1 (see also contract sum analysis)

ascertainment of amounts due, 8.88.15, 8.258.27

deductions from amounts due, 8.14, 8.308.32

employer’s obligation to pay, 8.338.35

fair payment provisions, 2.18

final date for, 2.18

final payment, 8.408.46

following termination of employment, 10.23

non-payment by employer, 8.368.38, 10.2710.28

partial possession, 5.37

practical completion, 8.398.40

procedure, 8.298.32

retention sums, 5.37, 8.268.27

withholding, 8.15, 8.30

performance bonds, 3.21, 3.46

performance indicators, 2.17

performance requirements, 3.7 (see also standards and quality)

phased completion see sectional completion

planning permission, 3.9, 4.20, 4.26, 5.24

possession by employer, 5.355.41

possession of the site by contractor, 5.15.7

postponement of work, 5.55.7

practical completion, 5.425.49

information required, 3.12, 3.20, 5.43

partial possession, 5.36

payment on, 8.398.40

procedure, 5.475.49

use or occupation before, 5.395.41

pre-construction information, 3.19

price adjustment see fluctuations provision

principal contractor, 3.18, 4.294.30, 6.5, 6.9

principal designer, 3.18, 4.284.29, 6.6

priority of contract documents, 3.283.30

‘privity of contract’, 3.51

professional indemnity insurance (PII), 3.56, 4.10, 9.27

programme, contractor’s, 3.12, 5.95.11, 5.30 (see also construction phase plan)

protocols, 3.17

provisional sums, 3.14, 4.22, 7.6

public bodies, 2.222.23

as employer, 2.2, 3.21

payment provisions, 2.18

termination of contractor’s employment, 10.7, 10.32

Public Contracts Regulations 2015, 2.18

quality and standards, 1.281.29, 4.64.7, 4.114.16, 6.37

‘reasonable skill and care’, 1.29

rectification period, 5.36, 5.45, 6.58, 6.626.63

relevant events, 5.24, 6.36

after completion date, 5.27

change in site boundary, 3.32

notice by contractor, 5.22

relevant matters, 7.18, 7.24, 7.297.30

repudiation, 10.3, 10.5

restrictions on documentation, 3.45

retention bond, 2.4, 3.21, 8.26

retention of title clause, 8.168.17

retention sums, 5.37, 8.268.27

RIBA

Contractor’s Design Services Schedule, 1.22

Standard Agreement 2010 (2012 revision): Architect, 1.22

Sale and Supply of Goods Act 1994, 1.27

Sale of Goods Act 1979, 1.27

samples, 6.11

SBC16, 2.19, 2.21

sectional completion, 5.1, 5.20, 5.51 (see also partial possession)

sequencing of work, 5.8

single-stage tendering, 1.13

site access, 5.35.7, 6.4, 6.33

site boundary, 3.32, 6.7

site constraints, 3.10

site investigation, 3.10

site manager, 6.3

site meeting minutes, 6.25

‘snagging’ lists, 5.48

special terms, 3.29

specialist contractors, 1.11

specifications, 3.7

stage payments, 8.3, 8.4, 8.9, 8.13, 8.15

standards and quality, 1.281.29, 4.64.7, 4.114.16, 6.37 (see also workmanship)

start date, 5.15.7

statutory requirements, 4.184.27

changes in, 4.26, 5.24

delays in obtaining permissions, 5.24

divergence from, 3.42, 4.234.25

statutory undertaker’s work, 5.24, 6.55

sub-contractors, 2.16 (see also named sub-contractors)

contractor’s responsibility for, 4.17

documentation, 3.223.23

employer’s consent, 6.45

form of contract, 6.46

materials and goods, 8.18, 8.20

third party rights and/or warranties, 3.623.63, 6.47

substitution, 4.124.16

supplemental provisions, 2.3, 2.17, 2.18, 3.3

contractor’s estimates, 7.77.11

contractor’s loss and/or expense, 7.237.28

contractor’s obligations, 4.2

named sub-contractors, 2.16

Supply of Goods and Services Act 1982, 1.28, 5.2

suspension of work (see also disruption of work)

contractor’s costs and expenses, 8.24

delays in statutory approvals, 4.25

due to changes in requirements, 6.34

employer’s failure to provide instructions, etc., 6.7

grounds for termination, 10.10, 10.26, 10.31

non-payment by employer, 8.37

tender process, 1.101.13

termination of contractor’s employment, 10.410.25

initiated by contractor, 10.2610.30

initiated by employer, 10.710.25

named sub-contractors, 10.3410.36

terms of engagement, architect’s, 1.211.24

terrorism cover (insurance), 9.259.26

testing, 6.38, 6.42

third parties

indemnity and insurance, 9.19.31

rights, 3.26, 3.503.63, 6.47

‘time is of the essence’, 5.14

two-stage tendering, 1.101.12

Unfair Contract Terms Act 1977, 1.27

Unfair Terms in Consumer Contracts Regulations 1999, 2.20

valuation of changes, 3.15, 5.16, 7.67.16, 7.23 (see also contract sum analysis)

valuation of design work, 3.16

valuation of loss and/or expense, 7.247.28, 7.317.32

valuation rules, 7.147.16

value-improvement measures, 7.12

VAT, 7.4

warranties, 3.51, 3.583.63, 6.47

weather, adverse, 5.24

working hours, 6.33

workmanship, 4.7, 4.11, 4.17, 6.11, 6.37

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset